[Federal Register Volume 80, Number 99 (Friday, May 22, 2015)]
[Proposed Rules]
[Pages 29562-29565]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-12432]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
18 CFR Part 11
[Docket No. RM15-18-000]
Commencement of Assessment of Annual Charges
AGENCY: Federal Energy Regulatory Commission, DOE.
ACTION: Notice of proposed rulemaking.
-----------------------------------------------------------------------
SUMMARY: The Federal Energy Regulatory Commission (Commission) proposes
to revise its regulations regarding when the Commission will commence
assessing annual charges to hydropower licensees and exemptees, other
than state or municipal entities, with respect to licenses and
exemptions authorizing unconstructed projects and new capacity.
Specifically, the Commission proposes to commence assessing annual
charges two years from the effective date of the project license,
exemption, or amendment authorizing new capacity, rather than on the
date that project construction starts. The proposed revisions will
provide administrative efficiency and promote certainty among
licensees, exemptees, and Commission staff as to when annual charges
will commence.
DATES: Comments are due July 21, 2015.
ADDRESSES: Comments, identified by docket number, may be filed in the
following ways:
Electronic filing through http://www.ferc.gov. Documents
created electronically using word processing software should be filed
in native applications or print-to-PDF format, rather than in a scanned
format.
Mail/Hand Delivery. Those unable to file electronically
may mail or hand-deliver comments to: Federal Energy Regulatory
Commission, Secretary of the Commission, 888 First Street NE.,
Washington, DC 20426.
Instructions: For detailed instructions for submitting comments and
additional information on the rulemaking process, see the Comment
Procedures section of this document.
FOR FURTHER INFORMATION CONTACT:
Tara DiJohn (Legal Information), Office of the General Counsel, Federal
Energy Regulatory Commission, 888 First Street NE., Washington, DC
20426, (202) 502-8671, [email protected].
Norman Richardson (Technical Information), Office of the Executive
Director, Federal Energy Regulatory Commission, 888 First Street NE.,
Washington, DC 20426, (202) 502-6219, [email protected].
SUPPLEMENTARY INFORMATION:
TABLE OF CONTENTS
Paragraph
Number
I. Background.............................................. 1.
II. Proposed Revisions..................................... 8.
III. Regulatory Requirements............................... 13.
A. Information Collection Statement.................... 13.
B. Environmental Analysis.............................. 14.
C. Regulatory Flexibility Act.......................... 15.
D. Comment Procedures.................................. 20.
E. Document Availability............................... 24.
I. Background
1. Section 10(e)(1) of the Federal Power Act (FPA),\1\ and section
3401 of the Omnibus Budget Reconciliation Act of 1986,\2\ require the
Federal Energy Regulatory Commission (Commission) to, among other
things, collect annual charges from licensees in order to reimburse the
United States for the costs of administering Part I of the FPA. The
Commission assesses these annual charges against licensees and
exemptees of projects with more than 1.5 megawatts (MW) of installed
capacity under section 11.1 of its regulations.\3\
---------------------------------------------------------------------------
\1\ 16 U.S.C. 803(e)(1) (2012).
\2\ 42 U.S.C. 7178 (2012).
\3\ 18 CFR 11.1 (2014).
---------------------------------------------------------------------------
2. Currently, the Commission begins assessing these annual charges
against licensees and exemptees with original licenses or exemptions
authorizing unconstructed projects on the date project construction
starts.\4\ The Commission also begins assessing annual charges for new
capacity, authorized by a relicense \5\ or an amendment of a license or
exemption, on the date that the construction to enable such capacity
starts.\6\ Because this proposed rule affects only projects with
respect to which annual charges are assessed when project construction
starts, we will not further discuss state or municipal projects,
projects that do not have installed capacity that exceeds 1.5 MW, or
constructed projects without newly authorized capacity.\7\
---------------------------------------------------------------------------
\4\ Id. (c)(5).
\5\ We use the term ``relicense'' to refer to any new or
subsequent license.
\6\ 18 CFR 11.1(c)(5) (2014). We refer to the addition of
capacity and a reduction of capacity (on occasion, capacity is
reduced as a result of construction, in which case annual charges
are lowered) as ``new capacity.''
\7\ Licensees or exemptees that are state or municipal entities
are already not assessed annual charges until project operation
commences. 18 CFR 11.1(d)(6) (2014). As noted above, the Commission
does not assess annual charges with respect to projects with
installed capacity of less than or equal to 1.5 MW. Licensees or
exemptees of constructed projects without new capacity are assessed
annual charges immediately, because their entire capacity is already
in place. See 18 CFR 11.1(c)(5) (2014).
