DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP18-542-000]
KO Transmission Company; Notice of Amendment
Take notice that on August 24, 2018, KO Transmission Company (KOT),
139 East 4th Street, Cincinnati, Ohio, filed an application under
section 7(c) of the Natural Gas Act and Part 157 of the Commission's
regulations requesting authorization to amend its Certificate of Public
Convenience and Necessity issued on April 22, 1998, in Docket No. CP97-
720-000 \1\ in order to properly reflect the capacity acquired in that
proceeding. KOT further requests authorization to amend its
certificated capacity north of the Foster Station to reflect current
operating capacity, all as more fully set forth in the request which is
on file with the Commission and opens to public inspection. The filing
may be viewed on the web at http://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC at [email protected] or call toll-free, (886) 208-3676 or
TYY, (202) 502-8659.
---------------------------------------------------------------------------
\1\ KO Transmission Company, 83 FERC ] 62,066 (1998).
---------------------------------------------------------------------------
Any questions regarding the proposed amendment should be directed
to Lance Stotts, Administrator, KO Transmission Company, 4720 Piedmont
Row Drive, Room 864, Charlotte, North Carolina 28210; telephone
(704)731-4360; email energy.com">Lance.Stotts2@duke-energy.com.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
complete its environmental analysis (EA) and place it into the
Commission's public record (eLibrary) for this proceeding, or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
[[Page 46159]]
milestones, the anticipated date for the Commission staff's issuance of
the EA for this proposal. The filing of the EA in the Commission's
public record for this proceeding or the issuance of a Notice of
Schedule will serve to notify federal and state agencies of the timing
for the completion of all necessary reviews, and the subsequent need to
complete all federal authorizations within 90 days of the date of
issuance of the Commission staff's EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below, file with the Federal Energy
Regulatory Commission, 888 First Street NE, Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 5 copies of filings made with the Commission and must mail a
copy to the applicant and to every other party in the proceeding. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at http://www.ferc.gov. Persons unable to file electronically should
submit an original and 5 copies of the protest or intervention to the
Federal Energy Regulatory Commission, 888 First Street NE, Washington,
DC 20426.
Comment Date: 5 p.m., September 27, 2018.
Dated: September 6, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-19807 Filed 9-11-18; 8:45 am]