[Federal Register Volume 81, Number 168 (Tuesday, August 30, 2016)]
[Notices]
[Pages 59670-59672]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-20804]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-317 and 50-318; NRC-2016-0181]
Exelon Generation Company, LLC; Calvert Cliffs Nuclear Power
Plant, Units 1 and 2; Update Schedule for Updated Final Safety Analysis
Report
AGENCY: Nuclear Regulatory Commission.
ACTION: Exemption; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an
exemption in response to a January 29, 2016, application from Exelon
Generation Company, LLC (Exelon), the licensee for Calvert Cliffs
Nuclear Power Plant (CCNPP), Units 1 and 2, for Renewed Facility
Operating License Nos. DPR-53 and DPR-60, which requested an exemption
from the updated final safety analysis report (UFSAR) update schedule
requirements in the NRC's regulations. The NRC staff reviewed this
request and is granting an exemption from the requirement that an
update to the UFSAR be submitted 6 months after the refueling outage
for each unit. The exemption allows the update to the CCNPP UFSAR to be
submitted within 6 months following the completion of each CCNPP Unit 2
refueling outage, not to exceed 24 months from the last submittal.
DATES: The exemption was issued on August 18, 2016.
ADDRESSES: Please refer to Docket ID NRC-2016-0181 when contacting the
NRC about the availability of information regarding this document. You
may obtain publicly-available information related to this document
using any of the following methods:
Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2016-0181. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact
the individual listed in the FOR FURTHER INFORMATION CONTACT section of
this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may obtain publicly-available documents online in the
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS,
please contact the NRC's Public Document Room (PDR) reference staff at
1-800-397-4209, 301-415-4737, or by email to [email protected]. The
ADAMS accession number for each document referenced (if it available in
ADAMS) is provided the first time that a document is referenced.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Richard V. Guzman, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone: 301-415-1030, email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Background
The CCNPP is a two-unit plant, both units of which share an UFSAR.
A strict interpretation of the language contained in 50.71(e)(4) of
title 10 of the Code of Federal Regulations (10 CFR), would require
Exelon to update this single UFSAR within 6 months after each unit's
refueling outage. In August 1992, the NRC promulgated a rule change
entitled ``Reducing the Regulatory Burden on Nuclear Licensees,'' which
affected 10 CFR 50.71(e)(4). This rule change was published in the
Federal Register on August 31, 1992 (57 FR 39358), with an effective
date of October 1, 1992, and was intended to provide a reduction in
regulatory burden by, in part, providing licensees with the option to
submit UFSAR updates once per refueling outage, not to exceed 24 months
between successive updates, instead of annually. However, when a single
UFSAR is shared between the units of a multi-unit plant and those units
have staggered refueling outages (i.e., one unit a year on alternating
years), as is the case with CCNPP, 10 CFR 50.71(e)(4) has the net
effect of still requiring that the UFSAR be updated annually.
Therefore, as written, the burden reduction provided by 10 CFR
50.71(e)(4) of providing licensees with the option to submit UFSAR
updates each refueling outage instead of annually can only be realized
by single-unit facilities, by multi-unit facilities that maintain
separate UFSARs for each unit, or by multi-unit facilities that share a
single UFSAR and have non-staggered refueling outages--none of which is
the case for CCNPP. Consequently, since CCNPP is a multi-unit facility
with a single shared USFAR and a staggered refueling outage schedule,
the phrase ``each refueling outage'' in 10 CFR 50.71(e)(4) does not
decrease the regulatory burden on the licensee as was the intent of the
rule.
II. Request/Action
Pursuant to 10 CFR 50.12, ``Specific exemptions,'' the licensee
has, by application dated January 29, 2016 (ADAMS Accession No.
ML16033A048), requested an exemption from the requirements of 10 CFR
50.71, ``Maintenance of records, making of reports,'' paragraph (e)(4),
related to the schedule for submitting periodic updates to the CCNPP
UFSAR. Pursuant to 10 CFR 50.12(a), the NRC may, upon application by
any interested person or upon its own initiative, grant exemptions from
the requirements of the regulations of this part, which are authorized
by law, will not present an undue risk to the public health and safety,
and are consistent with the common defense and security and when
special circumstances are present.
