[Federal Register Volume 76, Number 250 (Thursday, December 29, 2011)]
[Notices]
[Pages 81996-81998]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2011-33461]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-416; NRC-2011-0262]
Entergy Operations, Inc.; Notice of Intent To Prepare an
Environmental Impact Statement and Conduct the Scoping Process for
Grand Gulf Nuclear Station, Unit 1
AGENCY: Nuclear Regulatory Commission.
ACTION: Intent to prepare environmental impact statement and conduct
scoping process; public meeting.
-----------------------------------------------------------------------
SUMMARY: Entergy Operations, Inc. (Entergy) has submitted an
application for renewal of Facility Operating License NPF-29 for an
additional 20 years of operation at Grand Gulf Nuclear Station, Unit 1
(GGNS). GGNS is located in Claiborne County, Mississippi.
The current operating license for GGNS expires on November 1, 2024.
The application for renewal, dated October 28, 2011, was submitted
pursuant to Title 10 of the Code of Federal Regulations (10 CFR) part
54, which included an environmental report (ER). A separate notice of
receipt and availability of the application was published in the
Federal Register on November 17, 2011 (76 FRN 71379). A notice of
acceptance for docketing of the application and opportunity for hearing
regarding renewal of the facility operating license is also being
published in the Federal Register. The purpose of this notice is to
inform the public that the U.S. Nuclear Regulatory Commission (NRC or
the Commission) will be preparing an environmental impact statement
(EIS) related to the review of the license renewal application and to
provide the public an opportunity to participate in the environmental
scoping process, as defined in 10 CFR 51.29.
As outlined in 36 CFR 800.8, ``Coordination with the National
Environmental Policy Act,'' the NRC plans to coordinate compliance with
Section 106 of the National Historic Preservation Act (NHPA) in meeting
the requirements of the National Environmental Policy Act of 1969
(NEPA). Pursuant to 36 CFR 800.8(c), the NRC intends to use its process
and documentation for the preparation of the EIS on the proposed action
to comply with Section 106 of the NHPA in lieu of the procedures set
forth at 36 CFR 800.3 through 800.6.
In accordance with 10 CFR 51.53(c) and 10 CFR 54.23, Entergy
submitted the ER as part of the application.
DATES: Submit comments by February 27, 2012.
ADDRESSES: Please include Docket ID NRC-2011-0262 in the subject line
of your comments. For additional instructions on submitting comments
and instructions on accessing documents related to this action, see
``Submitting Comments and Accessing Information'' in the SUPPLEMENTARY
INFORMATION section of this document. You may submit comments by any
one of the following methods:
Federal Rulemaking Web Site: Go to http://www.regulations.gov and search for documents filed under Docket ID NRC-
2011-0262. Address questions about NRC dockets to Carol Gallagher,
telephone: (301) 492-3668; email: [email protected].
Mail comments to: Cindy Bladey, Chief, Rules,
Announcements, and Directives Branch (RADB), Office of Administration,
Mail Stop: TWB-05-B01M, U.S. Nuclear Regulatory Commission, Washington,
DC 20555-0001.
Fax comments to: RADB at (301) 492-3446.
SUPPLEMENTARY INFORMATION:
Submitting Comments and Accessing Information
Comments submitted in writing or in electronic form will be posted
on the NRC Web site and on the Federal rulemaking Web site, http://www.regulations.gov. Because your comments will not be edited to remove
any identifying or contact information, the NRC cautions you against
including any information in your submission that you do not want to be
publicly disclosed.
The NRC requests that any party soliciting or aggregating comments
received from other persons for submission to the NRC inform those
persons that the NRC will not edit their comments to remove any
identifying or contact information, and therefore, they should not
include any information in their comments that they do not want
publicly disclosed.
You can access publicly available documents related to this
document using the following methods:
NRC's Public Document Room (PDR): The public may examine
and have copied, for a fee, publicly available documents at the NRC's
PDR, O1-F21,
[[Page 81997]]
One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852.
NRC's Agencywide Documents Access and Management System
(ADAMS): Publicly available documents created or received at the NRC
are available online in the NRC Library at http://www.nrc.gov/reading-rm/adams.html. From this page, the public can gain entry into ADAMS,
which provides text and image files of the NRC's public documents. If
you do not have access to ADAMS or if there are problems in accessing
the documents located in ADAMS, contact the NRC's PDR reference staff
at 1-(800) 397-4209, (301) 415-4737, or by email to
[email protected]. The ER is available electronically under ADAMS
Accession Number ML113080132 and may also be viewed on the Internet at
http://www.nrc.gov/reactors/operating/licensing/renewal/applications.html. In addition, the ER is available to the public near
the site at the Harriette Person Memorial Library, 606 Main St., Port
Gibson, Mississippi 39150.
Federal Rulemaking Web Site: Public comments and
supporting materials related to this notice can be found at http://www.regulations.gov by searching on Docket ID NRC-2011-0262.
