[Federal Register Volume 77, Number 126 (Friday, June 29, 2012)]
[Notices]
[Pages 38856-38857]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2012-15962]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[NRC-2012-0110]
An Approach for Probabilistic Risk Assessment in Risk-Informed
Decisions on Plant-Specific Changes to the Licensing Basis
AGENCY: Nuclear Regulatory Commission.
ACTION: Draft regulatory guides; extension of comment period.
-----------------------------------------------------------------------
SUMMARY: On May 17, 2012 (77 FR 29391), the U.S. Nuclear Regulatory
Commission (NRC or the Commission) issued for public comment four (4)
draft regulatory guides (DGs), DG-1285, ``An Approach for Probabilistic
Risk Assessment in Risk-Informed Decisions on Plant-Specific Changes to
the Licensing Basis,'' (proposed Revision 3 of Regulatory Guide [RG]
1.174); DG-1286, ``An Approach for Plant-Specific, Risk-Informed
Decisionmaking: Inservice Testing,'' (proposed Revision 1 of RG 1.175);
DG 1287, ``An Approach for Plant-Specific, Risk-Informed
Decisionmaking: Technical Specifications'' (proposed Revision 2 of RG
1.177); and DG-1288, ``An Approach for Plant-Specific Risk-Informed
Decisionmaking for Inservice Inspection of Piping'' (proposed Revision
2 of RG 1.178) in the Federal Register for a 30 day public comment
period. The NRC is extending the public comment period for these DGs
from June 29, 2012 to August 13, 2012. These guides describe methods
the NRC staff considers acceptable for plant-specific, risk-informed
decisionmaking on specific licensee activities.
DATES: Submit comments by August 13, 2012. Comments received after this
date will be considered if it is practical to do so, but the NRC is
able to ensure consideration only for comments received on or before
this date. Although a time limit is given, comments and suggestions in
connection with items for inclusion in guides currently being developed
or improvements in all published guides are encouraged at any time.
ADDRESSES: You may access information and comment submissions related
to this document, which the NRC possesses and are publicly available,
by searching on http://www.regulations.gov under Docket ID NRC-2012-
0110. You may submit comments by any of the following methods:
Federal rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2012-0110. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-492-
3668; email: [email protected].
Mail comments to: Cindy Bladey, Chief, Rules,
Announcements, and Directives Branch (RADB), Office of Administration,
Mail Stop: TWB-05-B01M, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001.
Fax comments to: RADB at 301-492-3446.
For additional directions on accessing information and submitting
comments, see ``Accessing Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Carol Moyer, Office of Nuclear
Regulatory Research, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001, telephone: 301-251-7641 or email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Accessing Information and Submitting Comments
A. Accessing Information
Please refer to Docket ID NRC-2012-0110 when contacting the NRC
about the availability of information regarding this document. You may
access information related to this document, which the NRC possesses
and are publicly available, by any of the following methods:
Federal Rulemaking Web Site: Go to http://www.regulations.gov and search for Docket ID NRC-2012-0110.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly available documents online in the NRC
Library at http://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to [email protected]. The DGs and their
corresponding regulatory analysis are available electronically under
the following ADAMS Accession Numbers: DG-1285 (ML12012A006 and
ML12013A089), DG-1286 (ML12017A053 and ML12017A052), DG-1287
(ML12017A054 and ML12017A059), and DG1288 (ML12017A076 and
ML12017A077).
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
Regulatory guides are not copyrighted, and NRC approval is not
required to reproduce them.
B. Submitting Comments
Please include Docket ID NRC-2012-0110 in the subject line of your
comment submission, in order to ensure that the NRC is able to make
your comment submission available to the public in this docket.
The NRC cautions you not to include identifying or contact
information that you do not want to be publicly disclosed in your
comment submission. The NRC will post all comment submissions at http://www.regulations.gov as well as enter the comment submissions into
ADAMS. The NRC does not routinely edit comment submissions to remove
identifying or contact information.
If you are requesting or aggregating comments from other persons
for submission to the NRC, then you should inform those persons not to
include identifying or contact information that they do not want to be
publically disclosed in their comment submission. Your request should
state that the NRC does not routinely edit comment submissions to
remove such information before making the comment submissions available
to the public or entering the comment submissions into ADAMS.
II. Further Information
The NRC is issuing for public comment 4 draft regulatory guides in
the NRC's ``Regulatory Guide'' series. This series was developed to
describe
[[Page 38857]]
and make available to the public such information as methods that are
acceptable to the NRC staff for implementing specific parts of the
NRC's regulations, techniques that the staff uses in evaluating
specific problems or postulated accidents, and data that the staff
needs in its review of applications for permits and licenses.