III. Discussion
Pursuant to 10 CFR 50.12, the NRC may, upon application by any
interested person or upon its own initiative, grant exemptions from the
requirements of 10 CFR part 50, including 10 CFR 50.71(e)(4) when: (1)
The exemptions are authorized by law, will not present an undue risk to
the public health or safety, and are consistent with the common defense
and security; and (2) when special circumstances are present. Under 10
CFR 50.12(a)(2), special circumstances include, among other things,
when application of the specific regulation in the particular
circumstances would not serve, or is not necessary to achieve, the
underlying purpose of the rule.
Authorized by Law
In accordance with 10 CFR 50.12, the NRC may grant an exemption
from the requirements of 10 CFR part 50 if the exemption is authorized
by law. The exemption requested in this instance is authorized by law
because no other prohibition of law exists to preclude the activities
which would be authorized by the exemption. Additionally, even with the
granting of the exemption, the underlying purpose of the regulation
will continue to be served. The underlying purpose of 10 CFR
50.71(e)(4) is to ensure that licensees periodically update their
UFSARs to assure that the UFSARs remain up-to-date such that they
accurately reflect the
[[Page 59671]]
plant design and operation. The rule does not require that licensees
review all of the information contained in the UFSAR for each periodic
update. Rather, the intent of the rule is for licensees to update only
those portions of the UFSAR that have been affected by licensee
activities since the previous update. As required by 10 CFR
50.71(e)(4), UFSAR updates shall be submitted within 6 months after
each refueling outage provided that the interval between successive
updates does not exceed 24 months. Submitting updates to the single
shared CCNPP UFSAR 6 months after the CCNPP Unit 2 refueling outage as
proposed and not exceeding 24 months between successive updates
continues to meet the intent of the regulation from the perspective of
regulatory burden reduction and maintaining UFSAR information up-to-
date. Therefore, this exemption request is authorized by law.
No Undue Risk to the Public Health and Safety
The underlying purpose of 10 CFR 50.71(e)(4) is to ensure that
licensees periodically update their UFSARs to assure that the UFSARs
remain up-to-date such that they accurately reflect the plant design
and operation. The NRC has determined by rule that an update frequency
not exceeding 24 months between successive updates is acceptable for
maintaining UFSAR content up-to-date. The requested exemption provides
an equivalent level of protection to the existing requirements because
it ensures that updates to the CCNPP UFSAR are submitted with no
greater than 24 months between successive updates. The requested
exemption also meets the intent of the rule for regulatory burden
reduction. Additionally, based on the nature of the requested exemption
and that updates will not exceed 24 months from the last submittal as
described above, no new accident precursors are created by the
exemption; therefore, neither the probability nor the consequences of
postulated accidents are increased. In conclusion, the requested
exemption does not result in any undue risk to the public health and
safety.
Consistent With the Common Defense and Security
The requested exemption from 10 CFR 50.71(e)(4) would allow Exelon
to submit its periodic updates to the CCNPP UFSAR within 6 months
following the completion of each CCNPP Unit 2 refueling outage, not to
exceed 24 months from the last submittal. Neither the regulation nor
the proposed exemption thereto has any relation to security issues.
Therefore, the common defense and security is not impacted by the
exemption.
Special Circumstances
Special circumstances, in accordance with 10 CFR 50.12(a)(2)(ii),
are present whenever application of the regulation in the particular
circumstances would not serve the underlying purpose of the rule or is
not necessary to achieve the underlying purpose of the rule. As
explained above, the rule change promulgated in August 1992 (57 FR
39358; August 31, 1992) was intended to provide a reduction in
regulatory burden by providing licensees with the option to submit
UFSAR updates once per refueling outage, not to exceed 24 months
between successive updates, instead of annually. However, as written,
this burden reduction can only be realized by single-unit facilities,
by multi-unit facilities that maintain separate UFSARs for each unit,
or by multi-unit facilities that share a single UFSAR and have non-
staggered refueling outages--none of which is the case for CCNPP. Since
CCNPP is a dual-unit facility with a single shared UFSAR and staggered
refueling outages, the phrase ``each refueling outage'' in 10 CFR
50.71(e)(4) does not decrease the regulatory burden on the licensee as
was the intent of the rule. Therefore, special circumstances exist
under 10 CFR 50.12(a)(2)(ii) in that application of the requirements in
these particular circumstances would not serve the underlying purpose
of the rule and are not necessary to achieve the underlying purpose of
the rule.
