DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. RM16-12-000; Docket No. RM15-21-000]
Review of Generator Interconnection Agreements and Procedures--
American Wind Energy Association; Supplemental Notice of Technical
Conference
As announced in the Notice of Technical Conference issued on March
29, 2016 \1\ and the Supplemental Notice of Technical Conference issued
on April 13, 2016 \2\ in the above-captioned proceedings, Federal
Energy Regulatory Commission (Commission) staff will hold a technical
conference on May 13, 2016 to discuss select issues related to a
petition for rulemaking submitted by the American Wind Energy
Association (Docket No. RM15-21-000).\3\ In addition, the conference
will explore other generator interconnection issues, including
interconnection of electric storage resources. The conference will be
held from 9:00 a.m. to 4:55 p.m. (EDT) (a time change from prior Notice
of Technical Conference) in the Commission Meeting Room at Commission
headquarters, 888 First Street NE., Washington, DC 20426. Members of
the Commission may attend the conference, which will also be open for
the public to attend. Advance registration is not required, but is
encouraged. Attendees may register at the following Web page: https://www.ferc.gov/whats-new/registration/05-13-16-form.asp.
---------------------------------------------------------------------------
\1\ Review of Generator Interconnection Agreements and
Procedures, Docket No. RM16-12-000 and American Wind Energy
Association, Docket No. RM15-21-000 (Mar. 29, 2016) (Notice of
Technical Conference).
\2\ Review of Generator Interconnection Agreements and
Procedures, Docket No. RM16-12-000 and American Wind Energy
Association, Docket No. RM15-21-000 (Apr. 13, 2016) (Supplemental
Notice of Technical Conference).
\3\ The comments filed in Docket No. RM15-21-000 will be
incorporated into Docket No. RM16-12-000.
---------------------------------------------------------------------------
An agenda with a list of selected speakers is attached and will be
available in the Commission Calendar of Events at http://www.ferc.gov.
Discussions at the conference may involve issues raised in
proceedings that are currently pending before the Commission. These
proceedings include, but are not limited to:
Northern Indiana Public Service Company, Docket No. EL13-88-000;
E.ON Climate & Renewables North America LLC, Pioneer Trail Wind
Farm, LLC, Settlers Trail Wind Farm, LLC v. Northern Indiana Public
Service Company, Docket No. EL14-66-002;
Internal MISO Generators v. Midcontinent Independent System
Operator, Inc., Docket No. EL15-99-000 and EL16-12;
Midcontinent Independent System Operator, Inc., Docket No. ER16-
675-000;
California Independent System Operator Corporation, Docket No.
ER16-693-000;
ISO New England, Inc., Docket No. ER16-946-000;
California Independent System Operator Corporation, Docket No.
ER16-1085-000;
Midcontinent Independent System Operator, Inc., Docket No. ER16-
1120-000;
Midcontinent Independent System Operator, Inc., Docket No. ER16-
1211-000;
Southwest Power Pool, Inc., Docket No. ER16-1350-000; and
Southern California Edison Company, Docket No. ER16-1459-000.
The conference will be transcribed and webcast. A link to the
webcast of this event will be available in the Commission Calendar of
Events at http://www.ferc.gov. Transcripts of the technical conference
will be available for a fee from Ace-Reporting (202-347-3700). The
Capitol Connection provides technical support for the webcasts and
offers the option of listening to the conferences via phone-bridge for
a fee. For additional information, visit www.CapitolConnection.org or
call (703) 993-3100.
Commission conferences are accessible under section 508 of the
Rehabilitation Act of 1973. For accessibility accommodations, please
send an email to [email protected] or call toll free (866) 208-
3372 (voice) or (202) 502-8659 (TTY), or send a FAX to (202) 208-2106
with the required accommodations.
For more information about the technical conference, please contact
Tony Dobbins ([email protected]; 202-502-6630) or Adam Pan
([email protected]; 202-502-6023). For information related to
logistics, please contact Sarah McKinley ([email protected]; 202-
502-8368).
Dated: May 4, 2016.
Kimberly D. Bose,
Secretary.
[[Page 28858]]
[GRAPHIC] [TIFF OMITTED] TN10MY16.000
Review of Generator Interconnection Agreements and Procedures Technical
Conference
Docket Nos. RM16-12-000 and RM15-21-000
May 13, 2016, Washington, DC
9:00 a.m.-9:20 a.m. Welcome and Commission Staff Opening Remarks
9:20 a.m.-10:20 a.m. The Current State of Generator Interconnection
Queues
Panelists should be prepared to discuss the following topics:
1. How well generator interconnection queues are working, the
metrics that are used to evaluate queue performance, and whether there
are clear areas in which improvement is needed.
