New England Hydropower Company, LLC; Notice of Surrender of 
Preliminary Permit

    Take notice that New England Hydropower Company, LLC, permittee for 
the proposed Lensdale Pond Dam Hydroelectric Project, has requested 
that its preliminary permit be terminated. The permit was issued on 
July 25, 2013, and would have expired on June 30,

[[Page 75081]]

2016.\1\ The project would have been located on the Quinebaug River in 
the town of Southbridge, Worcester County, Massachusetts.
---------------------------------------------------------------------------

    \1\ 144 FERC ] 62,066 (2013).
---------------------------------------------------------------------------

    The preliminary permit for Project No. 14518 will remain in effect 
until the close of business, December 18, 2015. But, if the Commission 
is closed on this day, then the permit remains in effect until the 
close of business on the next day in which the Commission is open.\2\ 
New applications for this site may not be submitted until after the 
permit surrender is effective.
---------------------------------------------------------------------------

    \2\ 18 CFR 385.2007(a)(2) (2015).

    Dated: November 18, 2015.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2015-30394 Filed 11-30-15; 8:45 am]