[Federal Register Volume 81, Number 204 (Friday, October 21, 2016)]
[Notices]
[Pages 72838-72841]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-25503]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-457; NRC-2016-0215]
Exelon Generation Company, LLC; Braidwood Station, Unit 2
AGENCY: Nuclear Regulatory Commission.
ACTION: License amendment application; opportunity to comment, request
a hearing, and petition for leave to intervene.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is considering
issuance of an amendment to Renewed Facility Operating License No. NPF-
77, issued to Exelon Generation Company, LLC, for operation of
Braidwood Station, Unit 2, located in Will County, Illinois. The
proposed amendment would allow a one-time extension from 72 hours to
200 hours of the technical specification (TS) completion time
associated with the 2A service water (SX) pump in support of
maintenance activities.
DATES: Submit comments by November 21, 2016. Requests for a hearing or
petition for leave to intervene must be filed by December 20, 2016.
ADDRESSES: You may submit comments by any of the following methods:
Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2016-0215. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
Mail comments to: Cindy Bladey, Office of Administration,
Mail Stop: OWFN-12-H08, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001.
For additional direction on obtaining information and submitting
comments, see ``Obtaining Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Joel S. Wiebe, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC
20555-0001; telephone: 301-415-6606, email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Obtaining Information and Submitting Comments
A. Obtaining Information
Please refer to Docket ID NRC-2016-0215 when contacting the NRC
about the availability of information for this action. You may obtain
publicly-available information related to this action by any of the
following methods:
Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2016-0215.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to [email protected]. The
application for license amendment dated September 30, 2016 is available
in ADAMS under Accession No. ML16274A474.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC-2016-0215 in your comment submission.
The NRC cautions you not to include identifying or contact
information that you do not want to be publicly disclosed in your
comment submission. The NRC will post all comment submissions at http://www.regulations.gov as well as enter the comment submissions into
ADAMS. The NRC does not routinely edit comment submissions to remove
identifying or contact information.
If you are requesting or aggregating comments from other persons
for submission to the NRC, then you should inform those persons not to
include identifying or contact information that they do not want to be
publicly disclosed in their comment submission. Your request should
state that the NRC does not routinely edit comment submissions to
remove such information before making the comment submissions available
to the public or entering the comment submissions into ADAMS.
II. Introduction
The NRC is considering issuance of an amendment to Renewed Facility
Operating License No. NPF-77, issued to Exelon Generation Company, LLC,
for operation of Braidwood Station, Unit 2, located in Will County,
Illinois.
The proposed amendment would allow a one-time extension from 72
hours to 200 hours of the TS completion time associated with the 2A SX
pump in support of maintenance activities.
Before any issuance of the proposed license amendment, the NRC will
need to make the findings required by the Atomic Energy Act of 1954, as
amended (the Act), and NRC's regulations.
The NRC has made a proposed determination that the license
amendment request involves no significant hazards consideration. Under
the NRC's regulations in section 50.92 of title 10 of the Code of
Federal Regulations (10 CFR), this means that operation of the facility
in accordance with the proposed amendment would not: (1) Involve a
significant increase in the probability or consequences of an accident
previously evaluated; or (2) create the possibility of a new or
different kind of accident from any accident previously evaluated; or
(3) involve a significant reduction in a margin of safety. As required
by 10 CFR 50.91(a), the licensee has provided its analysis of the issue
of no significant hazards consideration, which is presented below:
1. Does the proposed change involve a significant increase in
the probability or consequences of an accident previously evaluated?
Response: No.
The proposed changes have been evaluated using the risk informed
processes described in RG [Regulatory Guide] 1.174, ``An Approach
for Using Probabilistic Risk Assessment in Risk-Informed Decisions
on Plant-Specific Changes to the Licensing Basis,'' Revision 2 dated
May 2011, RG 1. 177, ``An Approach for Plant-Specific, Risk-Informed
Decisionmaking: Technical Specifications,'' Revision 1 dated May
2011 and NRC Regulatory Guide 1.200, ``An Approach for Determining
the Technical Adequacy of Probabilistic Risk Assessment Results for
Risk-Informed Activities,'' Revision 2 dated March 2009. The risk
associated with the proposed change was found to be acceptable.