Environmental Considerations
With respect to its impact on the quality of the human environment,
the NRC has determined that the issuance of the exemption discussed
herein meets the eligibility criteria for categorical exclusion set
forth in 10 CFR 51.22(c)(25). Under 10 CFR 51.22(c)(25), the granting
of an exemption from the requirements of any regulation of 10 CFR
chapter I (which includes 10 CFR 50.71(e)(4)) is an action that is a
categorical exclusion.
The NRC staff's determination that all of the criteria for this
categorical exclusion are met is as follows:
I. 10 CFR 51.22(c)(25)(i): There is no significant hazards
consideration.
Staff Analysis: The criteria for determining whether an action
involves a significant hazards consideration are found in 10 CFR 50.92.
The proposed action involves only a schedule change regarding the
submission of an update to the application. Therefore, there are no
significant hazard considerations because granting the exemption would
not:
(1) Involve a significant increase in the probability or
consequences of an accident previously evaluated; or
(2) Create the possibility of a new or different kind of accident
from any accident previously evaluated; or
(3) Involve a significant reduction in a margin of safety.
II. 10 CFR 51.22(c)(25)(ii): There is no significant change in the
types or significant increase in the amounts of any effluents that may
be released offsite.
Staff Analysis: The proposed action involves only a schedule
change, which is administrative in nature, and does not involve any
changes in the types or significant increase in the amounts of any
effluents that may be released offsite.
III. 10 CFR 51.22(c)(25)(iii): There is no significant increase in
individual or cumulative public or occupational radiation exposure.
Staff Analysis: Since the proposed action involves only a schedule
change, which is administrative in nature, it does not contribute to
any significant increase in occupational or public radiation exposure.
IV. 10 CFR 51.22(c)(25)(iv): There is no significant construction
impact.
Staff Analysis: Since the proposed action involves only a schedule
change, which is administrative in nature, it does not involve any
construction impact.
V. 10 CFR 51.22(c)(25)(v): There is no significant increase in the
potential for or consequences from radiological accidents.
Staff Analysis: The proposed action involves only a schedule
change, which is administrative in nature and does not impact the
potential for or consequences from accidents.
VI. 10 CFR 51.22(c)(25)(vi): The requirements from which the
exemption is sought involve scheduling requirements and other
requirements of an administrative, managerial, or organizational
nature.
Staff Analysis: The proposed action involves scheduling
requirements and other requirements of an administrative, managerial,
or organizational nature because it is associated with the submittal
schedule requirements contained in 10 CFR 50.71(e)(4), which stipulate
that revisions to the UFSAR must be filed annually or 6 months after
each refueling outage provided the interval between successive updates
does not exceed 24 months.
Based on the above, the NRC staff concludes that the proposed
exemption
[[Page 59672]]
meets the eligibility criteria for the categorical exclusion set forth
in 10 CFR 51.22(c)(25). Therefore, in accordance with 10 CFR 51.22(b),
no environmental impact statement or environmental assessment need be
prepared in connection with the NRC's issuance of this exemption.
IV. Conclusions
The NRC has determined that, pursuant to 10 CFR 50.12, the
exemption is authorized by law, will not present an undue risk to the
public health and safety, and is consistent with the common defense and
security. Also, special circumstances pursuant to 10 CFR
50.12(a)(2)(ii) are present. Therefore, the NRC hereby grants Exelon an
exemption from the requirements of 10 CFR 50.71(e)(4) to allow Exelon
to file its periodic updates to the CCNPP UFSAR within 6 months
following the completion of each CCNPP Unit 2 refueling outage, not to
exceed 24 months from the last submittal.
Dated at Rockville, Maryland, this 22nd Day of August 2016.
For the Nuclear Regulatory Commission.
Anne T. Boland,
Director, Division of Operating Reactor Licensing, Office of Nuclear
Reactor Regulation.
[FR Doc. 2016-20804 Filed 8-29-16; 8:45 am]
BILLING CODE 7590-01-P