[Federal Register Volume 76, Number 187 (Tuesday, September 27, 2011)]
[Notices]
[Pages 59745-59748]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2011-24776]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-338 and 50-339]
Virginia Electric and Power Company; North Anna Power Station,
Unit Nos. 1 and 2; Exemption
1.0 Background
Virginia Electric Power Company (VEPCO, the licensee) is the holder
of Facility Operating License Nos. NPF-4 and NPF-7, which authorize
operation of the North Anna Power Station, Unit Nos. 1 and 2 (North
Anna) respectively. The license provides, among other things, that the
facility is subject to all rules, regulations, and orders of the U.S.
Nuclear Regulatory Commission (NRC or the Commission) now or hereafter
in effect. The facility consists of two pressurized water reactors
located in Louisa County, Virginia.
2.0 Request/Action
Title 10 of the Code of Federal Regulations (10 CFR) part 26,
``Fitness
[[Page 59746]]
For Duty Programs,'' Subpart I, ``Managing Fatigue,'' requires that
individuals described in 10 CFR 26.4(a)(1) through (a)(5) are subject
to the work hour controls provided in 10 CFR 26.205. By letter dated
February 10, 2011 (Agencywide Documents Access and Management System
(ADAMS), Accession No. ML110450583), and supplemented March 10, 2011
(ADAMS Accession No. ML110740442),and pursuant to 10 CFR 26.9, VEPCO,
doing business as Dominion, requested an exemption from the
requirements of 10 CFR 26.205(c) and (d) during declarations of severe
weather conditions such as tropical storm and hurricane force winds at
the North Anna site. A subsequent response to requests for additional
information (RAI) is dated May 26, 2011 (ADAMS Accession No.
ML111470265).
The requested exemption applies to individuals who perform duties
identified in 10 CFR 26.4(a)(1) through (a)(5) who are designated to
perform work as a member of the North Anna hurricane response
organization (HRO). The exemption request states that the station HRO
typically consists of enough individuals to staff two 12-hour shifts of
workers consisting of personnel from operations, maintenance,
engineering, emergency planning, radiation protection, chemistry, site
services and security to maintain the safe and secure operation of the
plant.
Entry conditions for the requested exemption occur when the site
activates the station HRO and the Site Vice President (or his designee)
determines that travel conditions to the site will potentially become
hazardous such that HRO staffing will be required based on verifiable
weather conditions. Verifiable weather conditions are defined in the
exemption request as when the National Weather Service issues an Inland
High Wind Warning for Hurricane Force Winds for Louisa County or when
the Dominion Weather Center projects tropical storm or hurricane force
winds onsite within 12 hours.
After the high wind conditions pass, wind damage to the plant and
surrounding area might preclude sufficient numbers of individuals from
immediately returning to the site. Additionally, if mandatory civil
evacuations were ordered, this would also delay the return of
sufficient relief personnel. The exemption request states that the
exemption will terminate when hurricane watches and warnings or inland
hurricane watches and warnings have been cancelled; when weather
conditions and highway infrastructure support safe travel; and when the
Site Vice President or his designee determine that sufficient personnel
who perform the duties identified in 10 CFR 26.4(a)(1) through (a)(5)
are available to restore normal shift rotation and thereby meet the
requirements of 10 CFR 26.205(c) and (d).
3.0 Discussion
Pursuant to 10 CFR 26.09, the Commission may, upon application of
an interested person or on its own initiative, grant exemptions from
the requirements of 10 CFR Part 26 when the exemptions are authorized
by law and will not endanger life or property or the common defense and
security, or are otherwise in the public interest.
Authorized by Law
The exemption being requested for North Anna would allow the
licensee to not meet the work hour control requirements of 10 CFR
26.205(c) and (d), which would allow the licensee to sequester specific
individuals on site, prior and subsequent to severe weather conditions
such as tropical storms and hurricanes. No law exists which precludes
the activities covered by this exemption request. As stated above, 10
CFR 26.09 allows the NRC to grant exemptions from the requirements of
10 CFR Part 26. The NRC staff has determined that granting of the
licensee's proposed exemption will not result in a violation of the
Atomic Energy Act of 1954, as amended, or the Commission's regulations.
Therefore, the exemption is authorized by law.
No Endangerment of Life or Property and Otherwise in the Public
Interest
This exemption request expands on an exception that is already
provided in 10 CFR Part 26, during declared emergencies, and allows the
licensee to not meet the requirements in 10 CFR 26.205(c) and (d)
during time periods just prior and subsequent to the existing exception
(10 CFR 26.207(d)). Granting this exemption will allow the licensee to
ensure that the control of work hours does not impede the ability to
use whatever staff resources may be necessary to respond to a severe
weather event to ensure the plant reaches and maintains a safe and
secure status. Therefore, this exemption will not endanger life or
property or the common defense and security. Thus, this exemption
request is in the interest of the public health and safety.
The Fatigue Management provisions found in 10 CFR part 26 subpart I
are designed as an integrated approach to managing both cumulative and
acute fatigue through a partnership between licensees and individuals.
