[Federal Register Volume 80, Number 18 (Wednesday, January 28, 2015)]
[Notices]
[Pages 4558-4560]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2015-01497]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. PF15-2-000]
Venture Global Calcasieu Pass, LLC; Notice of Intent To Prepare
an Environmental Impact Statement for the Planned Calcasieu Pass
Project, and Request for Comments on Environmental Issues, and Notice
of Public Scoping Meeting
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental impact statement (EIS) that
will discuss the environmental impacts of the Calcasieu Pass Project
involving construction and operation of LNG export facilities by
Venture Global Calcasieu Pass, LLC (Venture Global) in Cameron Parish,
Louisiana. The Commission will use this EIS in its decision-making
process to determine whether the project is in the public convenience
and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. Your input will help the Commission staff
determine what issues they need to evaluate in the EIS. Please note
that the scoping period will close on February 19, 2015.
You may submit comments in written form or verbally. Further
details on how to submit written comments are in the Public
Participation section of this notice. If you sent comments on this
project to the Commission before the opening of this docket on October
10, 2014, you will need to file those comments in Docket No. PF15-2-000
to ensure they are considered as part of this proceeding. In lieu of or
in addition to sending written comments, the Commission invites you to
attend the public scoping meeting scheduled as follows: FERC Public
Scoping Meeting, Calcasieu Pass Project, February 5, 2015/7-9 p.m. CST,
Cameron Parish School Board Educational Conference Center, 510 Marshall
Street, Cameron, LA 70631.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this planned
project and encourage them to comment on their areas of concern.
The purpose of this scoping meeting is to provide the public an
opportunity to learn more about the Commission's environmental review
process, and to verbally comment on the project. The scoping meeting
will start at 6:00 p.m. and representatives from Venture Global will be
present one hour prior to the start of the meeting to answer questions
about the project. Additionally, Venture Global has established an
Internet Web site at www.venturegloballng.com that will be updated as
the environmental review of its project proceeds.
Affected landowners and interested groups and individuals are
encouraged to attend the scoping meetings and present comments on the
issues they believe should be addressed in the EIS. A transcript of the
meeting will be added to the Commission's administrative record to
ensure that your comments are accurately recorded.
If you are a landowner receiving this notice, a pipeline company
representative may contact you about the acquisition of an easement to
construct, operate, and maintain the planned facilities. The company
would seek to negotiate a mutually acceptable agreement. However, if
the Commission approves the project, that approval conveys with it the
right of eminent domain. Therefore, if easement negotiations fail to
produce an agreement, the pipeline company could initiate condemnation
proceedings where compensation would be determined in accordance with
state law.
A fact sheet prepared by the FERC entitled ``An Interstate Natural
Gas Facility On My Land? What Do I Need To Know?'' is available for
viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses
a number of typically asked questions, including the use of eminent
domain and how to participate in the Commission's proceedings.
Summary of the Planned Project
Venture Global plans to construct and operate an LNG export
facility in Cameron Parish, Louisiana adjacent to the Calcasieu Ship
Channel. The facility would receive natural gas from North American
sources and would liquefy and store it for export. When constructed,
the project could process about 487.2 billion cubic feet per year (Bcf/
yr) of natural gas.
The Calcasieu Pass project would consist of the following
facilities:
Ten (10) liquefaction blocks;
two (2) LNG storage tanks, each with approximately 200,000
cubic meter (``m\3\'') storage capacity;
two (2) marine berthing docks, to accommodate LNG carriers
ranging from 120,000 m\3\ to 185,000 m\3\ of carrying capacity;
a temporary floating LNG storage vessel berthed at one of
the LNG berthing docks, which would be discontinued after the first
permanent LNG storage tank becomes operational;
a turning basin on the Calcasieu Ship Channel;
a utility dock;
a gas-fired electric generation facility with generating
capacity of approximately 600 megawatts (``MW'') that will be
constructed to provide power for the project facilities;
two natural gas pipelines to connect to existing
transmission pipelines, a 23.8-mile-long, 42-inch-diameter pipeline and
a 42-inch-diameter, 18.5-mile-long pipeline;
a Gas Gate Station to receive gas from the two lateral
pipelines and will include pig \1\ receivers, filter/separators,
custody transfer meters, pressure regulators, emergency shutdown
valves, and gas analyzers;
---------------------------------------------------------------------------
\1\ A ``pig'' is a tool that the pipeline company inserts into
and pushes through the pipeline for cleaning the pipeline,
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------
various buildings, including administration, control
rooms, electrical equipment, workshop, and warehouse buildings and
structures;
connection to the existing municipal water supply for
construction and potable water requirements, and the potential drilling
of groundwater wells to allow for water-cooling of the power plant;
facilities associated with the project site's
communication system; and
facilities associated with plant safety and security.