The previously analyzed accidents are initiated by the failure
of plant structures, systems, or components. The SX System is not
considered an initiator for any of these previously analyzed events.
The proposed change does not have a detrimental impact on the
integrity of any plant structure, system, or component that
initiates an analyzed event. No active or passive failure mechanisms
that could lead to an accident are affected. The proposed change
will not
[[Page 72839]]
alter the operation of, or otherwise increase the failure
probability of any plant equipment that initiates an analyzed
accident.
Therefore, the proposed change does not involve a significant
increase in the probability of an accident previously evaluated.
The proposed change does not alter or prevent the ability of
structures, systems, and components (SSCs) from performing their
intended function to mitigate the consequences of an initiating
event within the assumed acceptance limits. The proposed change does
not require any physical change to any plant SSCs nor does it
require any change in systems or plant operations. The proposed one-
time increase in the CT [completion time] is consistent with the
philosophy of the current TS LCO [limiting condition for operation]
which allows one SX train to be inoperable for 72 hours. This change
only extends the 72 hour CT to 200 hours which has been shown to be
acceptable from a risk perspective. The minimum equipment required
to mitigate the consequences of an accident and/or safely shut down
the plant will be Operable or available during the extended CT. The
proposed change is consistent with the safety analysis assumptions
and resultant consequences. Based on the above, the proposed change
does not involve a significant increase in the consequences of an
accident previously evaluated.
Therefore, the proposed change does not involve a significant
increase in the probability or consequences of an accident
previously evaluated.
2. Does the proposed change create the possibility of a new or
different kind of accident from any accident previously evaluated?
Response: No.
The proposed changes do not involve the use or installation of
new equipment and the currently installed equipment will not be
operated in a new or different manner. No new or different system
interactions are created and no new processes are introduced. The
proposed changes will not introduce any new failure mechanisms,
malfunctions, or accident initiators not already considered in the
design and licensing bases. Based on this evaluation, the proposed
change does not create the possibility of a new or different kind of
accident from any accident previously evaluated.
3. Does the proposed change involve a significant reduction in a
margin of safety?
Response: No.
The proposed change does not alter any existing setpoints at
which protective actions are initiated and no new setpoints or
protective actions are introduced. The design and operation of the
SX System remains unchanged. The risk associated with the proposed
increase in the time the 2A SX pump is allowed to be inoperable was
evaluated using the risk informed processes described in RG 1.174,
``An Approach for Using Probabilistic Risk Assessment in Risk-
Informed Decisions on Plant-Specific Changes to the Licensing
Basis,'' Revision 2 dated May 2011, RG 1.177, ``An Approach for
Plant-Specific, Risk-Informed Decisionmaking: Technical
Specifications,'' Revision 1 dated May 2011 and NRC Regulatory Guide
1.200, ``An Approach for Determining the Technical Adequacy of
Probabilistic Risk Assessment Results for Risk-Informed
Activities,'' Revision 2 dated March 2009. The risk was shown to be
acceptable. Based on this evaluation, the proposed change does not
involve a significant reduction in a margin of safety.
Based on the above, EGC [Exelon Generation Company, LLC]
concludes that the proposed amendment does not involve a significant
hazards consideration under the standards set forth in 10 CFR
50.92(c), and, accordingly, a finding of no significant hazards
consideration is justified.
The NRC staff has reviewed the licensee's analysis and, based on
this review, it appears that the three standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff proposes to determine that the
license amendment request involves a No Significant Hazards
Consideration.
The NRC is seeking public comments on this proposed determination
that the license amendment request involves no significant hazards
consideration. Any comments received within 30 days after the date of
publication of this notice will be considered in making any final
determination.
