[Federal Register Volume 75, Number 186 (Monday, September 27, 2010)]
[Proposed Rules]
[Pages 59158-59160]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2010-24132]
========================================================================
Proposed Rules
Federal Register
________________________________________________________________________
This section of the FEDERAL REGISTER contains notices to the public of
the proposed issuance of rules and regulations. The purpose of these
notices is to give interested persons an opportunity to participate in
the rule making prior to the adoption of the final rules.
========================================================================
Federal Register / Vol. 75, No. 186 / Monday, September 27, 2010 /
Proposed Rules
[[Page 59158]]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
10 CFR Part 54
[Docket No. PRM-54-6; NRC-2010-0291]
Earth Day Commitment/Friends of the Coast, Beyond Nuclear,
Seacoast Anti-Pollution League, C-10 Research and Education Foundation,
Pilgrim Watch, and New England Coalition; Notice of Receipt of Petition
for Rulemaking
AGENCY: Nuclear Regulatory Commission.
ACTION: Petition for rulemaking; Notice of receipt.
-----------------------------------------------------------------------
SUMMARY: The Nuclear Regulatory Commission (NRC) has received and
requests public comment on a petition for rulemaking dated August 18,
2010, submitted by Raymond Shadis and Mary Lampert on Behalf of Earth
Day Commitment/Friends of the Coast, Beyond Nuclear, Seacoast Anti-
Pollution League, C-10 Research and Education Foundation, Pilgrim
Watch, and New England Coalition, for docketing as a petition for
rulemaking under 10 CFR 2.802. In another letter dated August 18, 2010,
Robin Read, State Representative for New Hampshire, requested to be
included as a petitioner for this petition for rulemaking. The petition
was docketed by the NRC and has been assigned PRM-54-6. The petitioners
request that the NRC amend its regulations to permit a license renewal
application no sooner than 10 years before the expiration of the
current license and to apply the rule to all license renewal
applications that have not yet been issued an NRC staff Final Safety
Evaluation Report (FSER). The petitioners also requested a freeze on
all new relicensing activity until the rulemaking is decided.
DATES: Submit comments by December 13, 2010. Comments received after
this date will be considered if it is practical to do so, but the NRC
is able to assure consideration only for comments received on or before
this date.
ADDRESSES: Please include Docket ID NRC-2010-0291 in the subject line
of your comments. For instructions on submitting comments and accessing
documents related to this action, see ``Submitting Comments and
Accessing Information'' in the SUPPLEMENTARY INFORMATION section of
this document. You may submit comments by any one of the following
methods.
Federal Rulemaking Web Site: Go to http://www.regulations.gov and
search for documents filed under Docket ID NRC-2010-0291. Address
questions about NRC dockets to Carol Gallagher, telephone 301-492-3668;
e-mail [email protected].
Mail comments to: Secretary, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, Attn: Rulemakings and Adjudications Staff.
E-mail comments to: [email protected]. If you do not
receive a reply e-mail confirming that we have received your comments,
contact us directly at 301-415-1966.
Hand Deliver comments to: 11555 Rockville Pike, Rockville, Maryland
20852 between 7:30 a.m. and 4:15 p.m. during Federal workdays
(Telephone 301-415-1966).
Fax comments to: Secretary, U.S. Nuclear Regulatory Commission at
301-415-1101.
FOR FURTHER INFORMATION CONTACT: Cindy Bladey, Chief, Rules,
Announcements, and Directives Branch, Division of Administrative
Services, Office of Administration, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, Telephone 301-492-3667, toll free 800-368-
5642, [email protected].
SUPPLEMENTARY INFORMATION:
Submitting Comments and Accessing Information
Comments submitted in writing or in electronic form will be posted
on the NRC Web site and on the Federal rulemaking Web site http://www.regulations.gov. Because your comments will not be edited to remove
any identifying or contact information, the NRC cautions you against
including any information in your submission that you do not want to be
publicly disclosed. The NRC requests that any party soliciting or
aggregating comments received from other persons for submission to the
NRC inform those persons that the NRC will not edit their comments to
remove any identifying or contact information, and therefore, they
should not include any information in their comments that they do not
want publicly disclosed.
