NUCLEAR REGULATORY COMMISSION
[Docket No. 50-259; NRC-2013-0198]
Tennessee Valley Authority, Browns Ferry Nuclear Plant, Unit 1;
Applications and Amendments to Facility Operating Licenses Involving
Proposed, No Significant Hazards Considerations
AGENCY: Nuclear Regulatory Commission.
ACTION: License amendment request; opportunity to comment, request a
hearing and to petition for leave to intervene.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is considering
issuance of an amendment to Facility Operating License No. DPR-33,
issued to Tennessee Valley Authority (TVA or the licensee), for
operation of the Browns Ferry Nuclear Plant (BFN) Unit 1, located in
Alabama, Limestone County.
DATES: Comments must be filed by September 6, 2013. A request for a
hearing must be filed by October 22, 2013.
ADDRESSES: You may submit comment by any of the following methods
(unless this document describes a different method for submitting
comments on a specific subject):
Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2013-0198. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-287-
3422; email: [email protected]. For technical questions, contact
the individual(s) listed in the FOR FURTHER INFORMATION CONTACT section
of this document.
Mail comments to: Cindy Bladey, Chief, Rules,
Announcements, and Directives Branch (RADB), Office of Administration,
Mail Stop: 3WFN, 06-44M, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001.
For additional direction on accessing information and submitting
comments, see ``Accessing Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Siva P. Lingam, Project Manager,
Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001, telephone: 301-415-1564; email:
[email protected].
SUPPLEMENTARY INFORMATION:
I. Accessing Information and Submitting Comments
A. Accessing Information
Please refer to Docket ID NRC-2013-0198 when contacting the NRC
about the availability of information regarding this document. You may
access publicly-available information related to this action by the
following methods:
Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2013-0198.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly-available documents online in the NRC
Library at http://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to [email protected]. The ADAMS accession number
for each document referenced in this notice (if that document is
available in ADAMS) is provided the first time that a document is
referenced. The application for amendment, dated August 14, 2013, is
available electronically under ADAMS Accession No. ML13227A103.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC-2013-0198 in the subject line of your
comment submission, in order to ensure that the NRC is able to make
your comment submission available to the public in this docket.
The NRC cautions you not to include identifying or contact
information that you do not want to be publicly disclosed in your
comment submission. The NRC posts all comment submissions at http://www.regulations.gov as well as entering the comment submissions into
ADAMS. The NRC does not routinely edit comment submissions to remove
identifying or contact information.
If you are requesting or aggregating comments from other persons
for submission to the NRC, then you should inform those persons not to
include identifying or contact information that they do not want to be
publicly disclosed in their comment submission. Your request should
state that the NRC does not routinely edit comment submissions to
remove such information before making the comment submissions available
to the public or entering the comment submissions into ADAMS.
II. Further Information
The proposed amendment would delete the Notes that cover the
Reactor Coolant System (RCS) Pressure and Temperature (P/T) Limits
curves on Technical Specification (TS) 3.4.9, ``RCS Pressure and
Temperatures (P/T) Limits,'' Figures 3.4.9-1 and 3.4.9-2 that are
applicable from 12 Effective Full Power Years (EFPY) to 16 EFFY and
allows usage of the figures up to 16 EFPY. The current Notes state,
``Do Not Use This Figure. This curve applies to operations > 12 EFPY.
For current operation, use previous curve, which is valid up to 12
EFPY.''
There are two sets of P/T curves in the BFN Unit 1 TS 3.4.9: One
set for operations up to 12 EFPY and another set for operations greater
than (>) 12 EFPY and less than or equal to (<=) 16 EFPY. However, the
second set of P/T curves (for operations > 12 EFPY and <= 16 EFPY)
includes Notes that state that these curves cannot be used, and to use
the first set of P/T curves for operations up to 12 EFPY. Therefore,
the second set of P/T curves that are applicable when operations are >
12 EFPY cannot be used until the Notes are removed. The BFN Unit 1
operation is expected to reach 12 EFPY on September 20, 2013.