---------------------------------------------------------------------------
[[Page 29563]]
3. Recently, to determine when project construction starts for
annual charges purposes, the Commission has included language in its
orders requiring the licensee or exemptee to notify the Commission when
project construction begins.\8\ Otherwise, the Commission has to
contact the licensee or exemptee to determine that date.
---------------------------------------------------------------------------
\8\ See, e.g., Eagle Crest Energy Company, 147 FERC ] 61,220, at
Article 207 (2014) (requiring the licensee to notify the Commission
of the date when it starts construction of the unconstructed
project); Wisconsin Electric Power Co., 144 FERC ] 62,268, at
ordering para. (G) (2013) (requiring the licensee to notify the
Commission of the date when it starts construction of the newly
authorized capacity).
---------------------------------------------------------------------------
4. Annual charges assessment should typically commence within two
years of the effective date of the order issuing a license, exemption,
or amendment adding capacity.\9\ Original licenses and relicenses
require a licensee to start construction no later than two years from
the effective license date pursuant to section 13 of the FPA.\10\
Similarly, exemptions of unconstructed projects include standard
exemption Article 3, which allows the Commission to revoke an exemption
if actual construction of the proposed generating facilities has not
begun within two years.\11\ Amendments adding new capacity include an
ordering paragraph that typically requires the licensee or exemptee to
start construction within two years of the amendment's issuance
date.\12\
---------------------------------------------------------------------------
\9\ Unless otherwise specified, orders are effective on the date
of issuance. 18 CFR 385.2007(c)(1) (2014). On occasion, a relicense
is issued before the expiration of the prior license. In that
circumstance, the effective date would not be the date of issuance
and would instead be established in the order to coincide with the
expiration of the prior license.
\10\ See 16 U.S.C. 806 (2012).
\11\ 18 CFR 4.94(c) (2014).
\12\ See, e.g., Northern States Power Co., 138 FERC ] 62,022, at
ordering para. (E) (2012).
---------------------------------------------------------------------------
5. In some cases, construction may not begin by the two-year
deadline and therefore annual charges assessment may begin more than
two years after the effective date (e.g., when a license's start of
construction deadline is extended by the Commission for an additional
period of no more than two years as permitted by section 13 of the
FPA).\13\ In rare cases, the Commission has granted requests for stay
of a license's start of construction deadline, or of an entire license,
in certain narrowly circumscribed circumstances.\14\ On average, the
Commission grants extensions and stays of a license's start of
construction deadline 3.4 and zero \15\ times per year, respectively.
---------------------------------------------------------------------------
\13\ 16 U.S.C. 806 (2012).
\14\ Such circumstances may exist where there are preconditions
to construction that are beyond a licensee's control but will likely
be resolved within a definitive period of time. See City of Broken
Bow, Oklahoma, 142 FERC ] 61,118, at PP 8-9 (2013) (staying the
start of construction deadline where City presented sufficient proof
it would not be able to timely start project construction for
reasons outside of its control).
\15\ From 2010 through 2014, the Commission granted three
requests for stays of construction deadlines to municipal licensees
with projects at U.S. Army Corps of Engineers' dams.
---------------------------------------------------------------------------
6. Similarly, exemptees may not begin construction by the deadline,
and may request that the Commission extend the deadline to start
construction. The Commission expects the prompt development of
exemption projects and that exemption applicants will anticipate and
solve problems that affect construction either before or during the
time that they seek their exemptions.\16\ From 2010 through 2014, the
Commission granted two extensions of start of construction deadlines,
or on average 0.4 times per year, to exemptees.
---------------------------------------------------------------------------
\16\ Ralph and Raleigh Coppedge, 28 FERC ] 61,363, at 61,654 &
n.11 (1984) (citing, FERC Stats. & Regs., Regulations Preambles
1977-1981 ] 30,204, at 31,368 (1980). Exemption from All or Part of
Part I of the Federal Power Act of Small Hydroelectric Power
Projects With an Installed Capacity of Five Megawatts or Less, Order
No. 106.
---------------------------------------------------------------------------
7. Licensees and exemptees can experience delays and may request an
extension of an amendment order's start of construction deadline as
well. From 2010 through 2014, the Commission granted six initial
extensions of a start of construction deadline, or an average of 1.2
extensions per year, to licensees granted amendments authorizing new
capacity.
II. Proposed Revisions
8. The Commission proposes to revise section 11.1(c)(5) of its
regulations regarding when it will commence assessing annual charges
with respect to hydropower licenses and exemptions authorizing
unconstructed projects and new capacity. Specifically, the Commission
proposes to commence assessing annual charges two years from the
effective date of an order issuing a license, exemption, or an
amendment authorizing additional capacity, rather than on the date
project construction starts.