You can access publicly available documents related to this
document, including the following documents, using the following
methods:
NRC's Public Document Room (PDR): The public may examine and have
copied for a fee publicly available documents at the NRC's PDR, Room O-
1F21, One White Flint North, 11555 Rockville Pike, Rockville, Maryland.
NRC's Agencywide Documents Access and Management System (ADAMS):
Publicly available documents created or received at the NRC are
available electronically at the NRC's Electronic Reading Room at http://www.nrc.gov/reading-rm/adams.html. From this page, the public can gain
entry into ADAMS, which provides text and image files of NRC's public
documents. If you do not have access to ADAMS or if there are problems
in accessing the documents located in ADAMS, contact the NRC's PDR
reference staff at 1-800-397-4209, or 301-415-4737, or by e-mail to
[email protected]. The ADAMS accession number for the petition is
ML1023803790.
Federal Rulemaking Web Site: Public comments and supporting
materials related to this action, including the petition for
rulemaking, can be found at http://www.regulations.gov by searching on
Docket ID NRC-2010-0291.
Petitioners
The petitioners all have a residence or interests within 50 miles
of the NextEra Seabrook Nuclear Generating Station, which has applied
for license renewal (Docket 050-00443) at 10 CFR 54.17(c), 20 years in
advance of the end of its current license. The petitioning
organizations all have members residing within 50 miles of NextEra
Seabrook Nuclear Generating Station. The petitioners who are elected-
officials represent constituents who reside within 50 miles of NextEra
Seabrook Nuclear Generating Station.
The petitioners are as follows:
Friends of the Coast has been incorporated as a non-profit, for the
public good, corporation in the State of Maine since 1995. Friends of
the Coast has members who live within fifty miles of the NextEra
Seabrook Nuclear Generating Station, which has applied
[[Page 59159]]
for license renewal 20 years in advance of the expiration of its
current license under 10 CFR 54.17(c).
Beyond Nuclear is incorporated as a not for profit organization
based in Takoma Park, MD, which aims to educate and activate the public
about the connections between nuclear power and nuclear weapons. Beyond
Nuclear has members who live and work within fifty miles of the NextEra
Seabrook Nuclear Generating Station which has applied for a license
renewal 20 years in advance of the expiration of its current license
under 10 CFR 55.17(c).
New England Coalition has been incorporated as a not for profit
corporation in the State of Vermont since 1971. It has intervened in
NRC licensing and license amendment proceedings at Vermont Yankee,
Yankee Rowe, and Seabrook.
Seacoast Anti-Pollution League (SAPL). SAPL has worked since 1969
to protect the health, safety and general well-being of the New
Hampshire Seacoast community from nuclear pollution and other threats
to the environment. Most of SAPL's members live and work within fifty
miles of the NextEra Seabrook Nuclear Generating Station.
New England Coalition has members who live within fifty miles of
the NextEra Seabrook Nuclear Generating Station, which has applied for
license renewal 20 years in advance of the expiration of its current
license under 10 CFR 54.17(c).
Pilgrim Watch is a public interest organization located in Duxbury,
MA. Pilgrim Watch is an intervener in the Entergy Pilgrim Nuclear Power
Station license renewal application. Pilgrim Watch has members who
reside within 50 miles of Seabrook Station.
C-10 Research & Education Foundation is located in Newburyport, MA,
and has members who reside within 50 miles of Seabrook Generating
Station. C-10 maintains an environmental monitoring system in the
vicinity of Seabrook Generating Station and provides public education
on environmental and energy matters.
Robin Read is a State Representative for the State of New
Hampshire.
Background
Grounds for Action Requested
The petitioners state that the NRC's current regulation (10 CFR
54.17), is unduly non-conservative with respect to its effect on
accuracy and completeness of the application, public participation,
changing environmental consideration, aging analysis and management,
regulatory follow-through, National Environmental Policy Act
compliance, changing regulation, and more. The petitioners state that
they seek to restore some margin of conservation by halving the lead
time on license renewal applications from 20 to 10 years.
The petitioners state that a rulemaking for 10 CFR 54.17(c) was
conducted more than 15 years ago. The rulemaking took place before
sweeping changes in NRC oversight and before economic and regulatory
shifts that enabled unprecedented changes in ownership and an industry-
wide shift of focus from anticipated decommissioning to uprate and
license renewal. The petitioners state that the rulemaking cannot have
contemplated how these changes have affected the dynamics of license
renewal aging analysis and aging management planning over a period of
40 years (20 years of current license, plus 20 years of extended period
of operation). The petitioners claim that because the rule does not
take into consideration its present context, the rule is antiquated and
obsolete and must be reconsidered.
