DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. CP14-83-000]
El Paso Natural Gas Company, LLC; Notice of Intent To Prepare an
Environmental Assessment for the Proposed Line 1000 and 1001
Abandonment Project and Request for Comments on Environmental Issues
The staff of the Federal Energy Regulatory Commission (FERC or
Commission) will prepare an environmental assessment (EA) that will
address the environmental impacts of the Line 1000 and 1001 Abandonment
Project (Project) which would include the abandonment of facilities by
El Paso Natural Gas Company, LLC (El Paso) in El Paso and Hudspeth
Counties, Texas. This EA will be used by the Commission in its
decision-making process to determine whether the project is in the
public convenience and necessity.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. Your input will help the Commission staff
determine what issues they need to evaluate in the EA. Please note that
the scoping period will close on April 14, 2014.
This notice announces the opening of the scoping process the
Commission will use to gather input from the public and interested
agencies on the project. Your input will help the Commission staff
determine what issues need to be evaluated in the EA. Please note that
the scoping period will close on April 14, 2014. Further details on how
to submit written comments are provided in the Public Participation
section of this notice.
This notice is being sent to the Commission's current environmental
mailing list for this project. State and local government
representatives are asked to notify their constituents of this planned
project and encourage them to comment on their areas of concern.
Summary of the Proposed Project
El Paso proposes to abandon in by sale to DKM Enterprises, LLC
(DKM) for salvage about 42 miles of its Jal Lines (Lines 1000 and 1001)
consisting of two segments of 16-inch-diameter pipeline between its
Cornudas Compressor Station at milepost (MP) 144.5 and its Clint Meter
Station at MP 186.5. The two pipeline segments are adjacent to each
other, offset by about 10 feet, and within the same permanent right-of-
way. Activities El Paso would conduct related to the abandonment
include disconnecting each end of the abandoned pipeline segments from
its other facilities; and removing one mainline valve, three cathodic
protection stations, and about 338 feet of station piping at the
Cornudas Compressor Station. DKM would salvage the two 42-mile-long
pipeline segments and aboveground ancillary facilities subject to the
terms of its purchase and sales agreement with El Paso and applicable
regulations and permits. El Paso states that the easements associated
with the abandoned pipelines would revert to the landowners.
The general location of the project facilities is shown in appendix
1.\1\
---------------------------------------------------------------------------
\1\ The appendices referenced in this notice will not appear in
the Federal Register. Copies of appendices were sent to all those
receiving this notice in the mail and are available at www.ferc.gov
using the link called ``eLibrary'' or from the Commission's Public
Reference Room, 888 First Street NE., Washington, DC 20426, or call
(202) 502-8371. For instructions on connecting to eLibrary, refer to
the last page of this notice.
---------------------------------------------------------------------------
Land Requirements for Abandonment
El Paso proposes abandoning these facilities by sale to DKM. It
states that all of its abandonment and DKM's salvage activities would
be conducted within El Paso's existing right-of-way, and that no
additional workspaces for access or storage of materials or equipment
would be needed. Therefore, there would be no new land requirements.
The EA Process
The National Environmental Policy Act (NEPA) requires the
Commission to take into account the environmental impacts that could
result from an action whenever it considers the issuance of a
Certificate of Public Convenience and Necessity. NEPA also requires us
\2\ to discover and address concerns the public may have about
proposals. This process is referred to as ``scoping.'' The main goal of
the scoping process is to focus the analysis in the EA on the important
environmental issues. By this notice, the Commission requests public
comments on the scope of the issues to address in the EA. We will
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------
\2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------
In the EA we will discuss impacts that could occur as a result of
the construction and operation of the proposed project under these
general headings:
geology and soils;
land use;
water resources, fisheries, and wetlands;
cultural resources;
vegetation and wildlife;
air quality and noise;
endangered and threatened species; and
cumulative resources.
We will also evaluate reasonable alternatives to the proposed
project or portions of the project, and make recommendations on how to
lessen or avoid impacts on the various resource areas.
The EA will present our independent analysis of the issues. The EA
will be available in the public record through the Commission's
eLibrary. Depending on the comments received during the scoping
process, we may also publish and distribute the EA to the public for an
allotted comment period. We will consider all comments on the EA before
we make our recommendations to the Commission. To ensure we have the
opportunity to consider and address your comments, please carefully
follow the instructions in the Public Participation section beginning
on page 4.
With this notice, we are asking agencies with jurisdiction by law
and/or special expertise with respect to the environmental issues of
this project to formally cooperate with us in the preparation of the
EA.\3\ Agencies that
[[Page 15992]]
would like to request cooperating agency status should follow the
instructions for filing comments provided under the Public
Participation section of this notice.
---------------------------------------------------------------------------
\3\ The Council on Environmental Quality regulations addressing
cooperating agency responsibilities are at Title 40, Code of Federal
Regulations, Part 1501.6.