Therefore, to utilize the correct and previously approved P/T Limits
curves once the BFN Unit 1 operation has reached 12 EFPY, this Note
must be removed from the > 12 EFPY and <= 16 EFPY TS Figures 3.4.9-1
and 3.4.9-2. Once 12 EFPY is achieved, the BFN Unit 1 will not be
allowed to continue operation in Mode 1 (i.e., critical operation) and
a unit shutdown will be required unless the Notes are removed. TVA
determined that a license amendment was necessary to remove the Note
from the figures. TVA further concluded that in the absence of an
amendment to remove the Notes, a shutdown of the BFN Unit 1 as early as
September 20, 2013, cannot be avoided.
Before issuance of the proposed license amendment, the Commission
will have made findings required by the Atomic Energy Act of 1954, as
amended (the Act), and the Commission's regulations.
Pursuant to Sec. 50.91(a)(6) of Title 10 of the Code of Federal
Regulations (10 CFR), for amendments to be granted under exigent
circumstances, the NRC staff must determine that the amendment request
involves no significant hazards consideration. Under the Commission's
regulations in 10 CFR 50.92, this means that operation of the
[[Page 52572]]
facility in accordance with the proposed amendment would not (1)
involve a significant increase in the probability or consequences of an
accident previously evaluated; or (2) create the possibility of a new
or different kind of accident from any accident previously evaluated;
or (3) involve a significant reduction in a margin of safety. As
required by 10 CFR 50.91(a), the licensee has provided its analysis of
the issue of no significant hazards consideration, which is presented
below:
1. Does the proposed amendment involve a significant increase in
the probability or consequences of any accident previously
evaluated?
Response: No.
The proposed administrative change will allow a set of TS
figures, contained in a previous NRC-approved license amendment, to
be used because the reactor fluence will soon reach the point at
which the figures are applicable. The proposed administrative change
does not revise any previously approved P/T limitations on plant
operation. The change is an administrative change removing Notes
that were placed on the approved figures to preclude using the
figures until the fluence reached the applicable values. Because the
NRC has previously approved the figures, the proposed amendment does
not involve a significant increase in the probability or
consequences of an accident previously evaluated.
2. Does the proposed amendment create the possibility of a new
or different kind of accident from any accident previously
evaluated?
Response: No.
The proposed administrative change will allow a set of TS
figures, contained in a previous NRC-approved license amendment, to
be used because the reactor fluence will soon reach the point at
which the figures are applicable. The proposed administrative change
does not revise any previously approved P/T limitations on plant
operation. The change is an administrative change removing Notes
that were placed on the approved figures to preclude using the
figures until the fluence reached the applicable value.
Therefore, the proposed amendment will not create the
possibility of a new or different kind of accident from any accident
previously evaluated.
3. Does the proposed amendment involve a significant reduction
in a margin of safety?
Response: No.
The proposed administrative change will allow a set of TS
figures, contained in a previous NRC-approved license amendment, to
be used because the reactor fluence will soon reach the point at
which the figures are applicable. The proposed administrative change
does not revise any previously approved P/T limitations on plant
operation. The change is an administrative change removing Notes
that were placed on the approved figures to preclude using the
figures until the fluence reached the applicable value. In addition,
the margin of safety change as a result of using these new figures
was previously evaluated when the figures were originally approved.
As such, deleting the Notes has no effect on a margin of safety.
Therefore, the proposed changes do not involve a significant
reduction in a margin of safety.
The NRC staff has reviewed the licensee's analysis and, based on
this review, it appears that the three standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff proposes to determine that the
amendment request involves no significant hazards consideration.
The Commission is seeking public comments on this proposed
determination. Any comments received within 14 days after the date of
publication of this notice will be considered in making any final
determination.
Normally, the Commission will not issue the amendment until the
expiration of the 14-day notice period. However, should circumstances
change during the notice period, such that failure to act in a timely
way would result, for example, in derating or shutdown of the facility,
the Commission may issue the license amendment before the expiration of
the 14-day notice period, provided that its final determination is that
the amendment involves no significant hazards consideration. The final
determination will consider all public and State comments received.
Should the Commission take this action, it will publish in the Federal
Register a notice of issuance. The Commission expects that the need to
take this action will occur very infrequently.
