DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2337-000]


PacifiCorp; Notice of Authorization for Continued Project 
Operation

    On December 30, 2016, PacifiCorp, licensee for the Prospect No. 3 
Hydroelectric Project, filed an Application for a New License pursuant 
to the Federal Power Act (FPA) and the Commission's regulations 
thereunder. The Prospect No. Hydroelectric Project is located on the 
South Fork Rogue River, in Jackson County, Oregon.
    The license for Project No. 2337 was issued for a period ending 
December 31, 2018. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), 
requires the Commission, at the expiration of a license term, to issue 
from year-to-year an annual license to the then licensee under the 
terms and conditions of the prior license until a new license is 
issued, or the project is otherwise disposed of as provided in section 
15 or any other applicable section of the FPA. If the project's prior 
license waived the applicability of section 15 of the FPA, then, based 
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), 
and as set forth at 18 CFR 16.21(a), if the licensee of such project 
has filed an application for a subsequent license, the licensee may 
continue to operate the project in accordance with the terms and 
conditions of the license after the minor or minor part license 
expires, until the Commission acts on its application. If the licensee 
of such a project has not filed an application for a subsequent 
license, then it may be required, pursuant to 18 CFR 16.21(b), to 
continue project operations until the Commission issues someone else a 
license for the project or otherwise orders disposition of the project.
    If the project is subject to section 15 of the FPA, notice is 
hereby given that an annual license for Project No. 2337 is issued to 
the licensee for a period effective January 1, 2019 through December 
31, 2019, or until the issuance of a new license for the project or 
other disposition under the FPA, whichever comes first. If issuance of 
a new license (or other disposition) does not take place on or before 
December 31, 2019, notice is hereby given that, pursuant to 18 CFR 
16.18(c), an annual license under section 15(a)(1) of the FPA is 
renewed automatically without further order or notice by the 
Commission, unless the Commission orders otherwise.
    If the project is not subject to section 15 of the FPA, notice is 
hereby given that the licensee, PacifiCorp, is authorized to continue 
operation of the Prospect No. 3 Hydroelectric Project, until such time 
as the Commission acts on its application for a subsequent license.

    Dated: December 12, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-27312 Filed 12-17-18; 8:45 am]
 BILLING CODE 6717-01-P