NUCLEAR REGULATORY COMMISSION
[NRC-2012-0065]
Preoperational Testing of Instrument and Control Air Systems
AGENCY: Nuclear Regulatory Commission.
ACTION: Draft regulatory guide; request for comment.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission (NRC or the Commission)
is issuing for public comment draft regulatory guide (DG), DG-1268,
``Preoperational Testing of Instrument and Control Air Systems.'' This
regulatory guide is being revised to address new issues that have been
raised since RG 1.68.3 was first issued. These include vibration
testing of instrument and control air systems (ICAS) to meet seismic
requirement, ICAS air-dryer testing to meet dew point design
requirements, ICAS accumulator check valves and solenoid valves
operating and testing experience, an update to ISA S7.3 for acceptable
industry standards for oil, water and particle matter in ICAS.
DATES: Submit comments by May 18, 2012. Comments received after this
date will be considered if it is practical to do so, but the NRC is
able to ensure consideration only for comments received on or before
this date. Although a time limit is given, comments and suggestions in
connection with items for inclusion in guides currently being developed
or improvements in all published guides are encouraged at any time.
ADDRESSES: You may access information and comment submissions related
to this document, which the NRC possesses and is publicly available, by
searching on http://www.regulations.gov under Docket ID NRC-2012-0065.
You may submit comments by the following methods:
[[Page 15814]]
Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2012-0065. Address
questions about NRC dockets to Carol Gallagher; telephone: 301-492-
3668; email: [email protected].
Mail comments to: Cindy Bladey, Chief, Rules,
Announcements, and Directives Branch (RADB), Office of Administration,
Mail Stop: TWB-05-B01M, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001.
Fax comments to: RADB at 301-492-3446.
For additional direction on accessing information and submitting
comments, see ``Accessing Information and Submitting Comments'' in the
SUPPLEMENTARY INFORMATION section of this document.
FOR FURTHER INFORMATION CONTACT: Frank Talbot, Division of Construction
Inspection, and Operational Programs, Office of New Reactors, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, telephone:
301-415-3146; email: [email protected].
SUPPLEMENTARY INFORMATION:
I. Accessing Information and Submitting Comments
A. Accessing Information
Please refer to Docket ID NRC-2012-0065 when contacting the NRC
about the availability of information regarding this document. You may
access information related to this document, which the NRC possesses
and is publicly available, by the following methods:
Federal Rulemaking Web Site: Go to http://www.regulations.gov and search for Docket ID NRC-2012-0065.
NRC's Agencywide Documents Access and Management System
(ADAMS): You may access publicly available documents online in the NRC
Library at http://www.nrc.gov/reading-rm/adams.html. To begin the
search, select ``ADAMS Public Documents'' and then select ``Begin Web-
based ADAMS Search.'' For problems with ADAMS, please contact the NRC's
Public Document Room (PDR) reference staff at 1-800-397-4209, 301-415-
4737, or by email to [email protected]. The draft regulatory guide
is available electronically under ADAMS Accession Number ML113180379.
The regulatory analysis may be found in ADAMS under Accession No.
ML113180380.
Regulatory guides are not copyrighted, and NRC approval is not
required to reproduce them.
NRC's PDR: You may examine and purchase copies of public
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555
Rockville Pike, Rockville, Maryland 20852.
B. Submitting Comments
Please include Docket ID NRC-2012-0065 in the subject line of your
comment submission, in order to ensure that the NRC is able to make
your comment submission available to the public in this docket.
The NRC cautions you not to include identifying or contact
information in comment submissions that you do not want to be publicly
disclosed. The NRC posts all comment submissions at http://www.regulations.gov as well as enters the comment submissions into
ADAMS. The NRC does not edit comment submissions to remove identifying
or contact information.
If you are requesting or aggregating comments from other persons
for submission to the NRC, then you should inform those persons not to
include identifying or contact information in their comment submissions
that they do not want to be publicly disclosed. Your request should
state that the NRC will not edit comment submissions to remove such
information before making the comment submissions available to the
public or entering the comment submissions into ADAMS.
II. Further Information
The NRC is issuing for public comment a draft guide in the NRC's
``Regulatory Guide'' series. This series was developed to describe and
make available to the public such information as methods that are
acceptable to the NRC staff for implementing specific parts of the
NRC's regulations, techniques that the staff uses in evaluating
specific problems or postulated accidents, and data that the staff
needs in its review of applications for permits and licenses.
The draft regulatory guide, entitled, ``Preoperational Testing of
Instrument and Control Air Systems,'' is temporarily identified by its
task number, DG-1268. The DG-1268 is proposed revision 2 of Regulatory
Guide 1.68.3, dated January 1977.
This guide describes methods and procedures the staff of the NRC
considers acceptable to implement preoperational testing of the
instrument and control air systems (ICAS) in a commercial nuclear power
plant. Successful demonstration of the operability of the ICAS is one
of the items required by Appendix A, ``General Design Criteria for
Nuclear Power Plants,'' of Title 10 of the Code of Federal Regulations,
part 50, ``Domestic Licensing of Production and Utilization
Facilities'' (10 CFR part 50). This guide also describes the methods
that the NRC staff finds acceptable for the initial test program for
ICAS systems, structures, and components (SSCs) in accordance with the
regulations in 10 CFR Part 52, ``Licenses, Certifications, and
Approvals for Nuclear Power Plants,'' Subpart B, ``Standard Design
Certifications,'' and Subpart C, ``Combined Licenses.''
For the Nuclear Regulatory Commission.
Dated at Rockville, Maryland, this 8th day of March, 2012.
Thomas H. Boyce,
Chief, Regulatory Guide Development Branch, Division of Engineering,
Office of Nuclear Regulatory Research.