On June 30, 2015, Dan Sullivan filed a notice of intent to
construct a qualifying conduit hydropower facility, pursuant to section
30 of the Federal Power Act (FPA), as amended by section 4 of the
Hydropower Regulatory Efficiency Act of 2013 (HREA). The proposed Drake
Cottonwood Hydropower Project would have an installed capacity of 14
kilowatts (kW) and would be located on the existing irrigation canal
off Cottonwood Creek; 1.5 miles of the canal will be enclosed with a
15-inch-diameter pipe. The project would be located near Hotchkiss in
Delta County, Colorado.
Applicant Contact: Dan Sullivan, 8301 Crawford Road, Hotchkiss, CO
81419, Phone No. (970) 216-6925.
FERC Contact: Robert Bell, Phone No. (202) 502-6062, email:
[email protected].
Qualifying Conduit Hydropower Facility Description: The proposed
project would consist of: (1) 1.5 miles of 15-inch PVC pipe located on
the existing irrigation canal off Cottonwood Creek; (2) a proposed 10-
foot-long by 12-foot-wide by 8-foot-high powerhouse containing four
generating units with a total installed capacity of 14 kW; (3) a 4-
foot-long by 10-foot-wide tailrace returning flow back into the
irrigation canal; and (4) appurtenant facilities. The proposed project
would have an estimated annual generating capacity of 95 megawatt-
hours.
A qualifying conduit hydropower facility is one that is determined
or deemed to meet all of the criteria shown in the table below.
Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
Satisfies (Y/
Statutory provision Description N)
------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by The conduit the Y
HREA. facility uses a
tunnel, canal,
pipeline, aqueduct,
flume, ditch, or
similar manmade water
conveyance that is
operated for the
distribution of water
for agricultural,
municipal, or
industrial
consumption and not
primarily for the
generation of
electricity.
FPA 30(a)(3)(C)(i), as amended The facility is Y
by HREA. constructed,
operated, or
maintained for the
generation of
electric power and
uses for such
generation only the
hydroelectric
potential of a non-
federally owned
conduit.
FPA 30(a)(3)(C)(ii), as amended The facility has an Y
by HREA. installed capacity
that does not exceed
5 megawatts.
FPA 30(a)(3)(C)(iii), as On or before August 9, Y
amended by HREA. 2013, the facility is
not licensed, or
exempted from the
licensing
requirements of Part
I of the FPA.
------------------------------------------------------------------------
Preliminary Determination: Based upon the above criteria,
Commission staff preliminarily determines that the proposal satisfies
the requirements for a qualifying conduit hydropower facility, which is
not required to be licensed or exempted from licensing.
Comments and Motions to Intervene: Deadline for filing comments
contesting whether the facility meets the qualifying criteria is 45
days from the issuance date of this notice.
Deadline for filing motions to intervene is 30 days from the
issuance date of this notice.
Anyone may submit comments or a motion to intervene in accordance
with the requirements of Rules of Practice and Procedure, 18 CFR
385.210 and 385.214. Any motions to intervene must be received on or
before the specified deadline date for the particular proceeding.
Filing and Service of Responsive Documents: All filings must (1)
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as
applicable; (2) state in the heading the name of the applicant and the
project number of the application to which the filing responds; (3)
state the name, address, and telephone number of the person filing; and
(4) otherwise comply with the requirements of sections 385.2001 through
385.2005 of the Commission's regulations.\1\ All comments contesting
Commission staff's preliminary determination that the facility meets
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------
\1\ 18 CFR 385.2001-2005 (2014).
---------------------------------------------------------------------------
The Commission strongly encourages electronic filing. Please file
motions to intervene and comments using the Commission's eFiling system
at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at http://www.ferc.gov/docs-filing/
[[Page 45209]]
ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support at [email protected], (866) 208-3676 (toll free), or
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper
copy to: Secretary, Federal Energy Regulatory Commission, 888 First
Street NE., Washington, DC 20426. A copy of all other filings in
reference to this application must be accompanied by proof of service
on all persons listed in the service list prepared by the Commission in
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
Locations of Notice of Intent: Copies of the notice of intent can
be obtained directly from the applicant or such copies can be viewed
and reproduced at the Commission in its Public Reference Room, Room 2A,
888 First Street NE., Washington, DC 20426. The filing may also be
viewed on the web at http://www.ferc.gov/docs-filing/elibrary.asp using
the ``eLibrary'' link. Enter the docket number (e.g., CD15-29-000) in
the docket number field to access the document. For assistance, call
toll-free 1-866-208-3676 or email [email protected]. For TTY,
call (202) 502-8659.
Dated: July 22, 2015.
Kimberly D. Bose,
Secretary.