2. Whether projects in the queue contributing most significantly to
queue backlogs are geographically dispersed or concentrated. Whether
there are queue solutions that might adequately account for the
geographic characteristics of projects contributing to queue
congestion.
3. Queue management practices and whether there are best practices
that should be incorporated across regions.
4. The extent to which regions have pursued changes to the
generator interconnection process that could be implemented without
requiring tariff changes, as noted by the Commission in the 2008 order
on interconnection queue practices.\1\
---------------------------------------------------------------------------
\1\ Interconnection Queueing Practices, 122 FERC ] 61,252, at P
10 (2008). As guidance in this order, the Commission stated that
reforms made without tariff changes could include: increasing the
staff available to work on interconnection studies; adopting more
efficient modeling for feasibility studies or system impact studies;
and performing a single system impact study for a cluster of
interconnection requests.
---------------------------------------------------------------------------
5. The primary considerations that should be taken into account
when developing solutions for each region's individual interconnection
queue issues.
Panelists:
Tim Aliff, Director of Reliability Planning, Midcontinent
Independent System Operator, Inc.
David Gabbard, Director, Electric Generation Interconnection,
Pacific Gas and Electric Company
Dean Gosselin, Vice President of Business Management
Transmission Services, NextEra Energy Resources LLC
Alan McBride, Director, Transmission Strategy and Services,
ISO New England, Inc.
Steven Naumann, Vice President, Exelon Corporation
Rick Vail, Vice President, Transmission, PacifiCorp
10:20 a.m.-10:30 a.m.: Break
10:30 a.m.-12:00 p.m.: Transparency and Timing in the Generator
Interconnection Study Process
Panelists should be prepared to discuss the following topics:
1. The length of time it takes to complete the interconnection
process, causes of variances in receiving study results, causes of
variations in length of time in the queue, and how delays (and their
causes) are reported to interconnection customers.
2. How study costs are determined, how consistent these costs are
between markets and regions, whether (and how) interconnection
customers are made aware of study costs in advance of requesting
interconnection service.
3. The information (models, assumptions, cost estimates, etc.) to
which interconnection customers currently have access and the stage in
the interconnection process when such access is provided (pre-request,
study stage, etc.). Whether additional information (historical and/or
projected curtailment or pricing information, etc.) should be available
to interconnection customers to assist them in planning projects, and
the challenges and/or barriers to providing this information.
4. How the capacity factor used for variable generation modeling is
determined (in general terms) and shared with interconnection
customers.
5. The triggers for restudy, how they are determined, and whether
they are stated in the tariff. The possible effect that limiting the
number of restudies would have on reliability or cost estimates,
allocations, or assignments.
Panelists:
David Angell, Customer Operations Planning Manager, Idaho
Power
Jennifer Ayers-Brasher, Director, Transmission & Market
Analysis, E.ON Climate & Renewables NA
Joshua Bohach, Senior Development Manager, EDP Renewables
North America
David Egan, Manager--Interconnection Projects, PJM
Interconnection, L.L.C.
Charles Hendrix, Manager, Generation Interconnection Studies,
Southwest Power Pool, Inc.
Randall Oye, Transmission Access Analyst, Xcel Energy
Stephen Rutty, Director of Grid Assets, California Independent
System Operator, Inc.
Kris Zadlo, Senior Vice President, Invenergy LLC
12:00 p.m.-1:00pm Break for Lunch
1:00 p.m.-2:10 p.m. Certainty in Cost Estimates and Construction Time
Panelists should be prepared to discuss the following topics:
1. The manner in which disputes regarding interconnection
configurations or direct assignment and network upgrade costs are
typically resolved and how such disputes could be avoided. The
frequency of such disputes.
2. When cost and construction schedule estimates are provided to
interconnection customers and the accuracy of these estimates compared
to actual results. Whether early cost estimates are sufficient to allow
customers to make decisions whether to move forward with a project. The
process changes necessary to provide more accurate estimates earlier to
interconnection customers.
[[Page 28859]]
3. The factors that affect accuracy of cost and schedule estimates
and how estimate variances can be reduced.
4. How other queued facilities that may impact an interconnection
customer's request are identified and when interconnection customers
are made aware of such facilities (e.g., a lower-queued project being
informed that the withdrawal of a specific higher-queued project may
affect it). The challenges of identifying those facilities that may
impact an interconnection request.