9. The Commission anticipates the proposed rule will provide
administrative efficiency and foster certainty among licensees,
exemptees, and Commission staff as to when annual charges will
commence. Licensees and exemptees will no longer need to notify the
Commission when project construction starts for the purpose of
assessing annual charges and, in turn, the Commission will not have to
contact the licensee or exemptee for this purpose.
10. This proposed change, however, will affect those licensees and
exemptees that do not start construction within two years. Annual
charges will be assessed two years from the effective date of an order
issuing a license, exemption, or an amendment authorizing additional
capacity, regardless of whether the Commission has granted an extension
of time for construction or a stay of the construction deadline.\17\ As
noted above, on average, 5 (3.4 licenses + 0.4 exemptions + 1.2 license
amendments) affected projects each year receive extensions of the start
of construction deadline, and zero receive a stay of the start of
construction deadline.\18\
---------------------------------------------------------------------------
\17\ Additionally, this proposed change may affect any licensees
and exemptees that utilize a phase-in approach for adding capacity.
\18\ Stays of entire licenses, however, will continue to stay
the assessment of annual charges.
---------------------------------------------------------------------------
11. In addition, licensees and exemptees that do not start
construction by the deadline established in their license or exemption,
or as extended by the Commission, will be affected. If a licensee fails
to start construction within two years of its license's effective date
or as extended by the Commission, the Commission must terminate the
license pursuant to section 13 of the FPA.\19\ Similarly, as noted
above, standard exemption Article 3 states that the Commission may
revoke an exemption if the exemptee fails to start construction within
the time prescribed by the Commission. From 2010 through 2014, the
Commission terminated one license, or an average of 0.2 licenses per
year, and no exemptions. Therefore, we estimate that annually 0.2
licenses would have been assessed annual charges after the two-year
deadline until their termination for failure to construct.
---------------------------------------------------------------------------
\19\ 16 U.S.C. 806 (2012).
---------------------------------------------------------------------------
12. In sum, we anticipate that, on average, 5.2 (5 extensions + 0.2
terminations) licensees and/or exemptees per year will begin paying
annual charges before starting construction or before the Commission
terminates its license or revokes its exemption under the proposed
rule.
[[Page 29564]]
III. Regulatory Requirements
A. Information Collection Statement
13. The Paperwork Reduction Act \20\ requires each federal agency
to seek and obtain Office of Management and Budget (OMB) approval
before undertaking a collection of information directed to ten or more
persons or contained in a rule of general applicability. OMB
regulations require approval of certain information collection
requirements contemplated by proposed rules.\21\ The proposed revisions
discussed above do not impose or alter existing reporting or
recordkeeping requirements on applicable entities as defined by the
Paperwork Reduction Act.\22\ Therefore, the Commission will submit this
proposed rule to OMB for informational purposes only.
---------------------------------------------------------------------------
\20\ 44 U.S.C. 3501-3521 (2012).
\21\ See 5 CFR 1320.11 (2014).
\22\ 44 U.S.C. 3502(2)-(3) (2012).
---------------------------------------------------------------------------
B. Environmental Analysis
14. The Commission is required to prepare an Environmental
Assessment or an Environmental Impact Statement for any action that may
have a significant adverse effect on the human environment.\23\
Commission actions concerning annual charges are categorically exempt
from this requirement.\24\
---------------------------------------------------------------------------
\23\ Regulations Implementing the National Environmental Policy
Act of 1969, Order No. 486, 52 FR 47,897 (Dec. 17, 1987), FERC
Stats. & Regs., Regulations Preambles 1986-1990 ] 30,783 (1987).
\24\ See 18 CFR 380.4 (a)(11) (2014).
---------------------------------------------------------------------------
C. Regulatory Flexibility Act
15. The Regulatory Flexibility Act of 1980 (RFA) \25\ generally
requires a description and analysis of proposed and final rules that
will have significant economic impact on a substantial number of small
entities. The RFA mandates consideration of regulatory alternatives
that accomplish the stated objectives of a proposed rule and minimize
any significant economic impact on a substantial number of small
entities.\26\
---------------------------------------------------------------------------
\25\ 5 U.S.C. 601-612 (2012).
\26\ 5 U.S.C. 603(c) (2012).
---------------------------------------------------------------------------
16. The Small Business Administration's (SBA) Office of Size
Standards develops the numerical definition of a small business.\27\
The SBA revised its size standard for electric utilities (effective
January 22, 2014) from a standard based on megawatt hours to a standard
based on the number of employees, including affiliates.\28\ Under SBA's
current size standards, a hydroelectric generator is small if,
including its affiliates, it employs 500 or fewer people.\29\ The
Commission, however, currently does not require information regarding
the number of individuals employed by hydroelectric generators to
administer Part I of the FPA, and therefore, is unable to estimate the
number of small entities using the new SBA definitions. Regardless, the
Commission anticipates that the proposed rule will affect few small
hydroelectric generators.