It is the responsibility of the licensees to provide training to
individuals regarding fatigue management. It is also the responsibility
of the licensee to provide covered workers with work schedules that are
consistent with the objective of preventing impairment from fatigue due
to duration, frequency or sequencing of successive shifts. Individuals
are required to remain fit-for-duty while at work.
Section 26.205(c) is the requirement to schedule
individuals work hours consistent with the objective of preventing
impairment from fatigue due to duration, frequency or sequencing of
successive shifts. The requirement to schedule is important as the work
hour controls, contained in 10 CFR 26.205, are not necessarily
sufficient to ensure that individuals will not be impaired owing to the
effects of fatigue.
Section 26.205(d) provides the actual work hour controls.
Work hour controls are limits on the number of hours an individual may
work; limits on the minimum break times between work periods; and
limits for the minimum number of days off an individual must be given.
Section 26.205(b) is the requirement to count work hours
and days worked. 10 CFR 26.205(d)(3) is the requirement to look back
into the ``calculation period'' so that all work hours can be included
in appropriate work hour calculations, when a covered individual
resumes covered work.
Section 26.207(d) provides an allowance for licensees to
not meet the requirements of Sec. 26.205(c) and (d) during declared
emergencies as defined in the licensee's emergency plan.
North Anna is located in Louisa County, Virginia, and is
approximately 40 miles north-northwest of Richmond, Virginia.
Historical analysis of severe weather in the vicinity of the station
shows that there has been approximately an average of two tropical
storms or hurricanes every five years that have passed within 100
nautical miles of the site. Consequently, there is a reasonable
likelihood of North Anna being affected by severe wind events. The
proposed exemption would support effective response to severe weather
conditions when travel to and from the North Anna site may not be safe
or even possible.
During these times, the North Anna HRO staff typically consists of
enough individuals to staff two 12-hour shifts of workers consisting of
personnel from operations, maintenance, engineering, emergency
planning, radiation protection, chemistry, site services and security
to maintain the safe and secure operation of the plant. This exemption
would be applied to the period
[[Page 59747]]
established by the entry and exit conditions regardless of whether the
Emergency Plan is entered or not. Therefore, North Anna's exemption
request can be characterized as having three parts: (1) High-wind
exemption encompassing the period starting with the initiating
conditions to just prior to declaration of an unusual event, (2) a
period defined as immediately following a high-wind condition, when an
unusual event is not declared, but when a recovery period is still
required, and (3) a recovery exemption immediately following an
existing 10 CFR 26.207(d) exception as discussed above.
Once North Anna has entered into a high-wind exemption or 10 CFR
26.207(d) exception, it would not need to make a declaration that it is
invoking the recovery exemption. As a tropical storm or hurricane
approaches landfall, high wind speeds in excess of wind speeds that
create unsafe travel conditions are expected. The National Hurricane
Center defines a hurricane warning as an announcement that hurricane
conditions (sustained winds of 74 mph or higher) are expected somewhere
within the specified coastal area within a 24-hour period. Severe wind
preparedness activities become difficult once winds reach tropical
storm force, a tropical storm warning is issued 36 hours in advance of
the anticipated onset of tropical-storm-force winds (39 to 73 mph).
Lessons learned that are included in NUREG-1474, ``Effect of Hurricane
Andrew on the Turkey Point Nuclear Generating Station from August 20-
30, 1992,'' include the acknowledgement that detailed, methodical
preparations should be made prior to the onset of hurricane force
winds. The NRC staff finds the North Anna proceduralized actions are
consistent with those lessons learned.
The entry conditions for the requested exemption could have been
exceeded, yet wind speeds necessary for the declaration of an unusual
event may not have been reached. This circumstance may still require a
recovery period. Also, high winds that make travel unsafe but that fall
below the threshold of an emergency, could be present for several days.
After the high wind condition has passed, sufficient numbers of
personnel may not be able to access the site to relieve the sequestered
individuals. An exemption during these conditions is consistent with
the intent of the 10 CFR 26.207(d) exemption. Following a declared
emergency, under 10 CFR 26.207(d), due to high wind conditions, the
site may not be accessible by sufficient numbers of personnel to allow
relief of the sequestered individuals. Once the high wind conditions
have passed and the unusual event exited, a recovery period might be
necessary. An exemption during these circumstances is consistent with
the intent of 10 CFR 26.207(d).
The licensee's RAI response letter of May 26, 2011, states that the
HRO shift start times will be pre-planned and consistent and that the
hurricane response plan is being revised to emphasize the need for pre-
planned and consistent work shift start times to better facilitate
fatigue management. The RAI response also states that the hurricane
response plan will be updated to include that the HRO staff will be
provided with an opportunity for restorative rest of at least 10 hours
when off and that these individuals will not be assigned any duties
when off-shift.
