[Federal Register Volume 81, Number 84 (Monday, May 2, 2016)]
[Notices]
[Pages 26221-26222]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-10096]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12496-002]
Rugraw, LLC; Notice of Application Ready for Environmental
Analysis and Soliciting Comments, Recommendations, Terms and
Conditions, and Prescriptions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Major Original License.
b. Project No.: P-12496-002.
c. Date filed: April 21, 2014.
d. Applicant: Rugraw, LLC.
e. Name of Project: Lassen Lodge Hydroelectric Project.
f. Location: On the South Fork Battle Creek near the Town of
Mineral in Tehama County, California. The project would be located on
private lands. No federal lands or Indian reservations are located
within the proposed project boundary.
g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
h. Applicant Contact: Charlie Kuffner, 70 Paseo Mirasol, Tiburon,
CA 94920; (415) 652-8553
i. FERC Contact: Kenneth Hogan at (202) 502-8434; or via email at
[email protected].
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions: 60 days from the issuance date of this
notice; reply comments are due 105 days from the issuance date of this
notice.
The Commission strongly encourages electronic filing. Please file
comments, recommendations, terms and conditions, and prescriptions
using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000
characters, without prior registration, using the eComment system at
http://www.ferc.gov/docs-filing/ecomment.asp. You must include your
name and contact information at the end of your comments. For
assistance, please contact FERC Online Support at
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to:
Secretary, Federal Energy Regulatory Commission, 888 First Street NE.,
Washington, DC 20426. The first page of any filing should include
docket number P-12496-002.
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. This application has been accepted and is now ready for
environmental analysis.
l. The proposed Lassen Lodge Project would consist of: (1) A 6-
foot-high and 94-foot-long diversion dam; (2) an impoundment of
approximately 0.5
[[Page 26222]]
acre; (3) a 20-foot by 10-foot enclosed concrete intake structure; (4)
a 7,258-foot-long pipeline and a 5,230-foot-long penstock with a net
head of 791 feet; (5) a 50-foot by 50-foot powerhouse containing one
generating unit with a 5,000-kilowatt capacity; (6) a 50-foot by 50-
foot substation area; (7) a 40-foot by 35-foot switchyard; (8) 100-foot
by 100-foot multipurpose area; and (9) a new 12-mile-long, 60-kilovolt
transmission line. The project is estimated to produce approximately
25,000,000 kilowatt hours annually.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at http://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
All filings must (1) bear in all capital letters the title
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. Each filing must be
accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 4.34(b), and 385.2010.
You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Public notice of the filing of the initial development
application, which has already been given, established the due date for
filing competing applications or notices of intent. Under the
Commission's regulations, any competing development application must be
filed in response to and in compliance with public notice of the
initial development application. No competing applications or notices
of intent may be filed in response to this notice.
o. Procedural Schedule: The application will be processed according
to the following revised Hydro Licensing Schedule. Revisions to the
schedule may be made as appropriate.
------------------------------------------------------------------------
Milestone Target
------------------------------------------------------------------------
Notice that application is ready for April 2016.
environmental analysis.
Filing of comments, recommendations, June 2016.
terms and conditions, and
prescriptions.
Filing of reply comments............... July 2016.
Notice of the availability of the draft October 2016.
EIS.
Initiate 10(j) process................. December 2016.
Notice of the availability of the final May 2017.
EIS.
------------------------------------------------------------------------
p. A license applicant must file no later than 60 days following
the date of issuance of this notice: (1) A copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of waiver of water quality certification.
Dated: April 25, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-10096 Filed 4-29-16; 8:45 am]
BILLING CODE 6717-01-P