[Federal Register Volume 80, Number 20 (Friday, January 30, 2015)]
[Notices]
[Pages 5104-5105]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-01730]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP14-96-000]
Algonquin Gas Transmission, LLC; Notice of Availability of the
Final Environmental Impact Statement for the Proposed Algonquin
Incremental Market Project
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) has prepared a final environmental impact statement (EIS)
for the Algonquin Incremental Market Project (AIM Project), proposed by
Algonquin Gas Transmission, LLC (Algonquin) in the above-referenced
docket. Algonquin requests authorization to expand its existing
pipeline system from an interconnection at Ramapo, New York to deliver
up to 342,000 dekatherms per day of natural gas transportation service
to the Connecticut, Rhode Island, and Massachusetts markets.
The final EIS assesses the potential environmental effects of the
construction and operation of the AIM Project in accordance with the
requirements of the National Environmental Policy Act (NEPA). The FERC
staff concludes that approval of the proposed project would result in
some adverse environmental impacts; however, most of these impacts
would be reduced to less-than-significant levels with the
implementation of Algonquin's proposed mitigation and the additional
measures recommended in the final EIS.
The U.S. Environmental Protection Agency, the U.S. Army Corps of
Engineers, and the U.S. Department of Transportation's Pipeline and
Hazardous Materials Safety Administration participated as cooperating
agencies in the preparation of the EIS. Cooperating agencies have
jurisdiction by law or special expertise with respect to resources
potentially affected by the proposal and participate in the NEPA
analysis. Although the cooperating agencies provided input to the
conclusions and recommendations presented in the final EIS, the
agencies will present their own conclusions and recommendations in
their respective records of decision or determinations for the AIM
Project.
The final EIS addresses the potential environmental effects of the
construction and operation of about 37.4 miles of pipeline composed of
the following facilities:
Replacement of 26.3 miles of existing pipeline with a 16-
and 42-inch-diameter pipeline;
extension of an existing loop \1\ pipeline with about 3.3
miles of additional 12- and 36-inch-diameter pipeline within
Algonquin's existing right-of-way; and
---------------------------------------------------------------------------
\1\ A pipeline loop is a segment of pipe constructed parallel to
an existing pipeline to increase capacity.
---------------------------------------------------------------------------
installation of about 7.8 miles of new 16-, 24-, and 42-
inch-diameter pipeline.
The AIM Project's proposed aboveground facilities consist of
modifications to six existing compressor stations, to add a total
81,620 horsepower, in New York, Connecticut, and Rhode Island.
Algonquin also proposes to abandon four existing compressor units for a
total of 10,800 horsepower at one compressor station in New York.
The FERC staff mailed copies of the final EIS to federal, state,
and local government representatives and agencies; elected officials;
environmental and public interest groups; Native American tribes;
potentially affected landowners and other interested individuals and
groups; newspapers and libraries in the area of the project; and
parties to this proceeding. Paper copy versions of this final EIS were
mailed to those specifically requesting them; all others received a CD
version. However, we note that due to its voluminous size, the comment
responses are provided as an electronic-only volume (Volume II) on a CD
that was mailed to the entire mailing list. In addition, the final EIS
is available for public viewing on the FERC's Web site (www.ferc.gov)
using the eLibrary link. A limited number of copies are available for
distribution and public inspection at: Federal Energy Regulatory
Commission, Public Reference Room, 888 First Street NE., Room 2A,
Washington, DC 20426, (202) 502-8371.
In accordance with the Council on Environmental Quality's (CEQ)
regulations implementing the NEPA, no agency decision on a proposed
action may be made until 30 days after the U.S. Environmental
Protection Agency publishes a notice of availability of a final EIS.
However, the CEQ regulations provide an exception to this rule when an
agency decision is subject to a formal internal appeal process that
allows other agencies or the public to make their views known. In such
cases, an agency decision may be made at the same time the notice of
the final EIS is published, allowing both periods to run concurrently.
The Commission decision for this proposed action is subject to a 30-day
rehearing period.
Additional information about the proposed project is available from
the Commission's Office of External Affairs, at (866) 208-FERC, or on
the FERC Web site (www.ferc.gov) using the eLibrary link. Click on the
eLibrary link, click on ``General Search,'' and enter the docket number
excluding the last three digits in the Docket Number field (i.e., CP14-
96). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
[email protected] or toll free at (866) 208-3676; for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission,
[[Page 5105]]
such as orders, notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription that allows you to keep track of all formal issuances and
submittals in specific dockets. This can reduce the amount of time you
spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Dated: January 23, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-01730 Filed 1-29-15; 8:45 am]
BILLING CODE 6717-01-P