Howard A. Hanson Power, LLC; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On March 3, 2014, Howard A. Hanson Power, LLC, filed an application 
for a preliminary permit, pursuant to section 4(f) of the Federal Power 
Act (FPA), proposing to study the feasibility of the Howard A. Hanson 
Hydroelectric Project (Hanson Project or project) to be located on 
Howard A. Hanson reservoir near Enumclaw in King County, Washington. 
The sole purpose of a preliminary permit, if issued, is to grant the 
permit holder priority to file a license application during the permit 
term. A preliminary permit does not authorize the permit holder to 
perform any land-disturbing activities or otherwise enter upon lands or 
waters owned by others without the owners' express permission.
    The proposed project would consist of the following: (1) An 
existing earth and rockfill dam on the Howard A. Hanson reservoir 
having a total storage capacity of 136,700 acre-feet at a normal 
maximum operating elevation of 1,141 feet mean sea level; (2) four 150 
to 300-foot-long, 48-inch-diameter steel penstocks each housing an 
inline turbine/generation unit for a total capacity of 5 megawatts; (3) 
an overhead or buried 1-mile-long, 15-kilovolt transmission line 
extending from the project to an existing local utility's line (the 
point of interconnection); and (4) appurtenant facilities. The 
estimated annual generation of the Hanson Project would be 26 gigawatt-
hours.
    Applicant Contact: Mr. Magn[uacute]s J[oacute]hannesson, Howard A. 
Hanson Power, LLC, 46 Peninsula Center, Ste. E, Rolling Hills Estates, 
CA 90274, phone 310-699-6400, email [email protected].
    FERC Contact: Ryan Hansen, phone: (202) 502-8074, email 
[email protected].
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent,

[[Page 29184]]

and competing applications using the Commission's eFiling system at 
http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. The first page of any filing should 
include docket number P-14594-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of 
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14594) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: May 14, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-11712 Filed 5-20-14; 8:45 am]