[Federal Register Volume 81, Number 99 (Monday, May 23, 2016)]
[Notices]
[Page 32324]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-12047]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice of Schedule for Environmental Review of the Nexus Gas
Transmission and Texas Eastern Appalachian Lease Projects
------------------------------------------------------------------------
Docket Nos.
------------------------------------------------------------------------
NEXUS Gas Transmission, LLC............... CP16-22-000
Texas Eastern Transmission, LP............ CP16-23-000
------------------------------------------------------------------------
On November 20, 2015, NEXUS Gas Transmission, LLC (NEXUS) and Texas
Eastern Transmission, LP (Texas Eastern) filed applications in Docket
Nos. CP16-22-000 and CP16-23-000 requesting a Certificate of Public
Convenience and Necessity pursuant to Section 7(c) of the Natural Gas
Act to construct, operate, and maintain certain natural gas pipeline
facilities. The proposed projects are known as the NEXUS Gas
Transmission (NGT) Project and Texas Eastern Appalachian Lease (TEAL)
Project (jointly referred to as ``Projects'') and would provide
transportation of 1.5 million dekatherms per day of Appalachian Basin
shale gas to consuming markets in Northern Ohio, Southeastern Michigan,
and Midwestern markets, as well as the Dawn Hub in Ontario, Canada.
On December 7, 2015, the Federal Energy Regulatory Commission (FERC
or Commission) issued its Notice of Application for the Projects. Among
other things, that notice alerted other agencies issuing federal
authorizations of the requirement to complete all necessary reviews and
to reach a final decision on the request for a federal authorization
within 90 days of the date of issuance of the Commission staff's final
Environmental Impact Statement (EIS) for the Projects. This instant
notice identifies the FERC staff's planned schedule for completion of
the final EIS for the Projects, which is based on an issuance of the
draft EIS in July 2016.
Schedule for Environmental Review
Issuance of Notice of Availability of the final EIS--November 30, 2016
90-day Federal Authorization Decision Deadline--February 28, 2017
If a schedule change becomes necessary for the final EIS, an
additional notice will be provided so that the relevant agencies are
kept informed of the Projects' progress.
Project Description
The NGT Project would include about 255 miles of new 36-inch-
diameter mainline pipeline, including about 208 miles in Columbiana,
Stark, Summit, Wayne, Medina, Lorain, Huron, Erie, Sandusky, Wood,
Lucas, Henry, and Fulton Counties, Ohio and about 47 miles in Lenawee,
Monroe, Washtenaw, and Wayne Counties, Michigan. The NGT Project also
would include about one mile of new 36-inch-diameter interconnecting
pipeline in Columbiana County, Ohio. In addition, NEXUS proposes to
construct and operate four new compressor stations and other
aboveground facilities.
The TEAL Project would include about 4.4 miles of new 36-inch-
diameter loop pipeline in Monroe County, Ohio; and about 0.3 mile of
new 30-inch-diameter interconnecting pipeline between in Columbiana
County, Ohio. The TEAL Project also would include construction of one
new compressor station, modification of one existing compressor
station, and construction and modification of other aboveground
facilities.
Background
On January 9, 2015 and January 26, 2015, the Commission staff
granted NEXUS and Texas Eastern's requests to use the FERC's Pre-filing
environmental review process and assigned the NGT Project and TEAL
Project Docket Nos. PF15-10-000 and PF15-11-000, respectively. On April
8, 2015, the Commission issued a Notice of Intent to Prepare an
Environmental Impact Statement for the Planned Nexus Gas Transmission
Project and Texas Eastern Appalachian Lease Project, Request for
Comments on Environmental Issues, and Notice of Public Scoping Meetings
(NOI).
The NOI was issued during the pre-filing review of the Projects and
was sent to federal, state, and local government agencies; elected
officials; affected landowners; environmental and public interest
groups; Native American tribes and regional organizations; commentors
and other interested parties; and local libraries and newspapers. Major
issues raised during scoping include underground mines, karst geology,
topsoil, drain tiles, drinking water, waterbodies, wetlands,
vegetation, wildlife, threatened and endangered species, Oak Openings
ecosystem, residential development, socioeconomic resources, cultural
resources, public safety, air quality, as well as potential cumulative
resource impacts and recommended project alternatives.
The U.S. Fish and Wildlife Service and U.S. Environmental
Protection Agency are cooperating agencies in the preparation of the
EIS.
Additional Information
In order to receive notification of the issuance of the EIS and to
keep track of all formal issuances and submittals in specific dockets,
the Commission offers a free service called eSubscription (http://www.ferc.gov/docs-filing/esubscription.asp). Additional information
about the Project is available from the Commission's Office of External
Affairs at (866) 208-FERC or on the FERC Web site (www.ferc.gov). Using
the ``eLibrary'' link, select ``General Search'' from the eLibrary
menu, enter the selected date range and ``Docket Number'' excluding the
last three digits (i.e., CP16-22 or CP16-23), and follow the
instructions.
Dated: May 17, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-12047 Filed 5-20-16; 8:45 am]
BILLING CODE 6717-01-P