These 4 draft regulatory guides are temporarily identified by their
task numbers, DG-1285, DG-1286, DG-1287, and DG-1288. The focus of the
revisions to these RGs addresses the Commission's Staff Requirements
Memorandum (SRM) (SECY-11-0014, issued 3-15-2011), titled ``Use of
Containment Accident Pressure in Analyzing Emergency Core Cooling
System and Containment Heat Removal System Pump Performance in
Postulated Accidents'' directing the staff to revise the discussion on
defense-in-depth. Specifically, the SRM stated,
Because the statements in Regulatory Guide 1.174 are subject to
different interpretations, the staff should revise this guide using
precise language to assure that the defense-in-depth philosophy is
interpreted and implemented consistently. To the extent that other
regulatory guidance refers to defense in depth, the relevant
documents should be updated also, as appropriate.
In reviewing these RGs, it was observed that clarification could be
added in several other places; for example:
The use of the terms ``PRA technical acceptability,''
``PRA technical adequacy,'' and ``PRA quality'' were not clear.
References in the RGs, in places, have been either updated
or are no longer in use.
Although the focus of this proposed revision is to revise the
discussion on defense-in-depth, the NRC staff believes that the
identified clarifications should be addressed. In DG-1285 (proposed
Rev. 3 of RG 1.174) the terms on PRA technical acceptability, PRA
technical adequacy, and PRA quality are revised to be consistent with
RG 1.200, ``An Approach for Determining the Technical Adequacy of
Probabilistic Risk Assessment Results for Risk-Informed Activities''
and the references were updated. It is the intent of the staff,
following the public review and comment period, to review all four RGs
and identify administrative changes that will improve the consistency,
quality, and usability of each guide. Stakeholders and the public are
requested to provide any input regarding areas in these DGs where
clarification and improvements may be needed.
DG-1285, is proposed revision 3 of Regulatory Guide 1.174 dated May
2011, it provides guidance on an approach the NRC finds acceptable for
analyzing issues associated with proposed changes to a plant's
licensing basis and for assessing the impact of these changes on the
risk associated with plant design and operation. One key element to
this type of decisionmaking is an engineering analysis of the proposed
change. As part of the engineering analysis, licensees evaluate the
impact of the change on maintaining adequate defense-in-depth. This
proposed revision incorporates additional language and specific
examples of how maintaining defense-in-depth is achieved when licensees
use risk-informed analysis of proposed changes to the plant's licensing
basis.
DG-1286, is proposed revision 1 of Regulatory Guide 1.175 dated
August 1998, it provides an approach to using risk-informed
decisionmaking in developing inservice testing programs for nuclear
power plants. This revision updates the defense-in-depth evaluation to
be consistent with the proposed changes to Regulatory Position 2.1.1 in
draft Regulatory Guide DG-1285, (above) which provides guidance on
evaluating proposed changes to a plant's licensing basis, including
changes to the inservice testing program.
DG-1287, is proposed revision 2 of Regulatory Guide 1.177 dated May
2011, it describes a method acceptable to the NRC for using
probabilistic risk analysis to evaluate proposed changes to a plant's
technical specifications. As in evaluating changes to a plant's
licensing basis, a key element in evaluating changes to technical
specifications is an engineering analysis of the proposed change. As
part of the engineering analysis, licensees evaluate the impact of the
change on maintaining adequate defense-in-depth. This revision updates
the defense-in-depth evaluation to be consistent with the proposed
changes to Regulatory Position 2.1.1 in draft Regulatory Guide DG-1285,
(above) which provides guidance on evaluating proposed changes to the
plant's technical specifications.
DG-1288, is proposed revision 2 of Regulatory Guide 1.178 dated
September 2003, it provides an approach to using risk-informed
decisionmaking in developing inservice inspection programs for piping
in nuclear power plants. This revision updates the defense-in-depth
evaluation to be consistent with the proposed changes to Regulatory
Position 2.1.1 in draft Regulatory Guide DG-1285, which provides
guidance on evaluating proposed changes to a plant's licensing basis,
including changes to the inservice inspection program for piping
systems.
On May 17, 2012 (77 FR 29391), the U.S. Nuclear Regulatory
Commission (NRC or the Commission) issued for public comment four (4)
DGs (DG-1285, DG-1286, DG-1287 and DG-1288). By letter dated June 4,
2012, the Nuclear Energy Institute (ADAMS Accession No. ML12174A174)
requested an extension of the stated comment period for the purpose of
providing sufficient review of the changes involving defense-in-depth
evaluations. It is the desire of the NRC to receive comments of high
quality from all stakeholders. Several factors have been considered in
granting an extension. The requested comment period extension is
reasonable and does not affect NRC deadlines. The additional time will
allow for stakeholders to discuss the proposed guide during related
meetings. Therefore, the comment submittal period is extended from the
original date of June 29, 2012 to August 13, 2012.
Dated at Rockville, Maryland, this 22nd day of June, 2012.
For the Nuclear Regulatory Commission.
Thomas H. Boyce,
Chief, Regulatory Guide Development Branch, Division of Engineering,
Office of Nuclear Regulatory Research.
[FR Doc. 2012-15962 Filed 6-28-12; 8:45 am]
BILLING CODE 7590-01-P