---------------------------------------------------------------------------
\27\ 13 CFR 121.101 (2014).
\28\ SBA Final Rule on ``Small Business Size Standards:
Utilities,'' 78 FR 77,343 (Dec. 23, 2013).
\29\ 13 CFR 121.201, Sector 22, Utilities (2014).
---------------------------------------------------------------------------
17. As noted earlier, the proposed rule will only affect non-state
or municipal licensed projects with an installed capacity exceeding 1.5
MW that are unconstructed or have newly authorized capacity. From 2010
through 2014, the Commission issued on average 3.6 original licenses
and 0.4 exemptions per year authorizing unconstructed projects to
affected licensees and exemptees, and 1.6 relicenses and 5 license
amendments per year authorizing new capacity. In sum, on average a
total of 10.6 licensees and exemptees may be affected by the proposed
rule annually.
18. Of the 10.6 total entities, only those that do not start
construction within two years, or receive a stay of their license, will
be negatively affected by the acceleration of annual charges. As noted
above, on average, 5.2 affected licensees and/or exemptees per year do
not start construction within two years. Conversely, small entities
that would otherwise start construction before the two year mark after
their effective date will benefit from the proposed rule as it delays
the commencement of their annual charges.
19. Accordingly, pursuant to section 605(b) of the RFA, the
Commission certifies that this proposed rule will not have a
significant economic impact on a substantial number of small entities.
D. Comment Procedures
20. The Commission invites interested persons to submit comments on
the matters and issues proposed in this notice to be adopted, including
any related matters or alternative proposals that commenters may wish
to discuss. Comments are due July 21, 2015. Comments must refer to
Docket No. RM15-18-000, and must include the commenter's name, the
organization they represent, if applicable, and their address.
21. The Commission encourages comments to be filed electronically
via the eFiling link on the Commission's Web site at http://www.ferc.gov. The Commission accepts most standard word processing
formats. Documents created electronically using word processing
software should be filed in native applications or print-to-PDF format
and not in a scanned format. Commenters filing electronically do not
need to make a paper filing.
22. Commenters that are not able to file comments electronically
must send an original of their comments to: Federal Energy Regulatory
Commission, Secretary of the Commission, 888 First Street NE.,
Washington, DC 20426.
23. All comments will be placed in the Commission's public files
and may be viewed, printed, or downloaded remotely as described in the
Document Availability section below. Commenters on this proposal are
not required to serve copies of their comments on other commenters.
E. Document Availability
24. In addition to publishing the full text of this document in the
Federal Register, the Commission provides all interested persons an
opportunity to view and print the contents of this document via the
Internet through the Commission's Home Page (http://www.ferc.gov) and
in the Commission's Public Reference Room during normal business hours
(8:30 a.m. to 5:00 p.m. Eastern time) at 888 First Street NE., Room 2A,
Washington, DC 20426.
25. From the Commission's Home Page on the Internet, this
information is available on eLibrary. The full text of this document is
available on eLibrary in PDF and Microsoft Word format for viewing,
printing, and downloading. To access this document in eLibrary, type
the docket number excluding the last three digits of this document in
the docket number field.
26. User assistance is available for eLibrary and the Commission's
Web site during normal business hours from the Commission's Online
Support at (202) 502-6652 (toll free at 1-866-208-3676) or email at
[email protected], or the Public Reference Room at (202) 502-
8371, TTY (202) 502-8659. Email the Public Reference Room at
[email protected].
List of Subjects in 18 CFR Part 11
Electric power, Reporting and recordkeeping requirements.
By direction of the Commission.
Issued: May 14, 2015
Nathaniel J. Davis, Sr.,
Deputy Secretary.
In consideration of the foregoing, the Commission proposes to amend
Part 11, Chapter I, Title 18, Code of Federal Regulations, as follows:
[[Page 29565]]
PART 11--ANNUAL CHARGES UNDER PART I OF THE FEDERAL POWER ACT
0
1. The authority citation for Part 11 continues to read as follows:
Authority: 16 U.S.C. 792-828c; 42 U.S.C. 7101-7352.
0
2. Revise Sec. 11.1(c)(5) to read as follows:
Sec. 11.1 Costs of administration.
* * * * *
(c) * * *
(5) For unconstructed projects, the assessments start two years
after the effective date of the license or exemption. For constructed
projects, the assessments start on the effective date of the license or
exemption, except for any new capacity authorized therein. The
assessments for new authorized capacity start two years after the
effective date of the license, exemption, or amendment, authorizing
such new capacity. In the event that assessment commences during a
fiscal year, the charges will be prorated based on the date of
commencement.
* * * * *
[FR Doc. 2015-12432 Filed 5-21-15; 8:45 am]