The exemption request specifies that the exemption is not for
discretionary maintenance activities. The exemption request states that
the exemption would provide for use of whatever plant staff and
resources may be necessary to respond to a plant emergency and ensure
that the units achieve and maintain a safe and secure status and can be
safely restarted. The exemption request also states that maintenance
activities for structures, systems and components that are significant
to public health and safety will be performed, if required. The NRC
staff finds the exclusion of discretionary maintenance from the
exemption request to be consistent with the intent of the exemption.
In its exemption request the licensee committed to maintain the
following guidance in a North Anna site procedure:
The conditions necessary to sequester site personnel that
are consistent with the conditions specified in the North Anna
exemption request.
The provisions for ensuring that personnel who are not
performing duties are provided an opportunity as well as accommodations
for restorative rest.
The condition for departure from this exemption,
consistent with the Site Vice President's (or his designee's)
determination that adequate staffing is available to meet the
requirements of Part 26.205(c) and (d).
In its RAI response letter the licensee committed to maintain the
following guidance in its hurricane response procedure:
Guidance that emphasizes the need for pre-planned and
consistent work-shift start times to better facilitate fatigue
management.
Guidance that states that the Station Hurricane Response
Organization staff will be provided an opportunity for at least 10
hours of restorative rest when off-shift and should not be assigned any
duties when off-shift.
When the exemption period(s) ends, the licensee is immediately
subject to the scheduling requirements of 10 CFR 26.205(c) and the work
hour/rest break/days off requirements of 10 CFR 26.205(d), and must
ensure that any individual performing covered work complies with these
requirements. Section 26.205(d)(3) requires the licensee to ``look
back'' over the calculation period and count the hours the individual
has worked and the rest breaks and days off he/she has had, including
those that occurred during the licensee-declared emergency. Hours
worked must be below the maximum limits and rest breaks must be above
the minimum requirements in order for the licensee to allow the
individual to perform covered work. Days off and hours and shifts
worked during the licensee-declared emergency and the exempted period
before and after the declared emergency, would be counted as usual in
the establishment of the applicable shift schedule and compliance with
the minimum-days-off requirements.
Granting these exemptions is consistent with 10 CFR 26.207(d) Plant
Emergencies which allows the licensee to not meet the requirements of
10 CFR 26.205 (c) and (d) during declared emergencies as defined in the
licensee's emergency plan. The Part 26 Statement of Considerations in
the Federal Register on March 31, 2008, page 17148, states that ``Plant
emergencies are extraordinary circumstances that may be most
effectively addressed through staff augmentation that can only be
practically achieved through the use of work hours in excess of the
limits of Sec. 26.205(c) and (d).'' The objective of the exemption is
to ensure that the control of work hours do not impede a licensee's
ability to use whatever staff resources may be necessary to respond to
a plant emergency and ensure that the plant reaches and maintains a
safe and secure status. The actions described in the exemption request
and submitted procedures are consistent with the recommendations in
NUREG-1474, ``Effect of Hurricane Andrew on the Turkey Point Nuclear
Generating Station from August 20-30, 1992.'' Also consistent with
NUREG-1474, NRC staff expects the licensee would have completed a
reasonable amount of hurricane preparation prior to the need to
sequester personnel, in order to
[[Page 59748]]
minimize personnel exposure to high winds.
The NRC staff has reviewed the exemption request from certain work
hour controls during conditions of high winds and recovery from high
wind conditions. Based on the considerations discussed above, the NRC
staff has concluded that (1) there is a reasonable assurance that the
health and safety of the public will not be endangered by the proposed
exemption (2) such activities will be consistent with the Commission's
regulations and guidance, and (3) the issuance of the exemption will
not be contrary to the common defense and security or to the health and
safety of the public.
Consistent With Common Defense and Security
This change has no relation to security issues. Therefore, the
common defense and security is not impacted by this exemption.
4.0 Conclusion
Accordingly, the Commission has determined that, pursuant to 10 CFR
26.09, granting an exemption to the licensee from the requirements in
10 CFR 26.205(c) and (d) during severe wind events such as tropical
storms and hurricanes and bounded by the entry and exit conditions of
the exemption request, by allowing North Anna to sequester individuals
to ensure the plant reaches and maintains a safe and secure status, is
authorized by law, will not present an undue risk to the public health
and safety, and is consistent with the common defense and security.
Therefore, the Commission hereby grants Virginia Electric Power Company
an exemption from the requirement of 10 CFR 26.205(c) and (d) during
periods of severe winds.
Pursuant to 10 CFR 51.32, the Commission has determined that the
granting of this exemption will not have a significant effect on the
quality of the human environment published in the Federal Register on
August 31, 2011 (76 FR 54259).
This exemption is effective upon issuance.
Dated at Rockville, Maryland, this 20th day of September 2011.
For the Nuclear Regulatory Commission.
Joseph G. Giitter,
Director, Division of Operating Reactor Licensing, Office of Nuclear
Reactor Regulation.
[FR Doc. 2011-24776 Filed 9-26-11; 8:45 am]
BILLING CODE 7590-01-P