[Federal Register Volume 82, Number 143 (Thursday, July 27, 2017)]
[Notices]
[Pages 34992-34993]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-15754]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 52-025 and 52-026; NRC-2008-0252]
Southern Nuclear Operating Company, Inc., Vogtle Electric
Generating Plant, Units 3 and 4; Inspections, Tests, Analyses, and
Acceptance Criteria
AGENCY: Nuclear Regulatory Commission.
ACTION: Determination of the successful completion of inspections,
tests, and analyses.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has determined
that the inspections, tests, and analyses have been successfully
completed, and that the specified acceptance criteria are met for the
Vogtle Electric Generating Plant (VEGP), Units 3 and 4.
DATES: The determination of the successful completion of inspections,
tests, and analyses for VEGP, Units 3 and 4 is effective July 27, 2017.
ADDRESSES: Please refer to Docket ID NRC-2008-0252 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2008-0252. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to [email protected]. The
ADAMS accession number for each document referenced (if it is available
in ADAMS) is provided the first time that it is mentioned in this
document.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Chandu Patel, Office of New Reactors,
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001;
telephone: 301-415-3025; email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Licensee Notification of Completion of ITAAC
Southern Nuclear Operating Company, Inc. (SNC), Georgia Power
Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC., MEAG
Power SPVJ, LLC., MEAG Power SPVP, LLC., and the City of Dalton,
Georgia, (hereafter called the licensee) has submitted inspections,
tests, analyses, and acceptance criteria (ITAAC) closure notifications
(ICNs) under Sec. 52.99(c)(1) of title 10 of the Code of Federal
Regulations (10 CFR), informing the NRC that the licensee has
successfully performed the required inspections, tests, and analyses,
and that the acceptance criteria are met for:
VEGP, Unit 3 ITAAC
2.1.01.06.ii (7), 2.1.03.09a.i (81), 2.2.01.06d.i (105), 2.2.03.09b
(204), 2.3.05.02.ii (341), 2.5.02.07b (535), and 3.2.00.01c.i (741)
VEGP, Unit 4 ITAAC
2.1.01.06.ii (7), 2.1.03.09a.i (81), 2.2.01.06d.i (105), 2.2.03.09b
(204), 2.3.05.02.ii (341), 2.5.02.07b (535), and 3.2.00.01c.i (741)
The ITAAC for VEGP, Unit 3 are in Appendix C of the VEGP, Unit 3
combined license (ADAMS Accession No. ML14100A106). The ITAAC for VEGP,
Unit 4 are in Appendix C of VEGP, Unit 4 combined license (ADAMS
Accession No. ML14100A135).
II. NRC Staff Determination of Completion of ITAAC
The NRC staff has determined that the specified inspections, tests,
and analyses have been successfully completed, and that the specified
acceptance criteria are met. The documentation of the NRC staff's
determination is in the ITAAC Closure Verification Evaluation Form
(VEF) for each ITAAC. The VEF is a form that represents the NRC staff's
structured process for reviewing ICNs. Each ICN presents a narrative
description of how the ITAAC was completed. The NRC's ICN review
process involves a determination on whether, among other things: (1)
each ICN provides sufficient information, including a summary of the
methodology used to perform the ITAAC, to demonstrate that the
inspections, tests, and analyses have been successfully completed; (2)
each ICN provides sufficient information to demonstrate that the
acceptance criteria of the ITAAC are met; and (3) any NRC inspections
for the ITAAC have been completed and any ITAAC findings associated
with that ITAAC have been closed.
The NRC staff's determination of the successful completion of these
ITAAC is based on information available at this time and is subject to
the licensee's ability to maintain the condition that the acceptance
criteria are met. If the NRC staff receives new information that
suggests the NRC staff's determination on any of these ITAAC is
incorrect, then the NRC staff will determine whether to reopen that
ITAAC (including
[[Page 34993]]
withdrawing the NRC staff's determination on that ITAAC). The NRC
staff's determination will be used to support a subsequent finding,
pursuant to 10 CFR 52.103(g), at the end of construction that all
acceptance criteria in the combined license are met. The ITAAC closure
process is not finalized for these ITAAC until the NRC makes an
affirmative finding under 10 CFR 52.103(g). Any future updates to the
status of these ITAAC will be reflected on the NRC's Web site at http://www.nrc.gov/reactors/new-reactors/oversight/itaac.html.
This notice fulfills the NRC staff's obligations under 10 CFR
52.99(e)(1) to publish a notice in the Federal Register of the NRC
staff's determination of the successful completion of inspections,
tests and analyses.
Vogtle Electric Generating Plant Unit 3, Docket No. 5200025
A complete list of the review status for VEGP, Unit 3 ITAAC,
including the submission date and ADAMS Accession Number for each ICN
received, the ADAMS Accession Number for each VEF, and the ADAMS
Accession Numbers for the inspection reports associated with these
specific ITAAC, can be found on the NRC's Web site at http://www.nrc.gov/reactors/new-reactors/new-licensing-files/vog3-icnsr.pdf.
Vogtle Electric Generating Plant Unit 4, Docket No. 5200026
A complete list of the review status for VEGP Unit 4 ITAAC,
including the submission date and ADAMS Accession Number for each ICN
received, the ADAMS Accession Number for each VEF, and the ADAMS
Accession Numbers for the inspection reports associated with these
specific ITAAC, can be found on the NRC's Web site at http://www.nrc.gov/reactors/new-reactors/new-licensing-files/vog4-icnsr.pdf.
Dated at Rockville, Maryland, this 18th day of July 2017.
For the Nuclear Regulatory Commission.
Jennifer Dixon-Herrity,
Chief, Licensing Branch 4, Division of New Reactor Licensing, Office of
New Reactors.
[FR Doc. 2017-15754 Filed 7-26-17; 8:45 am]
BILLING CODE 7590-01-P