---------------------------------------------------------------------------
Consultations Under Section 106 of the National Historic Preservation
Act
In accordance with the Advisory Council on Historic Preservation's
implementing regulations for section 106 of the National Historic
Preservation Act, we are using this notice to initiate consultation
with the applicable State Historic Preservation Office (SHPO), and to
solicit their views and those of other government agencies, interested
Indian tribes, and the public on the project's potential effects on
historic properties.\4\ We will define the project-specific Area of
Potential Effects (APE) in consultation with the SHPO as the project
develops. On natural gas facility projects, the APE at a minimum
encompasses all areas subject to ground disturbance (examples include
construction right-of-way, contractor/pipe storage yards, compressor
stations, and access roads). Our EA for this project will document our
findings on the impacts on historic properties and summarize the status
of consultations under section 106.
---------------------------------------------------------------------------
\4\ The Advisory Council on Historic Preservation's regulations
are at Title 36, Code of Federal Regulations, Part 800. Those
regulations define historic properties as any prehistoric or
historic district, site, building, structure, or object included in
or eligible for inclusion in the National Register of Historic
Places.
---------------------------------------------------------------------------
Public Participation
You can make a difference by providing us with your specific
comments or concerns about the project. Your comments should focus on
the potential environmental effects, reasonable alternatives, and
measures to avoid or lessen environmental impacts. The more specific
your comments, the more useful they will be. To ensure that your
comments are timely and properly recorded, please send your comments so
that the Commission receives them in Washington, DC on or before April
14, 2014.
For your convenience, there are three methods which you can use to
submit your comments to the Commission. In all instances please
reference the project docket number (CP14-83-000) with your submission.
The Commission encourages electronic filing of comments and has expert
staff available to assist you at (202) 502-8258 or [email protected].
(1) You can file your comments electronically using the eComment
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. This is an easy method for interested persons to
submit brief, text-only comments on a project;
(2) You can file your comments electronically using the eFiling
feature on the Commission's Web site (www.ferc.gov) under the link to
Documents and Filings. With eFiling, you can provide comments in a
variety of formats by attaching them as a file with your submission.
New eFiling users must first create an account by clicking on
``eRegister.'' You must select the type of filing you are making. If
you are filing a comment on a particular project, please select
``Comment on a Filing''; or
(3) You can file a paper copy of your comments by mailing them to
the following address: Kimberly D. Bose, Secretary, Federal Energy
Regulatory Commission, 888 First Street NE., Room 1A, Washington, DC
20426.
Environmental Mailing List
The environmental mailing list federal, state, and local government
representatives and agencies; elected officials; environmental and
public interest groups; Native American Tribes; other interested
parties; and local libraries and newspapers. This list also includes
all affected landowners (as defined in the Commission's regulations)
who are potential right-of-way grantors, whose property may be used
temporarily for project purposes, or who own homes within certain
distances of aboveground facilities, and anyone who submits comments on
the project. We will update the environmental mailing list as the
analysis proceeds to ensure that we send the information related to
this environmental review to all individuals, organizations, and
government entities interested in and/or potentially affected by the
proposed project.
If we publish and distribute the EA, copies will be sent to the
environmental mailing list for public review and comment. If you would
prefer to receive a paper copy of the document instead of the CD
version or would like to remove your name from the mailing list, please
return the attached Information Request (appendix 2).
Becoming an Intervenor
In addition to involvement in the EA scoping process, you may want
to become an ``intervenor'' which is an official party to the
Commission's proceeding. Intervenors play a more formal role in the
process and are able to file briefs, appear at hearings, and be heard
by the courts if they choose to appeal the Commission's final ruling.
An intervenor formally participates in the proceeding by filing a
request to intervene. Instructions for becoming an intervenor are in
the User's Guide under the ``e-filing'' link on the Commission's Web
site.
Additional Information
Additional information about the project is available from the
Commission's Office of External Affairs, at (866) 208-FERC, or on the
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the
eLibrary link, click on ``General Search'' and enter the docket number,
excluding the last three digits in the Docket Number field (i.e., CP14-
83-000). Be sure you have selected an appropriate date range. For
assistance, please contact FERC Online Support at
[email protected] or toll free at (866) 208-3676, or for TTY,
contact (202) 502-8659. The eLibrary link also provides access to the
texts of formal documents issued by the Commission, such as orders,
notices, and rulemakings.
In addition, the Commission now offers a free service called
eSubscription which allows you to keep track of all formal issuances
and submittals in specific dockets. This can reduce the amount of time
you spend researching proceedings by automatically providing you with
notification of these filings, document summaries, and direct links to
the documents. Go to www.ferc.gov/esubscribenow.htm.
Finally, public meetings or site visits will be posted on the
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.
Dated: March 14, 2014.
Kimberly D. Bose,
Secretary.
[FR Doc. 2014-06313 Filed 3-21-14; 8:45 am]