DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF16-1-000]
Algonquin Gas Transmission, LLC; Notice of Intent To Prepare an
Environmental Impact Statement for the Planned Access Northeast
Project, Request for Comments on Environmental Issues, and Notice of
Public Scoping Meetings
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental impact statement (EIS) for
the planned Access Northeast Project (ANE Project). This EIS will
discuss the potential impacts on the environment resulting from
Algonquin Gas Transmission, LLC's (Algonquin) construction and
operation of interstate natural gas transmission and storage facilities
in New Jersey, New York, Connecticut, Rhode Island, and Massachusetts.
The Commission will use this EIS in its decision-making process to
determine whether the Project is in the public convenience and
necessity.
This notice, which is being sent to the Commission's current
environmental mailing list describes the process the Commission will
use to gather input from the public and interested agencies on the ANE
Project. The Review Process flow chart in Appendix 1 also illustrates
public input opportunities.\1\ State and local government
representatives should notify their constituents of this planned
Project and encourage them to comment on their areas of concern.
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary'' or from the
Commission's Public Reference Room, 888 First Street NE.,
Washington, DC 20426, or call (202) 502-8371. For instructions on
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------
Comments on the ANE Project may be submitted in written form or
verbally. The Public Participation section of this notice describes how
to submit written comments. To ensure that written comments are
properly recorded and that staff has sufficient time to consider them,
please send these comments so that the Commission receives them in
Washington, DC on or before May 30, 2016. The Commission's staff will
also consider comments received after this date, but we encourage you
to file your comments within the identified comment period. Verbal
comments can be given at the public scoping meetings described in the
Public Participation section below.
If you sent comments on the ANE Project to the Commission before
November 17, 2015, you will need to resend those comments, attention
Docket No. PF16-1-000, to ensure they are considered as part of this
proceeding.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the planned facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the Project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement and the Project is approved, the pipeline company
could initiate condemnation proceedings where compensation would be
determined in accordance with state law.
To help potentially affected landowners and other interested
parties better understand the Commission and its environmental review
process, the ``For Citizens'' section of the FERC Web site
(www.ferc.gov) provides information about getting involved in FERC
jurisdictional projects, and a citizens' guide entitled ``An Interstate
Natural Gas Facility On My Land? What Do I Need to Know?'' This guide
addresses a number of frequently asked questions, including the use of
eminent domain and how to participate in the Commission's proceedings.
Public Participation
Submitting comments can make a difference. Your comments should
focus on potential environmental impacts, measures to avoid or lessen
these impacts, and reasonable alternatives. These comments will help
the Commission's staff determine what issues need to be evaluated in
the EIS and focus the analysis in the EIS on the important
environmental issues.
For your convenience, there are four methods you can use to submit
your comments to the Commission. The commission will provide equal
consideration to all comments received, whether filed in written form
or provided verbally. In all instances, please reference the Project
docket number (PF16-1-000) with your submission. The Commission
encourages electronic filing of comments and has expert staff available
to assist you at (202) 502-8258 or [email protected].
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for submitting brief,
text-only comments on a project;
(2) You can file your comments electronically using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' If you are filing a comment on a particular project,
please select ``Comment on a Filing'' as the filing type; or
(3) You can file a paper copy of your comments by mailing them to
the following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
(4) In lieu of sending written or electronic comments, the
Commission invites you to attend one of the public scoping meetings its
staff will conduct in the project area, scheduled as follows.
------------------------------------------------------------------------
Date and time Location
------------------------------------------------------------------------
Monday, May 16, 2016, 6:30 p.m. Eastern Southbury Fire Department, 461
Time. Main Street South, Southbury,
CT 06488.
Monday, May 16, 2016, 6:30 p.m. Eastern Mansfield Middle School, 205
Time. Spring Hill Road, Storrs, CT
06268.
Tuesday, May 17, 2016, 6:30 p.m. Sleepy Hollow High School, 210
Eastern Time. North Broadway, Sleepy Hollow,
NY 10591.
