[Federal Register Volume 80, Number 52 (Wednesday, March 18, 2015)]
[Notices]
[Pages 14105-14106]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-06207]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP15-102-000]
Rockies Express Pipeline LLC: Notice of Application
Take notice that on March 2, 2015, Rockies Express Pipeline LLC,
(Rockies Express) filed an application with the Federal Energy
Regulatory Commission pursuant to section 7(c) of the Natural Gas Act
(NGA) requesting a certificate of public convenience and necessity
authorizing the operation as section 7(c) jurisdictional facilities
certain pipeline assets, located in Noble and Monroe Counties, Ohio,
that heretofore have been constructed and operated solely for the
purpose of providing transportation services permitted under section
311 of the Natural Gas Policy Act, all as more completely described in
the Application. This filing is available for review at the Commission
in the Public Reference Room or may be viewed on the Commission's Web
site web at http://www.ferc.gov using the ``eLibrary'' link. Enter the
docket number excluding the last three digits in the docket number
field to access the document. For assistance, contact FERC at
[email protected] or call toll-free, (886) 208-3676 or TYY,
(202) 502-8659.
Any questions regarding the application should be directed to David
Haag, Vice President, Regulatory, Rockies Express Pipeline LLC, 370 Van
Gordon Street, Lakewood, Colorado 80228-8304, phone (303) 763-3258.
Specifically, the facilities for which Rockies Express is
requesting NGA section 7(c) authority were the subject of two advance
notification filings made by Rockies Express on August 26, 2013 in
Docket No. CP13-539-000 (Seneca Lateral Project) and on April 18, 2014
in Docket No. CP14-194-000 (Seneca Compressor Expansion Project). The
facilities consist of: (1) Approximately 14.7 miles of 24-inch lateral
pipeline extending from an interconnect with MarkWest Energy Partners,
L.P. Seneca Processing Plant to Rockies Express' mainline; (2)
measurement facilities; and (3) 15,980 horsepower of booster
compression. Rockies Express proposes incremental firm and
interruptible transportation recourse rates based on the cost of the
facilities of $135,950,429.
Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9,
within 90 days of this Notice the Commission staff will either:
Complete its environmental assessment (EA) and place it into the
Commission's public record (eLibrary) for this proceeding; or issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) or EA for this
proposal. The filing of the EA in the Commission's public record for
this proceeding or the issuance of a Notice of Schedule for
Environmental Review will serve to notify federal and state agencies of
the timing for the completion of all necessary reviews, and the
subsequent need to complete all federal authorizations within 90 days
of the date of issuance of the Commission staff's FEIS or EA.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the comment date stated below file with the Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit seven copies of filings made in the proceeding with the
Commission and must mail a copy to the applicant and to every other
party. Only parties to the proceeding can ask for court review of
Commission orders in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commentors will be
[[Page 14106]]
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commentors will not be required to serve copies of filed
documents on all other parties. However, the non-party commentors will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
The Commission strongly encourages electronic filings of comments,
protests and interventions in lieu of paper using the ``eFiling'' link
at http://www.ferc.gov. Persons unable to file electronically should
submit an original and seven copies of the protest or intervention to
the Federal Energy Regulatory Commission, 888 First Street NE.,
Washington, DC 20426.
Comment Date: 5 p.m. Eastern Time on April 2, 2015.
Dated: March 12, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-06207 Filed 3-17-15; 8:45 am]
BILLING CODE P