This notice advises the public that the NRC intends to gather the
information necessary to prepare a plant-specific supplement to the
NRC's ``Generic Environmental Impact Statement (GEIS) for License
Renewal of Nuclear Plants'' (NUREG-1437), related to the review of the
application for renewal of the GGNS operating license for an additional
20 years.
Possible alternatives to the proposed action (license renewal)
include no action and reasonable alternative energy sources. The NRC is
required by 10 CFR 51.95 to prepare a supplement to the GEIS in
connection with the renewal of an operating license. This notice is
being published in accordance with NEPA and the NRC's regulations found
at 10 CFR Part 51.
The NRC will first conduct a scoping process for the supplement to
the GEIS and, as soon as practicable thereafter, will prepare a draft
supplement to the GEIS for public comment. Participation in the scoping
process by members of the public and local, State, Tribal, and Federal
government agencies is encouraged. The scoping process for the
supplement to the GEIS will be used to accomplish the following:
a. Define the proposed action, which is to be the subject of the
supplement to the GEIS;
b. Determine the scope of the supplement to the GEIS and identify
the significant issues to be analyzed in depth;
c. Identify and eliminate from detailed study those issues that are
peripheral or that are not significant;
d. Identify any environmental assessments and other ElSs that are
being or will be prepared that are related to, but are not part of, the
scope of the supplement to the GEIS being considered;
e. Identify other environmental review and consultation
requirements related to the proposed action;
f. Indicate the relationship between the timing of the preparation
of the environmental analyses and the Commission's tentative planning
and decision-making schedule;
g. Identify any cooperating agencies and, as appropriate, allocate
assignments for preparation and schedules for completing the supplement
to the GEIS to the NRC and any cooperating agencies; and
h. Describe how the supplement to the GEIS will be prepared and
include any contractor assistance to be used.
The NRC invites the following entities to participate in scoping:
a. The applicant, Entergy;
b. Any Federal agency that has jurisdiction by law or special
expertise with respect to any environmental impact involved or that is
authorized to develop and enforce relevant environmental standards;
c. Affected State and local government agencies, including those
authorized to develop and enforce relevant environmental standards;
d. Any affected Indian tribe;
e. Any person who requests or has requested an opportunity to
participate in the scoping process; and
f. Any person who has petitioned or intends to petition for leave
to intervene.
In accordance with 10 CFR 51.26, the scoping process for an EIS may
include a public scoping meeting to help identify significant issues
related to a proposed activity and to determine the scope of issues to
be addressed in an EIS. The NRC has decided to hold public meetings for
the GGNS license renewal supplement to the GEIS. The scoping meetings
will be held on January 31, 2012, and there will be two sessions to
accommodate interested parties. The first session will convene at 2
p.m. and will continue until 3:30 p.m. The second session will convene
at 7 p.m. with a repeat of the overview portions of the meeting and
will continue until 8:30 p.m., as necessary. Both sessions will be held
at the Port Gibson City Hall, 1005 College Street, Port Gibson,
Mississippi 39150.
Both meetings will be transcribed and will include: (1) an overview
by the NRC staff of the NEPA environmental review process, the proposed
scope of the supplement to the GEIS, and the proposed review schedule;
and (2) the opportunity for interested government agencies,
organizations, and individuals to submit comments or suggestions on the
environmental issues or the proposed scope of the supplement to the
GEIS. Additionally, the NRC staff will host informal discussions one
hour prior to the start of each session at the same location. No formal
comments on the proposed scope of the supplement to the GEIS will be
accepted during the informal discussions. To be considered, comments
must be provided either at the transcribed public meetings or in
writing, as discussed in the ADDRESSES section of this notice.
Persons may register to attend or present oral comments at the
meetings on the scope of the NEPA review by contacting the NRC Project
Manager, David Drucker, by telephone at (800) 368-5642, ext. 6223, or
by email at [email protected] no later than January 24, 2012.
Members of the public may also register to speak at the meeting within
15 minutes of the start of each session. Individual oral comments may
be limited by the time available, depending on the number of persons
who register. Members of the public who have not registered may also
have an opportunity to speak if time permits. Public comments will be
considered in the scoping process for the supplement to the GEIS. David
Drucker will need to be contacted no later than January 10, 2012, if
special equipment or accommodations are needed to attend or present
information at the public meeting so that the NRC staff can determine
whether the request can be accommodated.
Participation in the scoping process for the supplement to the GEIS
does not entitle participants to become parties to the proceeding to
which the supplement to the GEIS relates. Matters related to
participation in any hearing are outside the scope of matters to be
discussed at this public meeting. The notice of acceptance for
docketing of the application and opportunity for hearing that was
published in the Federal Register describes the hearing process.
Dated at Rockville, Maryland, this 22nd day of December, 2011.
[[Page 81998]]
For the Nuclear Regulatory Commission.
David J. Wrona,
Chief, Projects Branch 2, Division of License Renewal, Office of
Nuclear Reactor Regulation.
[FR Doc. 2011-33461 Filed 12-28-11; 8:45 am]
BILLING CODE 7590-01-P