[Federal Register Volume 77, Number 204 (Monday, October 22, 2012)]
[Notices]
[Pages 64497-64498]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2012-25812]
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Project No. 12796-004]
City of Wadsworth, OH; Notice of Application Ready for
Environmental Analysis and Soliciting Comments, Recommendations, Terms
and Conditions, and Prescriptions
Take notice that the following hydroelectric application has been
filed with the Commission and is available for public inspection.
a. Type of Application: Major Original License.
b. Project No.: P-12796-004.
c. Date filed: March 28, 2011.
d. Applicant: City of Wadsworth, Ohio.
e. Name of Project: R.C. Byrd Hydroelectric Project.
f. Location: On the Ohio River at the U.S. Army Corps of Engineers
(Corps) R.C. Byrd Locks and Dam (river mile 279.2), approximately 12.7
miles south of the confluence of the Ohio River and the Kanawha River
and 9 miles south of the Town of Gallipolis, Gallia County, Ohio. The
project would occupy 7.6 acres of federal land managed by the Corps.
g. Filed Pursuant to: Federal Power Act, 16 U.S.C. 791 (a)-825(r).
h. Applicant Contact: Mr. Chris Easton, Director of Public
Services, City of Wadsworth, Ohio, 120 Maple Street, Wadsworth, OH
44281, (330) 335-2777; or Mr. Phillip E. Meier, Assistant Vice
President, Hydro Development, American Municipal Power, Inc., 1111
Schrock Road, Suite 100, Columbus, OH 43229, (614) 540-0913.
i. FERC Contact: Gaylord Hoisington, (202) 502-6032 or
[email protected].
j. Deadline for filing comments, recommendations, terms and
conditions, and prescriptions is 60 days from the issuance date of this
notice; reply comments are due 105 days from issuance date of this
notice.
All documents may be filed electronically via the Internet. See 18
CFR 385.2001(a)(1)(iii) and the instructions on the Commission's Web
site http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit
brief comments up to 6,000 characters, without prior registration,
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the
end of your comments. For assistance, please contact FERC Online
Support at [email protected] or toll
[[Page 64498]]
free at 1-866-208-3676, or for TTY, (202) 502-8659. Although the
Commission strongly encourages electronic filing, documents may also be
paper-filed. To paper-file, mail an original and seven copies to:
Kimberly D. Bose, Secretary, Federal Energy Regulatory Commission, 888
First Street NE., Washington, DC 20426
The Commission's Rules of Practice require all intervenors filing
documents with the Commission to serve a copy of that document on each
person on the official service list for the project. Further, if an
intervenor files comments or documents with the Commission relating to
the merits of an issue that may affect the responsibilities of a
particular resource agency, they must also serve a copy of the document
on that resource agency.
k. The application has been accepted and is now ready for
environmental analysis.
l. The proposed project would use the existing Corps' R.C. Byrd
Locks and Dam and would consist of the following new facilities: (1) A
1,200-foot-long intake channel; (2) a trash rack located in front of
each of the generating unit intakes, with a bar spacing of
approximately 8 inches; (3) a reinforced concrete powerhouse measuring
approximately 258 feet long by 145 feet wide by 110 feet high and
housing two bulb-type turbine generator units with a total installed
capacity of 50 megawatts; (4) a 900-foot-long tailrace channel; (5) a
2.41-mile-long, 138-kilovolt transmission line; and (6) appurtenant
facilities. The proposed project would have an average annual
generation of 266 gigawatt-hours.
m. A copy of the application is available for review at the
Commission in the Public Reference Room or may be viewed on the
Commission's Web site at http://www.ferc.gov using the ``eLibrary''
link. Enter the docket number excluding the last three digits in the
docket number field to access the document. For assistance, contact
FERC Online Support. A copy is also available for inspection and
reproduction at the address in item (h) above.
All filings must (1) bear in all capital letters the title
``COMMENTS,'' ``REPLY COMMENTS,'' ``RECOMMENDATIONS,'' ``TERMS AND
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the
name of the applicant and the project number of the application to
which the filing responds; (3) furnish the name, address, and telephone
number of the person submitting the filing; and (4) otherwise comply
with the requirements of 18 CFR 385.2001 through 385.2005. All
comments, recommendations, terms and conditions or prescriptions must
set forth their evidentiary basis and otherwise comply with the
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the
application directly from the applicant. Each filing must be
accompanied by proof of service on all persons listed on the service
list prepared by the Commission in this proceeding, in accordance with
18 CFR 4.34(b), and 385.2010.
You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances
related to this or other pending projects. For assistance, contact FERC
Online Support.
n. Public notice of the filing of the initial development
application, which has already been given, established the due date for
filing competing applications or notices of intent. Under the
Commission's regulations, any competing development application must be
filed in response to and in compliance with public notices of the
initial development application. No competing applications or notices
of intent may be filed in response to this notice.
o. A license applicant must file no later than 60 days following
the date of issuance of this notice: (1) A copy of the water quality
certification; (2) a copy of the request for certification, including
proof of the date on which the certifying agency received the request;
or (3) evidence of wavier of water quality certification.
Dated: October 15, 2012.
Kimberly D. Bose,
Secretary.