[Federal Register Volume 81, Number 36 (Wednesday, February 24, 2016)]
[Notices]
[Pages 9192-9193]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-03836]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Notice Revising Post-Technical Conference Comment Schedule
------------------------------------------------------------------------
Docket Nos.
------------------------------------------------------------------------
PJM Interconnection, L.L.C............. ER15-2562-000, ER15-2563-000.
Consolidated Edison Company of New EL15-18-001.
York, Inc. v. PJM Interconnection,
L.L.C.
Linden VFT, LLC v. PJM Interconnection, EL15-67-000.
L.L.C.
Delaware Public Service Commission and EL15-95-000.
Maryland Public Service Commission v.
PJM Interconnection, L.L.C.
PJM Interconnection, L.L.C............. ER14-972-003.
PJM Interconnection, L.L.C............. ER14-1485-005, Not
Consolidated.
------------------------------------------------------------------------
In an order dated November 24, 2015,\1\ the Commission found that
the assignment of cost allocation for the projects in the filings and
complaints listed in the caption using PJM's solution-based
distribution factor (DFAX) cost allocation method had not been shown to
be just and reasonable and may be unjust, unreasonable, or unduly
discriminatory or preferential. The Commission directed its staff to
establish a technical conference to explore both whether there is a
definable category of reliability projects within PJM for which the
solution-based DFAX cost allocation method may not be just and
reasonable, such as projects addressing reliability violations that are
not related to flow on the planned transmission facility, and whether
an alternative just and reasonable ex ante cost allocation method could
be established for any such category of projects.
---------------------------------------------------------------------------
\1\ PJM Interconnection, L.L.C., et al., 153 FERC ] 61,245
(2015).
---------------------------------------------------------------------------
The technical conference was held on January 12, 2016. At the
technical conference, staff indicated that it would establish a
schedule for post-technical conference comments after reviewing the
technical conference transcript. On February 9, 2016 a technical
conference transcript was place in the above-referenced dockets, and a
post-technical conference comment schedule was established. On February
18, 2016, an errata transcript of the February 9, 2016 transcript was
placed in the dockets. The schedule for post-technical conference
comments is revised accordingly.
Post-technical conference comments, not to exceed 20 pages, are due
on or before March 9, 2016.
[[Page 9193]]
For more information about this technical conference, please
contact [email protected]; or Sarah McKinley, 202-502-8368,
[email protected], regarding logistical issues.
Dated: February 18, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-03836 Filed 2-23-16; 8:45 am]
BILLING CODE 6717-01-P