The general location of the project facilities is shown in Appendix
1.\2\
---------------------------------------------------------------------------
\2\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of the appendices were sent to all
those receiving this notice in the mail and are available at
www.ferc.gov using the link called ``eLibrary'' or from the
Commission's Public Reference Room, 888 First Street NE.,
Washington, DC 20426, or call (202) 502-8371. For instructions on
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the planned facilities would disturb about 914.1
acres of land for the aboveground facilities and the pipeline.
Following construction, Venture Global would maintain about 347.6 acres
for permanent operation of the project's facilities and pipeline.
The Terminal facilities will occupy an approximately 203.6-acre
property
[[Page 4559]]
adjacent to the Calcasieu Ship Channel. Of the 203.6 acres, 86.8 acres
will support permanent operational facilities and 116.8 acres will be
used for temporary workspace. Of the 86.8 acres supporting permanent
operational facilities, 8.6 acres will be converted to open water
through excavation and dredging to create the LNG berthing area.
Collectively, the approximately 42.3-mile long pipelines would
require 665.7 acres of construction workspace (of which 415.78 acres
will be temporary workspace and 250.0 acres will remain as the
permanent operational right-of-way).
The EIS Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\3\ to discover and address concerns the public may have about
proposals. This process is referred to as scoping. The main goal of the
scoping process is to focus the analysis in the EIS on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EIS. We will
consider all filed comments during the preparation of the EIS.
---------------------------------------------------------------------------
\3\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EIS we will discuss impacts that could occur as a result of
the construction and operation of the planned project under these
general headings:
Geology and soils;
land use;
socioeconomics;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species;
reliability and safety; and
cumulative impacts.
We will also evaluate possible alternatives to the planned project
or portions of the project, and make recommendations on how to lessen
or avoid impacts on the various resource areas.
Although no formal application has been filed, we have already
initiated our NEPA review under the Commission's pre-filing process.
The purpose of the pre-filing process is to encourage early involvement
of interested stakeholders and to identify and resolve issues before
the FERC receives an application. As part of our pre-filing review, we
have begun to contact some federal and state agencies to discuss their
involvement in the scoping process and the preparation of the EIS.
The EIS will present our independent analysis of the issues. We
will publish and distribute the draft EIS for public comment. After the
comment period, we will consider all timely comments and revise the
document, as necessary, before issuing a final EIS. To ensure we have
the opportunity to consider and address your comments, please carefully
follow the instructions in the Public Participation section on the
following page.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues
related to this project to formally cooperate with us in the
preparation of the EIS.\4\ Agencies that would like to request
cooperating agency status should follow the instructions for filing
comments provided under the Public Participation section of this
notice.
---------------------------------------------------------------------------
\4\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the Louisiana State Historic Preservation Office (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\5\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPO as the project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EIS for this project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\5\ The Advisory Council on Historic Preservation regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Currently Identified Environmental Issues
We have already identified several issues that we think deserve
attention based on a preliminary review of the planned facilities and
the environmental information provided by Venture Global. This
preliminary list of issues may change based on your comments and our
analysis:
Protected species;
cultural resources;
water resources;
Coastal Zone Management Act;
fisheries;
site alternatives;
ship traffic;
public safety; and
cumulative impacts.
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that the Commission receives them in Washington, DC on or before
February 19, 2015.
For your convenience, there are three methods you can use to submit
your comments to the Commission. In all instances, please reference the
project docket number (PF15-2-000) with your submission. The Commission
encourages electronic filing of comments and has expert staff available
to assist you at (202) 502-8258 or [email protected].
(1) You can file your comments electronically using the eComment
feature located on the Commission's Web site (www.ferc.gov) under the
link to Documents and Filings. This is an easy method for interested
persons to submit brief, text-only comments on a project;
(2) You can file your comments electronically using the eFiling
feature located on the Commission's Web site (www.ferc.gov) under the
link to Documents and Filings. With eFiling, you can provide comments
in a variety of formats by attaching them as a file with your
submission. New eFiling users must first create an account by clicking
on ``eRegister.'' You must select the type of filing you are making. If
you are filing a comment on a particular project, please select
``Comment on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the
[[Page 4560]]
following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who are potential right-of-way grantors, whose property
may be used temporarily for project purposes, or who own homes within
certain distances of aboveground facilities, and anyone who submits
comments on the project. We will update the environmental mailing list
as the analysis proceeds to ensure that we send the information related
to this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
planned project.
Copies of the completed draft EIS will be sent to the environmental
mailing list for public review and comment. If you would prefer to
receive a paper copy of the document instead of the CD version or would
like to remove your name from the mailing list, please return the
attached Information Request (Appendix 2).
Becoming an Intervenor
Once Venture Global files its application with the Commission, you
may want to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are in
the User's Guide under the ``e-filing'' link on the Commission's Web
site. Please note that the Commission will not accept requests for
intervenor status at this time. You must wait until the Commission
receives a formal application for the project.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., PF15-
2). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
[email protected] or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: January 20, 2015.
Kimberly D. Bose,
Secretary.
[FR Doc. 2015-01497 Filed 1-27-15; 8:45 am]
BILLING CODE 6717-01-P