NUCLEAR REGULATORY COMMISSION
[NRC-2009-0476; DC/COL-ISG-018]
Office of New Reactors; Final Interim Staff Guidance on Standard
Review Plan, Section 17.4, ``Reliability Assurance Program''
AGENCY: Nuclear Regulatory Commission (NRC).
ACTION: Notice of availability.
-----------------------------------------------------------------------
SUMMARY: The NRC staff is issuing its Final Interim Staff Guidance
(ISG) DC/COL-ISG-018 (Agencywide Documents Access and Management System
(ADAMS) Accession No. ML103010113). The purpose of this ISG is to
clarify the NRC staff guidance on the design reliability assurance
program (RAP). This ISG updates the guidance provided to the staff in
Standard Review Plan (SRP), Section 17.4, ``Reliability Assurance
Program,'' of NUREG-0800, ``Standard Review Plan for the Review of
Safety Analysis Reports for Nuclear Power Plants,'' March 2007. This
ISG revises the NRC staff's review responsibilities and further
clarifies the acceptance criteria and evaluation findings contained in
the SRP Section 17.4 in support of the NRC reviews of
[[Page 17160]]
the design certification (DC) and combined license (COL) applications.
The NRC staff issues DC/COL-ISGs to facilitate timely implementation of
current staff guidance and to facilitate activities associated with NRC
review of applications for DCs and COLs. The NRC staff intends to
incorporate the final approved DC/COL-ISG-018 into the next revisions
of NUREG-0800, SRP Section 17.4 and Regulatory Guide (RG) 1.206,
``Combined License Applications for Nuclear Power Plants (LWR
Edition),'' June 2007.
Disposition: On October 30, 2009, the NRC staff issued proposed DC/
COL-ISG-018 on ``Reliability Assurance Program,'' ADAMS Accession No.
ML092290791. The staff received only editorial comments which were
incorporated. However, the ISG was further discussed at public meetings
held at the NRC during 2010. These public meetings primarily focused on
the Tier 1 inspections, tests, analyses, and acceptance criteria for
the COL RAP during the design stage, which is specified in the ISG.
This final issuance incorporates clarifications that resulted from
these public meetings. A document comparing the version of the ISG that
was issued for public comments and the final version of the ISG can be
found under ADAMS Accession No. ML103010361.
ADDRESSES: The NRC maintains ADAMS, which provides text and image files
of NRC's public documents. These documents may be accessed through the
NRC's Public Electronic Reading Room on the Internet at http://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to
ADAMS or who encounter problems in accessing the documents located in
ADAMS should contact the NRC Public Document Room reference staff at 1-
800-397-4209, 301-415-4737, or by e-mail at [email protected].
FOR FURTHER INFORMATION CONTACT: Mr. Todd A. Hilsmeier, Project
Manager, PRA and Severe Accidents Branch, Division of Safety Systems &
Risk Assessment, U.S. Nuclear Regulatory Commission, Washington, DC,
20555-0001; telephone: 301-415-0525 or e-mail: [email protected].
SUPPLEMENTARY INFORMATION: The agency posts its issued staff guidance
in the agency external Web page (http://www.nrc.gov/reading-rm/doc-collections/isg/).
Dated at Rockville, Maryland, this 22nd day of March 2011.
For the Nuclear Regulatory Commission,
William F. Burton,
Chief, Rulemaking and Guidance Development Branch, Division of New
Reactor Licensing, Office of New Reactor.
[FR Doc. 2011-7204 Filed 3-25-11; 8:45 am]
BILLING CODE 7590-01-P