DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP14-514-000]
ANR Pipeline Company; Notice of Intent To Prepare an
Environmental Assessment for the Proposed Sulphur Springs Compression
Project and Request for Comments on Environmental Issues
August 15, 2014.
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
discuss the environmental impacts of the Sulphur Springs Compression
Project involving construction and operation of facilities by ANR
Pipeline Company (ANR) in Henry County, Indiana. The Commission will
use this EA in its decision-making process to determine whether the
project is in the public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. Your input will help the Commission staff
determine what issues they need to evaluate in the EA. Please note that
the scoping period will close on September 15, 2014.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives should notify their constituents of this proposed
project and encourage them to comment on their areas of concern.
ANR provided landowners with a fact sheet prepared by the FERC
entitled ``An Interstate Natural Gas Facility On My Land? What Do I
Need To Know?'' This fact sheet addresses a number of typically-asked
questions, including the use of eminent domain and how to participate
in the Commission's proceedings. It is also available for viewing on
the FERC Web site (www.ferc.gov).
Summary of the Proposed Project
ANR proposes to construct and operate one new compressor unit and
appurtenant facilities at its existing Sulphur Springs Compressor
Station in Henry County, Indiana. The Sulphur Springs Compression
Project would provide about 133.6 million standard cubic feet of
natural gas per day to ANR's wholly owned portion of the Lebanon
Lateral which connects the Glen Karn meter facilities in Darke County,
Ohio to the Sulphur Springs Compressor Station.
[[Page 49509]]
According to ANR, its project would increase reverse flow
capability on its system and provide greater reliability, flexibility,
and security to existing shippers.
The Sulphur Springs Compression Project consists of the following
facilities:
An approximately 10,915 horsepower Solar Taurus 70 turbine
with C65 compressor;
exhaust silencer, air inlet filtration, and lube oil
cooling equipment;
two high pressure gas coolers;
high-pressure gas filter/separator;
associated piping, valves, fittings, regulators, cables,
conduits, overhead cable trays, cathodic protection devices, parking
areas, and access road;
compressor building to house the new turbine;
control building;
natural gas-fired boiler; and
aboveground storage tanks.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Construction
Construction of the proposed aboveground facilities would disturb
about 24.3 acres of open and industrial/commercial land owned by ANR.
Of this total, approximately 1.1 acres would be permanently impacted to
accommodate the new facilities. Remaining disturbed areas would be
revegetated or otherwise returned to pre-existing conditions.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
Geology and soils;
land use;
water use and quality;
vegetation and wildlife;
air quality and noise;
public safety; and
cumulative impacts.
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through eLibrary. Depending on
the comments received during the scoping process, we may also publish
and distribute the EA to the public for an allotted comment period. We
will consider all comments on the EA before making our recommendations
to the Commission. To ensure we have the opportunity to consider and
address your comments, please carefully follow the instructions in the
Public Participation section beginning on page 4.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\3\ Agencies that would like to request cooperating agency status
should follow the instructions for filing comments provided under the
Public Participation section of this notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that the Commission receives them in Washington, DC on or before
September 15, 2014.
For your convenience, there are three methods which you can use to
submit your comments to the Commission. In all instances please
reference the project docket number (CP14-514-000) with your
submission. The Commission encourages electronic filing of comments and
has expert staff available to assist you at (202) 502-8258 or
[email protected].
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for interested persons to
submit brief, text-only comments on a project;
(2) You can file your comments electronically using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' You must select the type of filing you are making. If
you are filing a comment on a particular project, please select
``Comment on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
Environmental Mailing List
The environmental mailing list includes federal, state, and local
government representatives and agencies; elected officials;
environmental and public interest groups; Native American Tribes; other
interested parties; and local libraries and newspapers. This list also
includes all affected landowners (as defined in the Commission's
regulations) who own homes within certain distances of aboveground
facilities and anyone who submits comments on the project. We will
update the environmental mailing list as the analysis proceeds to
ensure that we send the information related to this environmental
review to all individuals, organizations, and government entities
interested in and/or potentially affected by the proposed project.
If we publish and distribute the EA, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's
[[Page 49510]]
proceeding. Intervenors play a more formal role in the process and are
able to file briefs, appear at hearings, and be heard by the courts if
they choose to appeal the Commission's final ruling. An intervenor
formally participates in the proceeding by filing a request to
intervene. Instructions for becoming an intervenor are in the User's
Guide under the ``e-filing'' link on the Commission's Web site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP14-
514). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
[email protected] or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-19861 Filed 8-20-14; 8:45 am]
BILLING CODE 6717-01-P