DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
Swan Lake North Hydro LLCProject No. 13318-003; Notice of
Application Accepted for Filing and Soliciting Motions To Intervene and
Protests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Unconstructed major project.
b. Project No.: 13318-003.
c. Date filed: October 28, 2015.
d. Applicant: Swan Lake North Hydro LLC.
e. Name of Project: Swan Lake North Pumped Storage Hydroelectric
Project.
f. Location: Approximately 11 miles northeast of the city of
Klamath Falls, Klamath County, Oregon. The proposed project boundary
would include about 730 acres of federal land managed by the U.S.
Bureau of Land Management.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Joe Eberhardt, EDF-Renewable Energy, 1000 SW
Broadway Ave., Ste. 1800, Portland, OR 97205; phone: (503) 889-3838.
i. FERC Contact: Dianne Rodman, [email protected]; phone:
(202) 502-6077.
j. Deadline for filing motions to intervene and protests: February
16, 2016.
The Commission strongly encourages electronic filing. Please file
filing motions to intervene and protests using the Commission's eFiling
system at http://www.ferc.gov/docs-filing/efiling.asp. For assistance,
please contact FERC Online Support at [email protected], (866)
208-3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic
filing, please send a paper copy to: Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426. The
first page of any filing should include docket number P-13318-003.
The Commission's Rules of Practice and Procedures require all
intervenors filing documents with the Commission to serve a copy of
that document on each person on the official service list for the
project. Further, if an intervenor files comments or documents with the
Commission relating to the merits of an issue that may affect the
responsibilities of a particular resource agency, they must also serve
a copy of the document on that resource agency.
k. This application has been accepted for filing, but is not ready
for environmental analysis at this time.
l. The proposed project would be a closed-loop system using
groundwater for initial fill and consist of the following new
facilities: (1) A 7,972-foot-long earthen embankment forming a
geomembrane-lined upper reservoir with a surface area of 64.21 acres
and a storage capacity of 2,568 acre-feet at a maximum surface
elevation of 6,135 feet above mean sea level (msl); (2) a 8,003-foot-
long earthen embankment forming a geomembrane-lined lower reservoir
with a surface area of 60.14 acres and a storage capacity of 3,206
acre-feet at a maximum surface elevation of 4,457 feet msl; (3) a 500-
foot-long, rip-rap lined trapezoidal spillway built into the crest of
each embankment; (4) a 0.5-percent slope perforated polyvinyl chloride
tube of varying diameter and accompanying optical fiber drainage system
designed to detect, collect, and monitor water leakage from the
reservoirs; (5) a 25-inch-diameter bottom outlet with manual valve for
gravitational dewatering of the lower reservoir; (6) an upper intake
consisting of a bell mouth, 38.6-foot-wide by 29.8-foot-long inclined
screen, head gate, and 13.8-foot-diameter foundational steel pipe; (7)
a 36.5-foot-diameter, 9,655-foot-long steel high-pressure penstock from
the upper reservoir to the powerhouse that is predominantly above
ground with a 14-foot-long buried segment; (8) three 9.8-foot-diameter,
1,430-foot-long steel low-pressure penstocks from the lower reservoir
to the powerhouse that are predominantly above ground with a 78-foot-
long buried segment ; (9) a partially-buried powerhouse with three
131.1-megawatt (MW) reversible pump-turbine units with a total
installed capacity of 393.3 MW; (10) a 32.8 mile, 230-kilovolt above-
ground transmission line interconnecting to an existing non-project
substation; (11) approximately 10.7 miles of improved project access
road; (12) approximately 3.4 miles of new permanent project access
road; (13) approximately 8.3 miles of temporary project access road;
and (14) appurtenant facilities. The project would generate about 1,187
gigawatt-hours annually.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at http://www.ferc.gov using the
[[Page 80350]]
``eLibrary'' link. Enter the docket number excluding the last three
digits in the docket number field to access the document. For
assistance, contact FERC Online Support. A copy is also available for
inspection and reproduction at the address in item h above.
You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Any qualified applicant desiring to file a competing application
must submit to the Commission, on or before the specified intervention
deadline date, a competing development application, or a notice of
intent to file such an application. Submission of a timely notice of
intent allows an interested person to file the competing development
application no later than 120 days after the specified intervention
deadline date. Applications for preliminary permits will not be
accepted in response to this notice.
A notice of intent must specify the exact name, business address,
and telephone number of the prospective applicant, and must include an
unequivocal statement of intent to submit a development application. A
notice of intent must be served on the applicant(s) named in this
public notice.
Anyone may submit a protest or a motion to intervene in accordance
with the requirements of Rules of Practice and Procedure, 18 CFR
385.210, 385.211, and 385.214. In determining the appropriate action to
take, the Commission will consider all protests filed, but only those
who file a motion to intervene in accordance with the Commission's
Rules may become a party to the proceeding. Any protests or motions to
intervene must be received on or before the specified deadline date for
the particular application.
When the application is ready for environmental analysis, the
Commission will issue a public notice requesting comments,
recommendations, terms and conditions, or prescriptions.
All filings must (1) bear in all capital letters the title
``PROTEST'' or ``MOTION TO INTERVENE,'' ``NOTICE OF INTENT TO FILE
COMPETING APPLICATION,'' or ``COMPETING APPLICATION;'' (2) set forth in
the heading the name of the applicant and the project number of the
application to which the filing responds; (3) furnish the name,
address, and telephone number of the person protesting or intervening;
and (4) otherwise comply with the requirements of 18 CFR 385.2001
through 385.2005. Agencies may obtain copies of the application
directly from the applicant. A copy of any protest or motion to
intervene must be served upon each representative of the applicant
specified in the particular application.
Dated: December 18, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-32405 Filed 12-23-15; 8:45 am]