III. Opportunity To Request a Hearing and Petition for Leave To
Intervene
Within 60 days of this notice, any person(s) whose interest may be
affected may file a request for hearing/petition to intervene. As
required by 10 CFR 2.309, a petition for leave to intervene shall set
forth with particularity the interest of the requestor/petitioner in
the proceeding, and how that interest may be affected by the results of
the proceeding. The petition should specifically explain the reasons
why intervention should be permitted with particular reference to the
following general requirements: (1) The name, address, and telephone
number of the requestor or petitioner; (2) the nature of the
requestor's/petitioner's right under the Act to be made a party to the
proceeding; (3) the nature and extent of the requestor's/petitioner's
property, financial, or other interest in the proceeding; and (4) the
possible effect of any decision or order which may be entered in the
proceeding on the requestor's/petitioner's interest. The petition must
also identify the specific contentions which the requestor/petitioner
seeks to have litigated at the proceeding.
Each contention must consist of a specific statement of the issue
of law or fact to be raised or controverted. In addition, the
requestor/petitioner shall provide a brief explanation of the bases for
the contention and a concise statement of the alleged facts or expert
opinion which support the contention and on which the petitioner
intends to rely in proving the contention at the hearing. The
requestor/petitioner must also provide references to those specific
sources and documents of which the requestor/petitioner is aware and on
which the requestor/petitioner intends to rely to establish those facts
or expert opinion. The requestor/petitioner must provide sufficient
information to show that a genuine dispute exists with the applicant on
a material issue of law or fact. Contentions shall be limited to
matters within the scope of the amendment under consideration. The
contention must be one which, if proven, would entitle the requestor/
petitioner to relief. A requestor/petitioner who fails to satisfy these
requirements with respect to at least one contention will not be
permitted to participate as a party.
Those permitted to intervene become parties to the proceeding,
subject to any limitations in the order granting leave to intervene,
and have the opportunity to participate fully in the conduct of the
hearing.
If a hearing is requested, the Commission will make a final
determination on the issue of no significant hazards consideration. The
final determination will serve to decide when the hearing is held. If
the final determination is that the amendment request involves no
significant hazards consideration, the Commission may issue the
amendment and make it immediately effective, notwithstanding the
request for a hearing. Any hearing held would take place after issuance
of the amendment. If the final determination is that the amendment
request involves a significant hazards consideration, then any hearing
held would take place before the issuance of any amendment.
IV. Electronic Submissions (E-Filing)
All documents filed in NRC adjudicatory proceedings, including a
request for hearing, a petition for leave to intervene, any motion or
other document filed in the proceeding prior
[[Page 52573]]
to the submission of a request for hearing or petition to intervene,
and documents filed by interested governmental entities participating
under 10 CFR 2.315(c), must be filed in accordance with the NRC E-
Filing rule (72 FR 49139; August 28, 2007). The E-Filing process
requires participants to submit and serve all adjudicatory documents
over the internet, or in some cases to mail copies on electronic
storage media. Participants may not submit paper copies of their
filings unless they seek an exemption in accordance with the procedures
described below.
To comply with the procedural requirements of E-Filing, at least 10
days prior to the filing deadline, the participant should contact the
Office of the Secretary by email at [email protected], or by
telephone at 301-415-1677, to request (1) a digital identification (ID)
certificate, which allows the participant (or its counsel or
representative) to digitally sign documents and access the E-Submittal
server for any proceeding in which it is participating; and (2) advise
the Secretary that the participant will be submitting a request or
petition for hearing (even in instances in which the participant, or
its counsel or representative, already holds an NRC-issued digital ID
certificate). Based upon this information, the Secretary will establish
an electronic docket for the hearing in this proceeding if the
Secretary has not already established an electronic docket.
Information about applying for a digital ID certificate is
available on the NRC's public Web site at http://www.nrc.gov/site-help/e-submittals/apply-certificates.html. System requirements for accessing
the E-Submittal server are detailed in the NRC's ``Guidance for
Electronic Submission,'' which is available on the NRC's public Web
site at http://www.nrc.gov/site-help/e-submittals.html. Participants
may attempt to use other software not listed on the Web site, but
should note that the NRC's E-Filing system does not support unlisted
software, and the NRC Meta System Help Desk will not be able to offer
assistance in using unlisted software.
