DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP15-138-000]
Transcontinental Gas Pipe Line Company, LLC; Notice of Schedule
for Environmental Review of the Atlantic Sunrise Expansion Project
On March 31, 2015, Transcontinental Gas Pipe Line Company, LLC
(Transco) a subsidiary of Williams Partners L.P. (Williams), filed an
application with the Federal Energy Regulatory Commission (FERC or
Commission) in Docket No. CP15-138-000 requesting authorization
pursuant to section 7(c) of the Natural Gas Act (NGA) and part 157 of
the Commission's regulations to construct, operate, and maintain
expansions of its existing interstate natural gas pipeline system in
Pennsylvania, Maryland, Virginia, North Carolina, and South Carolina.
The proposed project, referred to as the Atlantic Sunrise Expansion
Project (Project), would provide 1,700,000 dekatherms per day of
natural gas transportation service from various receipt points in
Pennsylvania to various delivery points along Transco's existing
interstate pipeline system.
FERC issued its Notice of Application for the Project on April 8,
2015. Among other things, the notice alerted other agencies issuing
federal authorizations of the requirement to complete all necessary
reviews and to reach a final decision on the request for a federal
authorization within 90 days of the date of issuance of the Commission
staff's final environmental impact statement (EIS) for the Project.
This notice identifies the FERC staff's planned schedule for completion
of the final EIS for the Project.
Schedule for Environmental Review
Issuance of Notice of Availability of the final EIS October 21, 2016
90-day Federal Authorization Decision Deadline January 19, 2017
If a schedule change becomes necessary, an additional notice will
be provided so that the relevant agencies are kept informed of the
Project's progress.
Project Description
The Project includes about 197.7 miles of pipeline composed of the
following facilities:
183.7 miles of new 30- and 42-inch-diameter greenfield \1\
natural gas pipeline;
---------------------------------------------------------------------------
\1\ A ``greenfield'' pipeline crosses land previously untouched
by natural gas infrastructure rather than using existing rights-of-
way.
---------------------------------------------------------------------------
11.5 miles of new 36- and 42-inch-diamater pipeline
looping; \2\
---------------------------------------------------------------------------
\2\ ``Looping'' is the practice of installing a pipeline in
parallel to another pipeline to increase the capacity along an
existing stretch of right-of-way, often beyond what can be achieved
by one pipeline or pipeline expansion.
---------------------------------------------------------------------------
2.5 miles of 30-inch-diameter replacements; and
associated equipment and facilities.
The Project's aboveground facilities consist of two new compressor
stations; additional compression and related modifications to three
existing compressor stations; two new meter stations and three new
regulator stations; and minor modifications at existing aboveground
facilities at various locations to allow for bi-directional flow and
the installation of supplemental odorization, odor detection, and/or
odor masking/deodorization equipment.
Background
On April 4, 2014, the Commission staff granted Transco's request to
use the FERC's pre-filing environmental review process and assigned the
Project Docket No. PF14-8-000. On July 18, 2014, the Commission issued
a Notice of Intent to Prepare an Environmental Impact Statement for the
Planned Atlantic Sunrise Expansion Project, Request for Comments on
Environmental Issues, and Notice of Public Scoping Meetings (NOI). The
NOI was sent to federal, state, and local government representatives
and agencies; elected officials; environmental and public interest
groups; Native American Tribes; affected property owners; other
interested parties; and local libraries and newspapers. Major issues
raised
[[Page 13789]]
during scoping include potential impacts on forested areas,
groundwater, and threatened and endangered species; socioeconomic
impacts; land use and recreational impacts; air quality; safety;
potential cumulative impacts; and potential alternative routes. The
U.S. Army Corps of Engineers is a cooperating agency in the preparation
of the EIS.
Additional information about the Project may be obtained by
contacting the Environmental Project Manager, Joanne Wachholder, by
telephone at (202) 502-8056 or by electronic mail at
[email protected].
Dated: March 9, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.