[Federal Register Volume 82, Number 38 (Tuesday, February 28, 2017)]
[Notices]
[Page 12121]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2017-03991]
-----------------------------------------------------------------------
DEPARTMENT OF THE INTERIOR
National Park Service
[NPS-AKR-GAAR-22618; PR.RGAAR1502.00.1]
Extension of Time for Preparation of an Environmental and
Economic Analysis, Gates of the Arctic National Preserve
AGENCY: National Park Service, Interior.
ACTION: Notice of extension of time.
-----------------------------------------------------------------------
SUMMARY: The time for completion of the draft and final environmental
and economic analysis is being extended.
DATES: The date for completion of the draft environmental and economic
analysis (EEA) is extended to March 29, 2019, and completion of the
final EEA is extended to December 30, 2019.
ADDRESSES: Superintendent, Gates of the Arctic National Park and
Preserve, 4175 Geist Road, Fairbanks, Alaska 99709.
FOR FURTHER INFORMATION CONTACT: Greg Dudgeon, Superintendent, Gates of
the Arctic National Park and Preserve, 4175 Geist Road, Fairbanks,
Alaska 99709. Telephone: 907-457-5752. Email: [email protected].
SUPPLEMENTARY INFORMATION: An application for a right-of-way (ROW)
across the Western (Kobuk River) unit of Gates of the Arctic National
Preserve has been submitted by the Alaska Industrial Development and
Export Authority (AIDEA) to the National Park Service, pursuant to
section 201(4) of the Alaska National Interest Lands Conservation Act
(ANILCA), 16 U.S.C. 410hh(4). That section requires the preparation of
an environmental and economic analysis (EEA), and that the final EEA be
completed within one year and the draft EEA be completed within nine
months of the receipt of an application for such ROW. That analysis,
however, is subject to the procedures set out in 16 U.S.C. 3164(e) and
implemented by 43 CFR 36.6, which allow for extension of this time for
completion of the draft and final EEA if additional time is determined
to be necessary.
An application for a ROW was submitted by the AIDEA on November 25,
2015. The application was determined to be sufficient after submission
of supplemental information on June 30, 2016, which was deemed the
filing date of the application in accordance with 43 CFR 36.5(d)(1).
The draft EEA is currently due nine months from that filing date, on
March 30, 2017. The final EEA is currently due one year from that date,
on June 30, 2017.
Although the segment of the proposed road within the National
Preserve would be only 17 to 25 miles, the entire length of the
proposed road would be 221 miles. For the road to be constructed,
authorizations are also needed from other federal agencies. These
include the U.S. Army Corps of Engineers (wetlands permit) and the
Bureau of Land Management (right of way). An environmental impact
statement (EIS) is required for those authorizations, and is expected
to take several years to complete. In order to properly coordinate the
permitting actions among the several agencies, and to minimize the
chance of conflicting route determinations for the road, it is
necessary to have the timing of the EEA be in general harmony with that
of the EIS. For that reason, additional time is needed for the
completion of the EEA.
Accordingly, the date for completion of the draft EEA is extended
to March 29, 2019, and the date for completion of the final EEA is
extended to December 30, 2019.
Dated: February 24, 2017.
Herbert C. Frost,
Regional Director, Alaska Region.
[FR Doc. 2017-03991 Filed 2-27-17; 8:45 am]
BILLING CODE 4312-52-P