Normally, the Commission will not issue the amendment until the
expiration of 60 days after the date of publication of this notice. The
Commission may issue the license amendment before expiration of the 60-
day notice period if the Commission concludes the amendment involves no
significant hazards consideration. In addition, the Commission may
issue the amendment prior to the expiration of the 30-day comment
period if circumstances change during the 30-day comment period such
that failure to act in a timely way would result, for example, in
derating or shutdown of the facility. If the Commission takes action
prior to the expiration of either the comment period or the notice
period, it will publish in the Federal Register a notice of issuance.
If the Commission makes a final No Significant Hazards Consideration
Determination, any hearing will take place after issuance. The
Commission expects that the need to take this action will occur
infrequently.
II. Opportunity To Request a Hearing and Petition for Leave To
Intervene
Within 60 days after the date of publication of this notice, any
persons (petitioner) whose interest may be affected by this action may
file a request for a hearing and a petition for leave to intervene
(petition) with respect to the action. Petitions shall be filed in
accordance with the Commission's ``Agency Rules of Practice and
Procedure'' in 10 CFR part 2. Interested persons should consult a
current copy of 10 CFR 2.309, which is available at the NRC's PDR,
located at One White Flint North, Room O1-F21, 11555 Rockville Pike
(first floor), Rockville, Maryland 20852. The NRC's regulations are
accessible electronically from the NRC Library on the NRC's Web site at
http://www.nrc.gov/reading-rm/doc-collections/cfr/. If a petition is
filed within 60 days, the Commission or a presiding officer designated
by the Commission or by the Chief Administrative Judge of the Atomic
Safety and Licensing Board Panel, will rule on the petition; and the
Secretary or the Chief Administrative Judge of the Atomic Safety and
Licensing Board Panel will issue a notice of a hearing or an
appropriate order.
As required by 10 CFR 2.309, a petition shall set forth with
particularity the interest of the petitioner in the proceeding, and how
that interest may be affected by the results of the proceeding. The
petition should specifically explain the reasons why intervention
should be permitted with particular reference to the following general
requirements: (1) The name, address, and telephone number of the
petitioner; (2) the nature of the petitioner's right under the Act to
be made a party to the proceeding; (3) the nature and extent of the
petitioner's property, financial, or other interest in the proceeding;
and (4) the possible effect of any decision or order which may be
entered in the proceeding on the petitioner's interest. The petition
must also set forth the specific contentions which the petitioner seeks
to have litigated at the proceeding.
Each contention must consist of a specific statement of the issue
of law or fact to be raised or controverted. In addition, the
petitioner shall provide a brief explanation of the bases for the
contention and a concise statement of the alleged facts or expert
opinion which support the contention and on which the petitioner
intends to rely in proving the contention at the hearing. The
petitioner must also provide references to those specific sources and
documents of which the petitioner is aware and on which the petitioner
intends to rely to establish those facts or expert opinion to support
its position on the issue. The petition must include sufficient
information to show that a genuine dispute exists with the applicant on
a material issue of law or fact. Contentions shall be limited to
matters within the scope of the proceeding. The contention must be one
[[Page 72840]]
which, if proven, would entitle the petitioner to relief. A petitioner
who fails to satisfy these requirements with respect to at least one
contention will not be permitted to participate as a party.
Those permitted to intervene become parties to the proceeding,
subject to any limitations in the order granting leave to intervene,
and have the opportunity to participate fully in the conduct of the
hearing with respect to resolution of that person's admitted
contentions consistent with the NRC's regulations, policies, and
procedures.
Petitions must be filed no later than 60 days from the date of
publication of this notice. Requests for hearing, petitions for leave
to intervene, and motions for leave to file new or amended contentions
that are filed after the 60-day deadline will not be entertained absent
a determination by the presiding officer that the filing demonstrates
good cause by satisfying the three factors in 10 CFR 2.309(c)(1)(i)
through (iii).
