[Docket Nos. CP14-347-000, PF13-9-000]
Magnolia LNG, LLC; Notice of Application
Take notice that on April 30, 2014, Magnolia LNG, LLC (Magnolia),
1001 McKinney, Suite 400, Houston, Texas 77002, filed in Docket No.
CP14-347-000, an application pursuant to section 3(a) of the Natural
Gas Act (NGA) for authority to construct and operate liquefaction and
export facilities located at Magnolia LNG's proposed site near Lake
Charles, Louisiana. Specifically, Magnolia proposes to develop a
liquefied natural gas (LNG) facility capable of producing approximately
8 metric tonnes per annum (mtpa) of LNG for domestic consumption and
export to foreign markets. The project would receive natural gas via a
tie-in to an existing interstate pipeline owned by Kinder Morgan
Louisiana Pipeline, LLC, all as more fully set forth in the application
which is on file with the Commission and open to public inspection.
This filing may also be viewed on the Commission's Web site at http://www.ferc.gov using the ``eLibrary'' link. Enter the docket number,
excluding the last three digits, in the docket number field to access
the document. For assistance, call (202) 502-8659 or TTY, (202) 208-
3676.
Any questions regarding this application should be directed to
Ernie Megginson, Vice President, Development, Magnolia LNG, LLC, 1001
McKinney, Suite 400, Houston, TX 77002, by phone: (713) 815-6900, by
fax: (713) 815-6905 or email: [email protected].
On March 20, 2013, the Commission staff granted the Magnolia's
request to utilize the Pre-Filing Process and assigned Docket No. PF13-
9-000 to staff activities involved the Magnolia LNG Project. Now as of
filing the April 30, 2014 application, the Pre-Filing Process for this
project has ended. From this time forward, this proceeding will be
conducted in Docket No. CP14-347-000, as noted in the caption of this
Notice.
Pursuant to section 157.9 of the Commission's rules, 18 CFR Sec.
157.9, within 90 days of this Notice, the Commission staff will issue a
Notice of Schedule for Environmental Review. If a Notice of Schedule
for Environmental Review is issued, it will indicate, among other
milestones, the anticipated date for the Commission staff's issuance of
the final environmental impact statement (FEIS) for this proposal. The
issuance of a Notice of Schedule for Environmental Review will serve to
notify federal and state agencies of the timing for the completion of
all necessary reviews, and the subsequent need to complete all federal
authorizations within 90 days of the date of issuance of the Commission
staff's FEIS.
There are two ways to become involved in the Commission's review of
this project. First, any person wishing to obtain legal status by
becoming a party to the proceedings for this project should, on or
before the below listed comment date, file with the Federal Energy
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a
motion to intervene in accordance with the requirements of the
Commission's Rules of Practice and Procedure (18 CFR 385.214 or
385.211) and the Regulations under the NGA (18 CFR 157.10). A person
obtaining party status will be placed on the service list maintained by
the Secretary of the Commission and will receive copies of all
documents filed by the applicant and by all other parties. A party must
submit 7 copies of filings made with the Commission and must mail a
copy to the applicant and to every other party in the proceeding. Only
parties to the proceeding can ask for court review of Commission orders
in the proceeding.
However, a person does not have to intervene in order to have
comments considered. The second way to participate is by filing with
the Secretary of the Commission, as soon as possible, an original and
two copies of comments in support of or in opposition to this project.
The Commission will consider these comments in determining the
appropriate action to be taken, but the filing of a comment alone will
not serve to make the filer a party to the proceeding. The Commission's
rules require that persons filing comments in opposition to the project
provide copies of their protests only to the party or parties directly
involved in the protest.
Persons who wish to comment only on the environmental review of
this project should submit an original and two copies of their comments
to the Secretary of the Commission. Environmental commenters will be
placed on the Commission's environmental mailing list, will receive
copies of the environmental documents, and will be notified of meetings
associated with the Commission's environmental review process.
Environmental commenters will not be required to serve copies of filed
documents on all other parties. However, the non-party commenters will
not receive copies of all documents filed by other parties or issued by
the Commission (except for the mailing of environmental documents
issued by the Commission) and will not have the right to seek court
review of the Commission's final order.
Motions to intervene, protests and comments may be filed
electronically via the internet in lieu of paper; see, 18 CFR
385.2001(a)(1)(iii) and the instructions on the Commission's Web site
under the ``e-Filing'' link. The Commission strongly encourages
electronic filings.
Comment Date: 5:00 p.m. Eastern Time on June 3, 2014.
Dated: May 13, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-11719 Filed 5-20-14; 8:45 am]