Wednesday, May 18, 2016, 6:30 p.m. Stacey Middle School, 66 School
Eastern Time *. Street, Milford, MA 01757.
Wednesday, May 18, 2016, 6:30 p.m. Ford Middle School, 708 Middle
Eastern Time. Road, Acushnet, MA 02743.
[[Page 27430]]
Thursday, May 19, 2016, 6:30 p.m. Abigail Adams Middle School, 89
Eastern Time. Weymouth Street, East
Weymouth, MA 02189.
------------------------------------------------------------------------
* Due to venue availability, the Stacy Middle School in Milford,
Massachusetts will not be accessible until 6:00 p.m. Please plan
accordingly. Meeting attendees will be asked to wait outside.
The purpose of these meetings is to provide the public an
opportunity to learn more about the Commission's environmental review
process and to verbally comment on the ANE Project. Affected landowners
and other interested parties concerned about the ANE Project are
encouraged to attend these meetings and to give their comments on the
issues they believe should be addressed in the EIS. Individuals wishing
to provide comments on Algonquin's Incremental Market and Atlantic
Bridge Projects should file their comments in the respective FERC
administrative records (CP14-96-000 and CP16-9-000).
Individuals wishing to comment at a meeting may begin registering
to speak one hour prior to each meeting.\2\ Representatives from
Algonquin will also be present before each meeting to answer questions
about the ANE Project. The meetings will begin promptly at 6:30 p.m. To
ensure everyone has a chance to be heard, the time allotted for
speakers may be limited to three minutes. If a time limit is
implemented, it will be strictly enforced. Commenters should prepare
their remarks accordingly. All comments will be transcribed and entered
into the Commission's administrative record. Due to potential large
turnouts in Acushnet and Weymouth, Massachusetts, two court reporters
will be present at each meeting to transcribe comments. One court
reporter will be present in the main room and another will be present
in an adjacent room for those who wish to speak and not attend the
entire meeting. The meetings will end once all speakers have provided
their comments or at 10 p.m., whichever comes first.
---------------------------------------------------------------------------
\2\ Due to venue availability, the Stacy Middle School in
Milford, Massachusetts will not be accessible until 6:00 p.m.
Speaker registration will begin at that time. Please plan
accordingly.
---------------------------------------------------------------------------
Summary of the Planned Project
Over the past several years Algonquin has expanded its existing
natural gas transmission system in the Northeastern United States to
meet demand as it arises in the region. In response to growing demand
and interest from shippers, Algonquin plans to modify its existing
system in New Jersey, New York, Connecticut, Rhode Island, and
Massachusetts. If constructed, the ANE Project would be capable of
providing up to 925 million cubic feet per day of natural gas at
various delivery points on the existing Algonquin pipeline system. The
planned ANE Project facilities are described below. The general
locations of the Project facilities are shown in Appendix 2.
Pipeline Facilities
Replacement of approximately 45.0 miles of existing 26-
inch-diameter pipeline with 42-inch-diameter pipeline as follows:
[cir] 1.2 miles in Rockland County, New York (Hanover Take-up and
Relay \3\);
---------------------------------------------------------------------------
\3\ Take-up and relay refers to a construction method by which
an existing pipeline is removed and replaced with a new pipeline.
---------------------------------------------------------------------------
[cir] 12.7 miles in Westchester and Putnam Counties, New York
(Stony Point Take-up and Relay);
[cir] 17.6 miles in Fairfield and New Haven Counties, Connecticut
(Southeast Take-up and Relay; and
[cir] 13.5 miles in New Haven and Hartford Counties, Connecticut
(Oxford Take-up and Relay.
Extensions of existing pipeline loops; \4\ approximately
22.7 miles of additional 36-inch-diameter pipeline and 25.9 miles of
additional 30-inch-diameter pipeline as follows:
---------------------------------------------------------------------------
\4\ A pipeline loop is a segment of pipe constructed parallel to
an existing pipeline to increase capacity.
