[Federal Register Volume 79, Number 18 (Tuesday, January 28, 2014)]
[Notices]
[Pages 4510-4511]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2014-01481]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 5200025; NRC-2008-0252]
Inspections, Tests, Analyses, and Acceptance Criteria; Vogtle
Unit 3 Combined License
AGENCY: Nuclear Regulatory Commission.
ACTION: Determination of inspections, tests, analyses, and acceptance
criteria (ITAAC).
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) staff has
determined that the inspections, tests, and analyses have been
successfully completed, and that the specified acceptance criteria are
met for ITAAC 3.3.00.09, for the Vogtle Unit 3 Combined License.
ADDRESSES: Please refer to Docket ID NRC-2008-0252 when contacting the
NRC about the availability of information regarding this document. You
may access publicly-available information related to this document
using any of the following methods:
Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2008-0252. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-287-
3422; email: [email protected]. For technical questions, contact
the individuals listed in the FOR FURTHER INFORMATION CONTACT section
of this document.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly available documents online in the NRC
Library at http://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to [email protected]. The ADAMS accession number
for each document referenced in this document (if that document is
available in ADAMS) is provided the first time that a document is
referenced.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: David H. Jaffe, Office of New
Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001; telephone: 301-415-1439, email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Licensee Notification of Completion of ITAAC
On December 11, 2013, Southern Nuclear Operating Company, Inc. (the
licensee) submitted an ITAAC closure notification (ICN) under Sec.
52.99(c)(1) of Title 10 of the Code of Federal Regulations (10 CFR)
informing the NRC that the licensee has successfully performed the
required inspections, tests, and analyses for ITAAC 3.3.00.09, and that
the specified acceptance criteria are met for the Vogtle Unit 3
Combined License (ADAMS Accession No. ML13345A275). This ITAAC was
approved as part of the issuance of the combined license, NPF-91, for
this facility.
II. NRC Staff Determination of Completion of ITAAC
The NRC staff has determined that the inspections, tests, and
analyses have been successfully completed, and that the specified
acceptance criteria are met for Vogtle Unit 3 Combined License, ITAAC
3.3.00.09. This notice fulfills the staff's obligations under 10 CFR
52.99(e)(1) to publish a notice in the Federal Register of the NRC
staff's determination of the successful completion of inspections,
tests and analyses.
The documentation of the NRC staff's determination is in the ITAAC
Closure Verification Evaluation Form (VEF) dated January 8, 2014 (ADAMS
Accession No. ML14008A377). The VEF is a form that represents the NRC
staff's structured process for reviewing ICNs. The ICN presents a
narrative description of how the ITAAC was completed, and the NRC's ICN
review process involves a determination on whether, among other things,
(1) the ICN provides sufficient information, including a summary of the
methodology used to perform the ITAAC, to demonstrate that the
inspections, tests, and analyses have been successfully completed; (2)
the ICN provides sufficient information to demonstrate that the
acceptance criteria are met; and (3) any inspections for the
[[Page 4511]]
ITAAC have been completed and any ITAAC findings associated with the
ITAAC have been closed.
The NRC staff's determination of the successful completion of this
ITAAC is based on information available at this time and is subject to
the licensee's ability to maintain the condition that the acceptance
criteria are met. If new information disputes the NRC staff's
determination, this ITAAC will be reopened as necessary. The NRC
staff's determination will be used to support a subsequent finding,
pursuant to 10 CFR 52.103(g), at the end of construction that all
acceptance criteria in the combined license are met. The ITAAC closure
process is not finalized for this ITAAC until the NRC makes an
affirmative finding under 10 CFR 52.103(g). Any future updates to the
status of this ITAAC will be reflected on the NRC's Web site at http://www.nrc.gov/reactors/new-reactors/oversight/itaac.html.
Dated at Rockville, Maryland, this 16th day of January 2014.
For the Nuclear Regulatory Commission.
David H. Jaffe,
Senior Project Manager, Division of New Reactor Licensing, Office of
New Reactors.
[FR Doc. 2014-01481 Filed 1-27-14; 8:45 am]
BILLING CODE 7590-01-P