If a hearing is requested, and the Commission has not made a final
determination on the issue of no significant hazards consideration, the
Commission will make a final determination on the issue of no
significant hazards consideration. The final determination will serve
to decide when the hearing is held. If the final determination is that
the amendment request involves no significant hazards consideration,
the Commission may issue the amendment and make it immediately
effective, notwithstanding the request for a hearing. Any hearing held
would take place after issuance of the amendment. If the final
determination is that the amendment request involves a significant
hazards consideration, then any hearing held would take place before
the issuance of any amendment unless the Commission finds an imminent
danger to the health or safety of the public, in which case it will
issue an appropriate order or rule under 10 CFR part 2.
A State, local governmental body, Federally-recognized Indian
Tribe, or agency thereof, may submit a petition to the Commission to
participate as a party under 10 CFR 2.309(h)(1). The petition should
state the nature and extent of the petitioner's interest in the
proceeding. The petition should be submitted to the Commission by
December 20, 2016. The petition must be filed in accordance with the
filing instructions in the ``Electronic Submissions (E-Filing)''
section of this document, and should meet the requirements for
petitions set forth in this section, except that under 10 CFR
2.309(h)(2) a State, local governmental body, or Federally-recognized
Indian Tribe, or agency thereof does not need to address the standing
requirements in 10 CFR 2.309(d) if the facility is located within its
boundaries. A State, local governmental body, Federally-recognized
Indian Tribe, or agency thereof may also have the opportunity to
participate under 10 CFR 2.315(c).
If a hearing is granted, any person who does not wish, or is not
qualified, to become a party to the proceeding may, in the discretion
of the presiding officer, be permitted to make a limited appearance
pursuant to the provisions of 10 CFR 2.315(a). A person making a
limited appearance may make an oral or written statement of position on
the issues, but may not otherwise participate in the proceeding. A
limited appearance may be made at any session of the hearing or at any
prehearing conference, subject to the limits and conditions as may be
imposed by the presiding officer. Details regarding the opportunity to
make a limited appearance will be provided by the presiding officer if
such sessions are scheduled.
III. Electronic Submissions (E-Filing)
All documents filed in NRC adjudicatory proceedings, including a
request for hearing, a petition for leave to intervene, any motion or
other document filed in the proceeding prior to the submission of a
request for hearing or petition to intervene (hereinafter
``petition''), and documents filed by interested governmental entities
participating under 10 CFR 2.315(c), must be filed in accordance with
the NRC's E-Filing rule (72 FR 49139; August 28, 2007, as amended at 77
FR 46562, August 3, 2012). The E-Filing process requires participants
to submit and serve all adjudicatory documents over the internet, or in
some cases to mail copies on electronic storage media. Participants may
not submit paper copies of their filings unless they seek an exemption
in accordance with the procedures described below.
To comply with the procedural requirements of E-Filing, at least 10
days prior to the filing deadline, the participant should contact the
Office of the Secretary by email at [email protected], or by
telephone at 301-415-1677, to request (1) a digital identification (ID)
certificate, which allows the participant (or its counsel or
representative) to digitally sign documents and access the E-Submittal
server for any proceeding in which it is participating; and (2) advise
the Secretary that the participant will be submitting a petition (even
in instances in which the participant, or its counsel or
representative, already holds an NRC-issued digital ID certificate).
Based upon this information, the Secretary will establish an electronic
docket for the hearing in this proceeding if the Secretary has not
already established an electronic docket.
Information about applying for a digital ID certificate is
available on the NRC's public Web site at http://www.nrc.gov/site-help/e-submittals/getting-started.html. System requirements for accessing
the E-Submittal server are available on the NRC's public Web site at
http://www.nrc.gov/site-help/e-submittals/adjudicatory-sub.html.