---------------------------------------------------------------------------
[cir] 13.3 miles of 36-inch-diameter pipeline in Hartford,
Middlesex, and Tolland Counties, Connecticut (Cromwell Loop);
[cir] 9.4 miles of 36-inch-diameter pipeline in Windham County,
Connecticut (Chaplin Loop);
[cir] 21.7 miles of 30-inch-diameter pipeline in Norfolk County,
Massachusetts (Q-1 Loop); and
[cir] 4.2 miles of 30-inch-pipeline in Norfolk County,
Massachusetts (I-8 Loop).
Installation of approximately 26.8 miles of new 16-inch-
diameter lateral pipeline in Norfolk and Worcester Counties,
Massachusetts.
Installation of approximately 2.9 miles of new 24-inch-
diameter lateral pipeline in Bristol County, Massachusetts.
Algonquin would also need to construct pig \5\ launcher and
receiver facilities and new mainline valves.
---------------------------------------------------------------------------
\5\ A ``pig'' is a tool that the pipeline company inserts into
and pushed through the pipeline for cleaning the pipeline,
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------
Compressor Stations and Other Pipeline-Related Aboveground Facilities
Algonquin plans to modify six existing compressor stations, expand
one currently proposed compressor station, construct one new compressor
station, modify seven existing metering and regulating (M&R) stations,
and construct two new M&R stations. The modifications to the six
existing compressor stations would be located in Rockland and Putnam
Counties, New York, New Haven, Middlesex, and Windham Counties
Connecticut, and Providence County, Rhode Island. The expansion of the
currently proposed compressor station would be located in Norfolk
County, Massachusetts and the new compressor station would be located
in Bristol County, Massachusetts. These eight compressor stations would
add a total of 165,560 horsepower to Algonquin's pipeline system.
The modifications to the seven existing Algonquin M&R stations
would occur in New Jersey, New York, Connecticut, and Massachusetts to
accept the new gas flows associated with the Project. The new M&R
stations would be constructed in Bristol and Worcester Counties
Massachusetts.
Liquefied Natural Gas (LNG) Storage Facility
The planned LNG Storage Facility would be located on a 210-acre
site in Acushnet, Massachusetts adjacent to an existing LNG peak-
shaving facility (the existing facility would not be affected). The
facility would include; two full containment LNG storage tanks with a
total combined capacity of 6.8 billion standard cubic feet (84.6
million gallons), feed gas pretreatment systems, liquefaction and
regasification capabilities, a new permanent access road, a flare or
other venting system yet to be determined, electrical service
facilities, and a refrigerant compressor driver with appropriate noise
suppression and emission controls. This facility would be connected to
Algonquin's existing natural gas transmission system by a new
approximately 2.86 mile pipeline.
[[Page 27431]]
Land Requirements for Construction
Construction of the planned facilities would disturb about 1,866
acres of land including forested, open, agricultural, industrial/
commercial, and residential lands. Of the lands affected, about 1,590
acres for the pipeline facilities, 118 acres for the compressor
stations, 150 acres for the LNG Facility, and 8 acres for the M&R
stations. About 1,100 acres of land that would be affected by pipeline
construction activities has already been disturbed by existing
pipelines or other utilities. Similarly, about 95 acres of land that
would be affected by the compressor stations has already been
disturbed. Following construction, Algonquin would retain about 494
acres of new, permanent easement outside of its current operating
footprint. This amount includes approximately 327 acres of permanent
easement for the new pipeline right-of-way, 20 acres for the new
compressor station, 150 acres for the LNG Facility, and a total of 2
acres for the M&R stations.
The EIS Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity under Section 7 of the
Natural Gas Act. NEPA also requires us \6\ to discover and address
concerns the public may have about proposals. This discovery process is
commonly referred to as ``scoping''. The main goal of the scoping
process is to focus the analysis in the EIS on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EIS. All comments
received will be considered during the preparation of the EIS, and
addressed as appropriate.
