[Federal Register Volume 81, Number 11 (Tuesday, January 19, 2016)]
[Notices]
[Pages 2857-2858]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2016-00819]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 2343-086]
PE Hydro Generation, LLC; Notice of Application Tendered for
Filing With the Commission and Establishing Procedural Schedule for
Licensing and Deadline for Submission of Final Amendments
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: New Major License.
b. Project No.: 2343-086.
c. Date Filed: December 30, 2015.
d. Applicant: PE Hydro Generation, LLC (PE Hydro).
e. Name of Project: Millville Hydroelectric Project.
f. Location: The existing project is located on the Shenandoah
River, near the town of Harpers Ferry in Jefferson County, West
Virginia. No federal lands are occupied by project works or located
within the project boundary.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Juan Kimble, President, PE Hydro Generation,
LLC, 5425 Wisconsin Avenue, 6th Floor, Chevy Chase, MD 20815;
Telephone--(301) 718-4496.
i. FERC Contact: Michael Spencer, (202) 502-6093, or
[email protected].
j. This application is not ready for environmental analysis (EA) at
this time.
k. Project Description: The Millville project consists of: (1) A
14.0-foot-high concrete and stone dam consisting of three sections: a
36-foot-long non-overflow abutment on the east bank; an 813-foot long,
non-gated spillway section; and a 122-foot-long intake structure,
equipped with four vertical lift gates and one canal gate, and
extending to the west riverbank; (2) a 100 acre reservoir with gross
storage capacity of 900 acre-feet at elevation 324.0 mean sea level;
(3) a 1,600-foot-long, 30-foot-wide, 12-foot-high masonry and concrete
sided headrace canal; (4) a 125-foot-long, 40-foot-wide brick
powerhouse containing 3 turbine-generating units with a combined
capacity of 2.84 megawatts; (5) a 550-foot-long tailrace, excavated in
bedrock and returning flow to the river channel; and (6) a 1,006-foot-
long, 2.4 kilovolt (kV) transmission line to a transformer, with a 794-
foot-long, 34.5 kV transmission line to the interconnection with the
local grid.
PE Hydro operates the project in a run-of-river mode, with a
minimum flow of 200 cfs, or inflow, whichever is less. Under an
agreement with the US Fish and Wildlife Service the licensee shuts down
Project nightly from September 15 to December 15 in an effort to reduce
entrainment of downstream-migrating American eels. The project
generates an annual average of 10,159.431 MWh.
l. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at http://www.ferc.gov, using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support at [email protected], (866) 208-3676 (toll
free), or (202) 502-8659 (TTY). A copy is also available for inspection
and reproduction at the address in item (h) above.
You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
m. Procedural Schedule: The application will be processed according
to the following preliminary Hydro Licensing Schedule. Revisions to the
schedule will be made as appropriate.
[[Page 2858]]
------------------------------------------------------------------------
------------------------------------------------------------------------
Notice of Acceptance/Notice of Ready for February 2016.
Environmental Analysis.
Filing of recommendations, preliminary April 2016.
terms and conditions, and fishway
prescriptions.
Commission issues EA...................... August 2016.
Comments on EA............................ September 2016.
Modified Terms and Conditions............. November 2016.
Commission Issues Final EA, if necessary.. February 2017.
------------------------------------------------------------------------
o. Final amendments to the application must be filed with the
Commission no later than 30 days from the issuance date of the notice
of ready for environmental analysis.
Dated: January 12, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-00819 Filed 1-15-16; 8:45 am]