[Federal Register Volume 79, Number 83 (Wednesday, April 30, 2014)]
[Notices]
[Pages 24460-24462]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2014-09879]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 52-025 and 52-026; NRC-2008-0252]
Vogtle Electric Generating Plant, Units 3 and 4; Southern Nuclear
Operating Company; Turbine Building Battery Room and Electrical Changes
AGENCY: Nuclear Regulatory Commission.
ACTION: Exemption and combined license amendment; issuance.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is granting an
exemption to allow a departure from the certification information of
Tier 1 of the generic design control document (DCD) and issuing License
Amendment No. 18 to Combined Licenses (COL), NPF-91 and NPF-92. The
COLs were issued to Southern Nuclear Operating Company (SNC), Georgia
Power Company, Oglethorpe Power Corporation, Municipal Electric
Authority of Georgia, and City of Dalton, Georgia (the licensee), for
construction and operation of the Vogtle Electric Generating Plant
(VGEP), Units 3 and 4, located in Burke County, Georgia. The amendment
revises the UFSAR by making changes to the Non-Class 1E dc and
Uninterruptible Power Supply System (EDS) and Class 1E dc and
Uninterruptible Power Supply System (IDS) and making changes to the
corresponding Tier 1 information in Appendix C to the Combined
Licenses.
The granting of the exemption allows the changes to Tier 1
information asked for in the amendment. Because the acceptability of
the exemption was determined in part by the acceptability of the
amendment, the exemption and amendment are being issued concurrently.
ADDRESSES: Please refer to Docket ID NRC-2008-0252 when contacting the
NRC about the availability of information regarding this document. You
may access information related to this document, which the NRC
possesses and is publicly available, using any of the following
methods:
Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2008-0252. Address
questions about NRC dockets to Carol
[[Page 24461]]
Gallagher; telephone: 301-287-3422; email: [email protected]. For
technical questions, contact the individual listed in the FOR FURTHER
INFORMATION CONTACT section of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly available documents online in the NRC
Library at http://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to [email protected]. The ADAMS accession number
for each document referenced in this document (if that document is
available in ADAMS) is provided the first time that a document is
referenced. The request for the amendment and exemption were submitted
by letter dated July 10, 2013 (ADAMS Accession No. ML13192A216)
(original application was submitted on March 15, 2013 (ADAMS Accession
No. ML13077A072)) and supplemented by a letter dated April 11, 2013
(ADAMS Accession No. ML13101A370). The licensee supplemented this
request by letters dated August 16 (ADAMS Accession No. ML13233A109),
and December 11, 2013 (ADAMS Accession No. ML13345A274), and February
3, 2014 (ADAMS Accession No. ML14034A157).
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Ravindra Joshi, Office of New
Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001; telephone: 301-415-6191; email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Introduction
The NRC is granting an exemption from Paragraph B of Section III,
``Scope and Contents,'' of Appendix D, ``Design Certification Rule for
the AP1000,'' to Part 52 of Title 10 of the Code of Federal Regulations
(10 CFR) and issuing License Amendment No. 18 to COLs, NPF-91 and NPF-
92, to the licensee. The exemption is required by Paragraph A.4 of
Section VIII, ``Processes for Changes and Departures,'' Appendix D to
10 CFR part 52 to allow the licensee to depart from Tier 1 information.
With the requested amendment, the licensee sought changes to the VEGP
Tier 1 (COL Appendix C) Tables 2.6.2-1, 2.6.2-2, 2.6.3-1, and 2.6.3-4
and Figure 2.6.2-1, and to the UFSAR (Tier 2 material) by making
changes to the Non-Class 1E dc and EDS and Class 1E dc and IDS.
Part of the justification for granting the exemption was provided
by the review of the amendment. Because the exemption is necessary in
order to issue the requested license amendment, the NRC granted the
exemption and issued the amendment concurrently, rather than in
sequence. This included issuing a combined safety evaluation containing
the NRC staff's review of both the exemption request and the license
amendment. The exemption met all applicable regulatory criteria set
forth in 10 CFR 50.12, 10 CFR 52.7, and Section VIII.A.4. of Appendix D
to 10 CFR part 52. The license amendment was found to be acceptable as
well. The combined safety evaluation is available in ADAMS under
Accession No. ML14065A565.
Identical exemption documents (except for referenced unit numbers
and license numbers) were issued to the licensee for VEGP Units 3 and 4
(COLs NPF-91 and NPF-92). These documents can be found in ADAMS under
Accession Nos. ML14065A558 and ML14065A561, respectively. The exemption
is reproduced (with the exception of abbreviated titles and additional
citations) in Section II of this document. The amendment documents for
COLs NPF-91 and NPF-92 are available in ADAMS under Accession Nos.