---------------------------------------------------------------------------
\6\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EIS we will discuss impacts that could occur as a result of
the construction, operation, and maintenance of the planned Project
under these general headings:
Geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
threatened and endangered species;
public safety and reliability; and
cumulative impacts.
Staff, in cooperation with other federal agencies, has already
begun an evaluation of alternatives to the ANE Project, including
pipeline route alternatives, compressor station equipment and
locations, and LNG Storage Facility sites. This alternatives analysis
will be included in the EIS along with any recommendations we may have
on how to avoid, minimize, and/or mitigate impacts on the various
resource areas.
Although no formal application has been filed, we have already
initiated our NEPA review under the Commission's pre-filing process.
The purpose of the pre-filing process is to encourage early involvement
of interested stakeholders and to identify and resolve issues before
the FERC receives an application. As part of our pre-filing review, we
have contacted federal and state agencies to discuss their involvement
in the scoping process and the preparation of the EIS.
The EIS will present our independent analysis of the issues. We
will publish and distribute the draft EIS for public comment. After the
comment period, we will consider all timely comments and revise the
document, as necessary, before issuing a final EIS. To ensure we have
the opportunity to consider and address your comments, please carefully
follow the instructions in the Public Participation section of this
notice.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues
related to this Project to formally cooperate with us in the
preparation of the EIS.\7\ Agencies that would like to request
cooperating agency status should follow the instructions for filing
comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\7\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with applicable State Historic Preservation Offices (SHPO), and to
solicit their views and those of other government agencies, interested
federally recognized Indian tribes, and the public on the Project's
potential effects on historic properties.\8\ We will define the
Project-specific Area of Potential Effects (APE) in consultation with
the SHPOs as the Project develops. On natural gas facility projects,
the APE at a minimum encompasses all areas subject to ground
disturbance (examples include construction right-of-way, contractor/
pipe storage yards, compressor stations, and access roads). Our EIS for
this project will document our findings on the impacts on historic
properties and summarize the status of consultations under section 106.
---------------------------------------------------------------------------
\8\ The Advisory Council on Historic Preservation regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Currently Identified Environmental Issues
Based on our preliminary review of the project; information
provided by Algonquin; and public comments filed in the Commission's
administrative record and submitted to staff at the applicant-sponsored
open houses, we have identified several issues that we think deserve
attention. This preliminary list of issues may change based on your
comments and our ongoing environmental analysis. These issues are:
Project reliability, pipeline and LNG storage tank
integrity;
public safety;
impacts on property values;
environmental justice;
compressor station emissions and noise;
impacts on land use; and
impacts on groundwater.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities and construction
workspaces, and anyone who submits comments on the Project. We will
update the environmental mailing list as the analysis proceeds to
ensure that we send the information related to this environmental
review to all individuals, organizations, and government entities
interested in and/or potentially affected by the planned Project.
When we publish and distribute the EIS, copies will be sent to the
environmental mailing list for public
[[Page 27432]]
review and comment. If you would prefer to receive a paper copy of the
document instead of the CD version or would like to remove your name
from the mailing list, please return the attached Information Request
(Appendix 3).
Becoming an Intervenor
In addition to involvement in the EIS scoping process, once
Algonquin files its application with the Commission, you may want to
become an ``intervenor,'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Motions to intervene are more fully described at
http://www.ferc.gov/resources/guides/how-to/intervene.asp. Instructions
for becoming an intervenor are in the ``Document-less Intervention
Guide'' under the ``e-filing'' link on the Commission's Web site.
Please note that the Commission will not accept requests for intervenor
status at this time. You must wait until the Commission receives a
formal application for the Project, which is currently anticipated to
be sometime in November 2016.
Additional Information
Additional information about the Project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., PF16-
1). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
[email protected] or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: April 29, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-10667 Filed 5-5-16; 8:45 am]
BILLING CODE 6717-01-P