Notice of Request Under Blanket Authorization: Kern River Gas
Transmission Company
Take notice that on December 10, 2018, Kern River Gas Transmission
Company (Kern River), 2755 East Cottonwood Parkway, Suite 300, Salt
Lake City, Utah 84121, filed in Docket No. CP19-23-000 a prior notice
request pursuant to Kern River's blanket authority granted on January
24, 1990, in Docket No. CP89-2048-000 and sections 157.205 and 157.211
of the Commission's regulations under the Natural Gas Act for
authorization to construct and operate a new delivery point, the
Eaglecrest meter station in Kern County, California, to serve E&B
Natural Resources Management Corporation, all as more fully set forth
in the application which is on file with the Commission and open to
public inspection. The filing may also be viewed on the web at http://www.ferc.gov using the ``eLibrary'' link. Enter the docket number
excluding the last three digits in the docket number field to access
the document. For assistance, please contact FERC Online Support at
[email protected] or toll free at (866) 208-3676, or TTY,
contact (202) 502-8659.
Any questions concerning this application may be directed to
Michael T. Loeffler, Senior Director, Certificates for Kern River, 1111
South 103rd Street, Omaha, Nebraska 68124, at (402) 398-7103.
Kern River states that, pursuant to Section 284.13(e) of the
Commission's regulations, it is advising the Commission that it has
provided the required notice to bypass to both Pacific Gas and Electric
Company, the local distribution company that is currently providing
service to E&B Natural Resources Management Corporation, and to
California Public Utilities Commission, the appropriate regulatory
agency, by sending copies of this application.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the
[[Page 65658]]
Secretary of the Commission. Environmental commenters will be placed on
the Commission's environmental mailing list, will receive copies of the
environmental documents, and will be notified of meetings associated
with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of
filed documents on all other parties. However, the non-party commenter
will not receive copies of all documents filed by other parties or
issued by the Commission (except for the mailing of environmental
documents issued by the Commission) and will not have the right to seek
court review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at http://www.ferc.gov. Persons unable to file electronically should
submit an original and 5 copies of the protest or intervention to the
Federal Energy Regulatory Commission, 888 First Street NE, Washington,
DC 20426.
Dated: December 14, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-27731 Filed 12-20-18; 8:45 am]