ML14065A554 and ML14065A556, respectively. A summary of the amendment
documents is provided in Section III of this document.
II. Exemption
Reproduced below is the exemption document issued to VEGP Units 3
and 4. It makes reference to the combined safety evaluation that
provides the reasoning for the findings made by the NRC (and listed
under Item 1) in order to grant the exemption:
1. In a letter dated July 10, 2013 and supplemented by the letters
dated August 16, December 11, 2013, and February 3, 2014, Southern
Nuclear Operating Company (licensee) requested from the Nuclear
Regulatory Commission (Commission) an exemption from the provisions of
Title 10 of the Code of Federal Regulation (10 CFR) part 52, Appendix
D, Section III.B, ``Design Certification Rule for the AP1000 Design,
Scope, and Contents,'' as part of license amendment request (LAR) 13-
007, ``Turbine Building Battery Room and Electrical Changes'' (LAR 13-
007).
For the reasons set forth in Section 3.1 of the NRC staff's Safety
Evaluation, which can be found at ADAMS Accession No. ML14065A565, the
Commission finds that:
A. The exemption is authorized by law;
B. the exemption presents no undue risk to public health and
safety;
C. the exemption is consistent with the common defense and
security;
D. special circumstances are present in that the application of the
rule in this circumstance is not necessary to serve the underlying
purpose of the rule;
E. the special circumstances outweigh any decrease in safety that
may result from the reduction in standardization caused by the
exemption; and
F. the exemption will not result in a significant decrease in the
level of safety otherwise provided by the design.
2. Accordingly, the licensee is granted an exemption to the
provisions of 10 CFR part 52, Appendix D, Section III.B, to allow
deviations from the certified DCD Tier 1 Tables 2.6.2-1, 2.6.2-2,
2.6.3-1, and 2.6.3-4 and Figure 2.6.2-1, as described in the licensee's
request dated July 10, 2013 and supplemented by the letters dated
August 16, December 11, 2013, and February 3, 2014. This exemption is
related to, and necessary for the granting of License Amendment No. 18,
which is being issued concurrently with this exemption.
3. As explained in Section 5 of the NRC staff's Safety Evaluation
(ADAMS Accession No. ML14065A565), this exemption meets the eligibility
criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9).
Therefore, pursuant to 10 CFR 51.22(b), no environmental impact
statement or environmental assessment needs to be prepared in
connection with the issuance of the exemption.
4. This exemption is effective as of April 2, 2014.
III. License Amendment Request
By letter dated March 15, 2013 (ADAMS Accession No. ML13077A072),
and supplemented by a letter dated April 11, 2013 (ADAMS Accession No.
ML13101A370), the licensee requested that the NRC amend the COLs for
VEGP Units 3 and 4. The licensee replaced the March 15, 2013 and April
11, 2013 letters in their entirety with a letter dated July 10, 2013
(ADAMS Accession No. ML13192A216). The proposed license amendment
request would depart from the plant-specific DCD Tier 1 and Tier 2
material by making changes to the Non-Class 1E DC and EDS and Class 1E
DC and IDS and making changes to the corresponding Tier 1 information
in Appendix C to the Combined License.
[[Page 24462]]
The Commission has determined for these amendments that the
application complies with the standards and requirements of the Atomic
Energy Act of 1954, as amended (the Act), and the Commission's rules
and regulations. The Commission has made appropriate findings as
required by the Act and the Commission's rules and regulations in 10
CFR Chapter I, which are set forth in the license amendment.
A notice of consideration of issuance of amendment to facility
operating license or combined license, as applicable, proposed no
significant hazards consideration determination, and opportunity for a
hearing in connection with these actions, was published in the Federal
Register on September 3, 2013 (78 FR 54287). No comments were received
during the 60-day comment period.
The Commission has determined that these amendments satisfy the
criteria for categorical exclusion in accordance with 10 CFR 51.22.
Therefore, pursuant to 10 CFR 51.22(b), no environmental impact
statement or environmental assessment need be prepared for these
amendments.
IV. Conclusion
Using the reasons set forth in the combined safety evaluation, the
staff granted the exemption and issued the amendment that the licensee
requested on July 10, 2013, and supplemented by letters dated August
16, December 11, 2013 and February 3, 2014. The exemption and amendment
were issued on April 2, 2014 as part of a combined package to the
licensee (ADAMS Accession No. ML14065A534).
Dated at Rockville, Maryland, this 23rd day of April 2014.
For the Nuclear Regulatory Commission.
Lawrence J. Burkhart,
Chief, Licensing Branch 4, Division of New Reactor Licensing, Office of
New Reactors.
[FR Doc. 2014-09879 Filed 4-29-14; 8:45 am]
BILLING CODE 7590-01-P