Participants may attempt to use other software not listed on the Web
site, but should note that the NRC's E-Filing system does not support
unlisted software, and the NRC Electronic Filing Help Desk will not be
able to offer assistance in using unlisted software.
Once a participant has obtained a digital ID certificate and a
docket has been created, the participant can then submit a petition.
Submissions should be in Portable Document Format (PDF). Additional
guidance on PDF submissions is available on the NRC's public Web site
at http://www.nrc.gov/site-help/electronic-sub-ref-mat.html. A filing
is considered complete at the time the documents are submitted through
the NRC's E-Filing system. To be timely, an electronic filing must be
submitted to the E-Filing system no later than 11:59 p.m. Eastern Time
on the due date. Upon receipt of a transmission, the E-Filing system
time-stamps the document and sends the submitter an email notice
confirming receipt of the document. The E-Filing system also
distributes an email notice that provides access to the document to the
NRC's Office of the General Counsel and any others who have advised the
Office of the Secretary that they wish to participate in the
proceeding, so that the filer need not serve the documents on those
participants separately. Therefore, applicants and other participants
(or their counsel or representative) must apply for and receive a
digital ID certificate before a hearing petition to intervene is filed
so that they can obtain access to the document via the E-Filing system.
A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC Electronic
Filing Help Desk through the ``Contact Us'' link located on the NRC's
public Web site at http://www.nrc.gov/site-help/e-submittals.html, by
email to [email protected], or by a toll-
[[Page 72841]]
free call at 1-866-672-7640. The NRC Electronic Filing Help Desk is
available between 9 a.m. and 7 p.m., Eastern Time, Monday through
Friday, excluding government holidays.
Participants who believe that they have a good cause for not
submitting documents electronically must file an exemption request, in
accordance with 10 CFR 2.302(g), with their initial paper filing
stating why there is good cause for not filing electronically and
requesting authorization to continue to submit documents in paper
format. Such filings must be submitted by: (1) First class mail
addressed to the Office of the Secretary of the Commission, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention:
Rulemaking and Adjudications Staff; or (2) courier, express mail, or
expedited delivery service to the Office of the Secretary, One White
Flint North, 11555 Rockville Pike, Rockville, Maryland, 20852,
Attention: Rulemaking and Adjudications Staff. Participants filing a
document in this manner are responsible for serving the document on all
other participants. Filing is considered complete by first-class mail
as of the time of deposit in the mail, or by courier, express mail, or
expedited delivery service upon depositing the document with the
provider of the service. A presiding officer, having granted an
exemption request from using E-Filing, may require a participant or
party to use E-Filing if the presiding officer subsequently determines
that the reason for granting the exemption from use of E-Filing no
longer exists.
Documents submitted in adjudicatory proceedings will appear in the
NRC's electronic hearing docket which is available to the public at
http://ehd1.nrc.gov/ehd/, unless excluded pursuant to an order of the
Commission, or the presiding officer. Participants are requested not to
include personal privacy information, such as Social Security numbers,
home addresses, or home phone numbers in their filings, unless an NRC
regulation or other law requires submission of such information.
However, in some instances, a petition will require including
information on local residence in order to demonstrate a proximity
assertion of interest in the proceeding. With respect to copyrighted
works, except for limited excerpts that serve the purpose of the
adjudicatory filings and would constitute a Fair Use application,
participants are requested not to include copyrighted materials in
their submission.
For further details with respect to this action, see the
application for license amendment dated September 30, 2016 (ADAMS
Accession No. ML16274A474).
Attorney for licensee: Tamra Domeyer, Associate General Counsel,
Exelon Generation Company, LLC, 4300 Winfield Road, Warrenville, IL
60555.
NRC Branch Chief: G. Edward Miller
Dated at Rockville, Maryland, this 12th day of October 2016.
For the Nuclear Regulatory Commission.
Joel S. Wiebe,
Senior Project Manager, Plant Licensing Branch III-2, Division of
Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2016-25503 Filed 10-20-16; 8:45 am]