[Federal Register Volume 78, Number 50 (Thursday, March 14, 2013)]
[Notices]
[Page 16302]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2013-05907]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-302; NRC-2011-0301]
Crystal River Unit 3 Nuclear Generating Plant, Application for
Amendment to Facility Operating License
AGENCY: Nuclear Regulatory Commission.
ACTION: License amendment application; withdrawal.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is granting the
request of Florida Power Corporation (the licensee), through its owner
Duke Energy, to withdraw its June 15, 2011, (Agencywide Documents
Access and Management System (ADAMS) Accession No. ML112070659),
application for proposed amendment to Facility Operating License No.
DPR-72 for the Crystal River Unit 3 Nuclear Generating Plant (CR-3),
located in Florida, Citrus County. The proposed amendment would have
revised the facility operating license and the technical specifications
to support operation at an increased core thermal power level.
ADDRESSES: Please refer to Docket ID NRC-2011-0301 when contacting the
NRC about the availability of information regarding this document. You
may access information related to this document, which the NRC
possesses and is publicly available, using any of the following
methods:
Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2011-0301. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-492-
3668; email: [email protected].
NRC's ADAMS: You may access publicly available documents
online in the NRC Library at http://www.nrc.gov/reading-rm/adams.html.
To begin the search, select ``ADAMS Public Documents'' and then select
``Begin Web-based ADAMS Search.'' For problems with ADAMS, please
contact the NRC's Public Document Room (PDR) reference staff at 1-800-
397-4209, 301-415-4737, or by email to [email protected]. The ADAMS
accession number for each document referenced in this notice (if that
document is available in ADAMS) is provided the first time that a
document is referenced.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
FOR FURTHER INFORMATION CONTACT: Siva P. Lingam, Office of Nuclear
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001; telephone: 301-415-1564; email: [email protected].
SUPPLEMENTARY INFORMATION: The NRC is granting the licensee's request
to withdraw its June 15, 2011, application for proposed amendment to
the CR-3 Facility Operating License No. DPR-72.
The proposed amendment would have increased the licensed core power
level for CR-3 from 2609 megawatts thermal (MWt) to 3014 MWt. The
increase in core thermal power would have been approximately 15.5
percent over the current licensed core thermal power level and was
categorized as an extended power uprate.
The Commission had previously issued a Notice of Consideration of
Issuance of Amendment published in the Federal Register on January 11,
2012 (77 FR 1743), and a Notice of Consideration of Issuance of draft
environmental assessment related to the proposed amendment published in
the Federal Register on January 16, 2013 (78 FR 3458). However, by
letter dated February 7, 2013 (ADAMS Accession No. ML13043A027), the
licensee withdrew the proposed change based on the determination to
retire CR-3 due to economic disadvantages to fix the containment
delamination that occurred during the steam generators replacement
refueling outage. As a result, all the comments received on the above
Federal Register notices will not be resolved and the environmental
assessment will not be finalized.
For further details with respect to this action, see the
application for amendment dated June 15, 2011, and the licensee's
letter dated February 7, 2013, which withdrew the application for
license amendment.
Dated at Rockville, Maryland, this 7th day of March 2013.
For the Nuclear Regulatory Commission.
Siva P. Lingam,
Project Manager, Plant Licensing Branch II-2, Division of Operating
Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2013-05907 Filed 3-13-13; 8:45 am]