DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 14550-001]
New England Hydropower Company, LLC; Notice of Application
Tendered for Filing With the Commission and Soliciting Additional Study
Requests
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Exemption from Licensing.
[[Page 39095]]
b. Project No.: 14550-001.
c. Date filed: June 26, 2015.
d. Applicant: New England Hydropower Company, LLC.
e. Name of Project: Hanover Pond Dam Hydroelectric Project.
f. Location: On the Quinnipiac River, near the city of Meriden, in
New Haven County, Connecticut. No federal lands would be occupied by
project works or located within the project boundary.
g. Filed Pursuant to: Public Utility Regulatory Policies Act of
1978, 16 U.S.C. 2705, 2708.
h. Applicant Contact: Mr. Michael C. Kerr, New England Hydropower
Company, LLC, P.O. Box 5524, Beverly Farms, Massachusetts 01915; (978)
360-2547, [email protected].
i. FERC Contact: John Ramer, (202) 502-8969, [email protected].
j. Cooperating agencies: Federal, state, local, and tribal agencies
with jurisdiction and/or special expertise with respect to
environmental issues that wish to cooperate in the preparation of the
environmental document should follow the instructions for filing such
requests described in item l below. Cooperating agencies should note
the Commission's policy that agencies that cooperate in the preparation
of the environmental document cannot also intervene. See, 94 FERC ]
61,076 (2001).
k. Pursuant to section 4.32(b)(7) of 18 CFR of the Commission's
regulations, if any resource agency, Indian Tribe, or person believes
that an additional scientific study should be conducted in order to
form an adequate factual basis for a complete analysis of the
application on its merit, the resource agency, Indian Tribe, or person
must file a request for a study with the Commission not later than 60
days from the date of filing of the application, and serve a copy of
the request on the applicant.
l. Deadline for filing additional study requests and requests for
cooperating agency status: August 25, 2015.
The Commission strongly encourages electronic filing. Please file
additional study requests and requests for cooperating agency status
using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. For assistance, please contact FERC Online Support
at [email protected], (866) 208-3676 (toll free), or (202)
502-8659 (TTY). In lieu of electronic filing, please send a paper copy
to: Secretary, Federal Energy Regulatory Commission, 888 First Street
NE., Washington, DC 20426. The first page of any filing should include
docket number P-14550-001.
m. The application is not ready for environmental analysis at this
time.
n. The Hanover Pond Dam Hydroelectric Project would consist of: (1)
An existing 25-foot-high, 150-foot-long earth embankment dam with four
low-level sluice gates and a 250-foot-long concrete spillway; (2) the
existing approximately 71.0-acre Hanover Pond with a storage capacity
of 1,800 acre-feet at a normal operating elevation of about 87.3 feet
NGVD29; (3) an existing 175-foot-long, 16.0-foot-wide fish ladder; (4)
a new 8-foot-high, 12.5-foot-wide hydraulically-powered sluice gate
equipped with a new 8-foot-high, 17-foot-wide trashrack with 9-inch bar
spacing; (5) a new 78-foot-long, 12-foot-diameter buried precast
concrete penstock; (6) a new 46.5-foot-long, 11.65-foot wide Archimedes
screw generator unit, with an installed capacity of 192 kilowatts; (7)
a new 12-foot-high, 18-foot-long, 16.0-foot-wide concrete powerhouse
containing a new gearbox, generator, and electrical controls; (8) a new
15-foot-long, variable-width concrete tailrace; (9) a new 500-foot-
long, 35-kilovolt above ground transmission line connecting the
powerhouse to Connecticut Light and Power's distribution system; and
(10) appurtenant facilities. The estimated annual generation of the
proposed Hanover Pond Dam Project would be about 900 megawatt-hours.
o. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at http://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item h above.
You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
p. With this notice, we are initiating consultation with the New
Hampshire State Historic Preservation Officer (SHPO), as required by
section 106 of the National Historic Preservation Act and the
regulations of the Advisory Council on Historic Preservation, 36 CFR
800.4.
q. Procedural schedule: The application will be processed according
to the following preliminary schedule. Revisions to the schedule will
be made as appropriate (e.g., study requests and/or application
deficiencies may lengthen the schedule).
Issue Notice of Acceptance/Ready for Environmental Analysis--
September 2015
Issue EA/Order--February 2016
Dated: June 30, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-16685 Filed 7-7-15; 8:45 am]