If a participant is electronically submitting a document to the NRC
in accordance with the E-Filing rule, the participant must file the
document using the NRC's online, Web-based submission form. In order to
serve documents through the Electronic Information Exchange System,
users will be required to install a Web browser plug-in from the NRC's
Web site. Further information on the Web-based submission form,
including the installation of the Web browser plug-in, is available on
the NRC's public Web site at http://www.nrc.gov/site-help/e-submittals.html.
Once a participant has obtained a digital ID certificate and a
docket has been created, the participant can then submit a request for
hearing or petition for leave to intervene. Submissions should be in
Portable Document Format (PDF) in accordance with NRC guidance
available on the NRC's public Web site at http://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the time the
documents are submitted through the NRC's E-Filing system. To be
timely, an electronic filing must be submitted to the E-Filing system
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of
a transmission, the E-Filing system time-stamps the document and sends
the submitter an email notice confirming receipt of the document. The
E-Filing system also distributes an email notice that provides access
to the document to the NRC's Office of the General Counsel and any
others who have advised the Office of the Secretary that they wish to
participate in the proceeding, so that the filer need not serve the
documents on those participants separately. Therefore, applicants and
other participants (or their counsel or representative) must apply for
and receive a digital ID certificate before a hearing request/petition
to intervene is filed so that they can obtain access to the document
via the E-Filing system.
A person filing electronically using the NRC's adjudicatory E-
Filing system may seek assistance by contacting the NRC Meta System
Help Desk through the ``Contact Us'' link located on the NRC's public
Web site at http://www.nrc.gov/site-help/e-submittals.html, by email to
[email protected], or by a toll-free call to 1-866-672-7640. The
NRC Meta System Help Desk is available between 8 a.m. and 8 p.m.,
Eastern Time, Monday through Friday, excluding government holidays.
Participants who believe that they have a good cause for not
submitting documents electronically must file an exemption request, in
accordance with 10 CFR 2.302(g), with their initial paper filing
requesting authorization to continue to submit documents in paper
format. Such filings must be submitted by: (1) First class mail
addressed to the Office of the Secretary of the Commission, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention:
Rulemaking and Adjudications Staff; or (2) courier, express mail, or
expedited delivery service to the Office of the Secretary, Sixteenth
Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland
20852, Attention: Rulemaking and Adjudications Staff. Participants
filing a document in this manner are responsible for serving the
document on all other participants. Filing is considered complete by
first-class mail as of the time of deposit in the mail, or by courier,
express mail, or expedited delivery service upon depositing the
document with the provider of the service. A presiding officer, having
granted an exemption request from using E-Filing, may require a
participant or party to use E-Filing if the presiding officer
subsequently determines that the reason for granting the exemption from
use of E-Filing no longer exists.
Documents submitted in adjudicatory proceedings will appear in
NRC's electronic hearing docket which is available to the public at
http://ehd1.nrc.gov/ehd/, unless excluded pursuant to an order of the
Commission, or the presiding officer. Participants are requested not to
include personal privacy information, such as social security numbers,
home addresses, or home phone numbers in their filings, unless an NRC
regulation or other law requires submission of such information.
However, a request to intervene will require including information on
local residence in order to demonstrate a proximity assertion of
interest in the proceeding. With respect to copyrighted works, except
for limited excerpts that serve the purpose of the adjudicatory filings
and would constitute a Fair Use application, participants are requested
not to include copyrighted materials in their submission.
Petitions for leave to intervene must be filed no later than 30
days from August 23, 2013. Requests for hearing, petitions for leave to
intervene, and motions for leave to file new or amended contentions
that are filed after the 60-day deadline will not be entertained absent
a determination by the presiding officer that the filing demonstrates
good cause by satisfying the three factors in 10 CFR 2.309(c)(1)(i)-
(iii).
For further details with respect to this exigent license
application, see the application for amendment dated August 14, 2013.
Attorney for licensee: General Counsel, Tennessee Valley Authority,
400 West Summit Hill Drive, ET 11A, Knoxville, Tennessee 37902.
Dated at Rockville, Maryland, this August 16, 2013.
[[Page 52574]]
For the Nuclear Regulatory Commission.
Siva P. Lingam,
Project Manager, Plant Licensing Branch 2-2, Division of Operating
Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2013-20627 Filed 8-22-13; 8:45 am]