Panelists:
Tim Aliff, Director of Reliability Planning, Midcontinent
Independent System Operator, Inc.
Dean Gosselin, Vice President of Business Management
Transmission Services, NextEra Energy Resources LLC
Paul Kelly, Director, Federal Regulatory Policy, Northern
Indiana Public Service Company
Omar Martino, Director, Transmission, EDF Renewable Energy
Alan McBride, Director, Transmission Strategy and Services,
ISO New England, Inc.
Stephen Rutty, Director of Grid Assets, California Independent
System Operator, Inc.
Rick Vail, Vice President, Transmission, PacifiCorp
2:10 p.m.-2:20 p.m. Break
2:20 p.m.-3:30 p.m. Other Interconnection Queue Coordination and
Management Issues
Panelists should be prepared to discuss the following topics:
1. Coordinating interconnection requests with affected systems \2\
and the challenges associated with affected system coordination and
areas for improvement.
---------------------------------------------------------------------------
\2\ As defined in the pro forma LGIA and pro forma LGIP,
Affected System refers to an electric system other than the
transmission provider's transmission system that may be affected by
the proposed interconnection. Order No. 2003-A, FERC Stats. & Regs.
] 31,160 at App. 6 (Standard Large Generator Interconnection
Agreement), art. 1, order on reh'g, Order No. 2003-B, FERC Stats. &
Regs. ] 31,171 (2004), order on reh'g, Order No. 2003-C, FERC Stats.
& Regs. ] 31,190 (2005), aff'd sub nom. Nat'l Ass'n of Regulatory
Util. Comm'rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007), cert. denied,
552 U.S. 1230 (2008).
---------------------------------------------------------------------------
2. The types of changes to a project that should be allowed without
changing the project's position in the queue, i.e., determining an
appropriate threshold for modifications to a project before it should
lose its place in the queue.
3. How to manage the effects of project withdrawals from the
interconnection queue and possible best practices to keep the queue
moving despite project withdrawal. The appropriate balance between
attempts to prevent speculative projects from entering the queue and
the recognition that the study process is designed to iteratively
provide information that project developers will use to decide whether
to proceed or withdraw (possibly causing restudies).
4. How transmission providers, transmission owners, and
interconnection customers coordinate during the interconnection
process, and possible areas for improvement.
5. Technologies, tools, or administrative processes that could
improve the accuracy of cost and time estimates, reduce the processing
time, or increase the efficiency of the interconnection queue process.
Panelists:
Tim Aliff, Director of Reliability Planning, Midcontinent
Independent System Operator, Inc.
David Angell, Customer Operations Planning Manager, Idaho
Power
Jennifer Ayers-Brasher, Director, Transmission & Market
Analysis, E.ON Climate & Renewables NA
Daniel Barr, Principal Engineer, ITC Holdings
Charles Hendrix, Manager, Generation Interconnection Studies,
Southwest Power Pool, Inc.
Paul Kelly, Director, Federal Regulatory Policy, Northern
Indiana Public Service Company
Omar Martino, Director, Transmission, EDF Renewable Energy
Steven Naumann, Vice President, Exelon Corporation
3:30 p.m.-4:45 p.m. Interconnection of Electric Storage Resources
Panelists should be prepared to discuss the following topics:
1. Whether existing small and large pro forma interconnection
agreements and procedures are sufficient to accommodate the
interconnection of electric storage resources.
2. Modeling of electric storage resources for interconnection
studies, including potential means for interconnection studies to
better reflect the intended operation of electric storage devices.
3. Interconnection of combined storage and generation facilities,
including (i) the appropriate level of interconnection service for the
combined facility; (ii) the operational understanding, telemetry, and
metering of the combined facility; and (iii) the appropriate
interconnection process for adding storage to an existing generation
facility.
4. Potential processes to facilitate the interconnection of
electric storage resources.
5. Interconnection of distribution-level and aggregated electric
storage resources that participate in the RTO and ISO markets.
Panelists:
David Egan, Manager--Interconnection Projects, PJM
Interconnection, L.L.C.
Mason Emnett, Senior Attorney, NextEra Energy, Inc.
John Fernandes, Director, Policy & Market Development, RES
Americas
David Gabbard, Director, Electric Generation Interconnection,
Pacific Gas and Electric Company
Alan McBride, Director, Transmission Strategy and Services,
ISO New England, Inc.
Stephen Rutty, Director of Grid Assets, California Independent
System Operator, Inc.
4:45 p.m.-4:55 p.m. Closing Remarks