The petitioners state that of 32 license renewals granted, none
were filed 20 years in advance of license expiration and only among 14
license renewal applications under consideration and filed in the last
few years is an exception to be found, Seabrook Station-Unit 1. The
petitioners state that NextEra Seabrook has provided no credible
justification for its very early filing. The petitioners state that the
great majority of licensees have filed applications for license renewal
within 10 years of original license expiration without any apparent
negative consequences. The petitioners believe that this experience is
a clear demonstration that more than 10 years lead time is unnecessary
and of little benefit. The petitioners state that filing, reviewing,
and granting license renewal applications more than 10 years in advance
of the original license expiration can have negative consequences.
The petitioners state that the rulemaking for 10 CFR 54.17(c)
proceeded without sufficient consideration of the impact of 20 year
advance consideration of license renewal on the hearing rights of
affected persons. By renewing the license of a nuclear power station 20
years in advance of the licensed extended period of operation NRC
removes to the distance of a full generation, the opportunity for an
adjudicatory hearing, a coming generation of affected residents,
visitors, and commercial interests as yet unable or unprepared to speak
for themselves. The petitioners state that 10 CFR 54.17(c) introduces
the question of whether the action proposed is obtaining the license or
entering into an extended period of operation 20 years hence. The
petitioners believe that the safety and environmental ramifications
(the physical impact on affected persons) begin 20 years away. The
petitioners state that 10 CFR 54.17(c) allows for effective
segmentation of the proposed action rendering the permission so far
removed in time from the implementation as to provide an intellectual
disconnect or, in effect, void legal notice.
The petitioners state that 10 CFR 54.17(c) allows licensees and NRC
reviewing staff to press to untenable lengths the unproven ability to
predict the aging and deterioration of systems, structures, and
components (SSCs). The petitioners state that 10 CFR 54.17(c) promotes
failure of the license renewal application to encompass the potential
effects of an environment that is arguably changing at an unprecedented
rate. The petitioners state that active proposals for more than 3,000
megawatts of wind power are currently on the books in New England, with
potential for 12,000 more. The petitioners state that it cannot be
credibly projected over 20 years what wind power will then be
available, in part because wind power projects are seldom, if ever,
planned 20 years in advance.
The petitioners state that filing for license renewal at mid-term
of the current license finds the licensee at a place in SSC service
life where in industry experience, few failures are observed and,
generally, those that are observed are episodic or anomalous in nature
and cannot be readily plotted as a trend for prediction purposes. The
petitioners state that the time of an elevated rate of failures due to
design, manufacturing, and construction defects has passed and is
largely irrelevant to aging management in the proposed extended period
of operation. The petitioners state that the anticipated end-of-design
life and aging issues have barely, if at all, begun to emerge, so
little or no plant-specific information on how a given plant will age
is available to be trended, provide lessons, or otherwise illuminate
the path forward. It is generally observed that for many SCCs this
information flow rates increase rapidly in the fourth quarter and
toward the end of a license. The petitioners state that this SSC
reliability progression is well-known and often illustrated in the so-
called ``Bath Tub Curve.'' Additionally, corrosion risk is a function
of time. The petitioners state that the Beaver Valley NPP containment
[[Page 59160]]
issue provides a powerful example of operating experience emerging at a
late date in a way that affects the license renewal. VT Yankee also
provides a series of later life structural failures as additional
examples. The petitioners state that it is appropriate, from a
regulatory audit standpoint, to wait until applicable failure rate and
observed aging phenomena data is in hand, before attempting time-
limited aging analysis or aging management planning; less than 10; not
less than 20 years in advance of operating license expiration.
The petitioners state that the current rule exacerbates NRC staff
and licensee difficulty in following license renewal commitments. The
petitioners state that license renewal applications are often approved
with the proviso that certain commitments be made and fulfilled;
generally before the period of extended operation begins. These
commitments often include inspections, tests, analyses, and development
of programs vital to safety and environmental protection. The
petitioners state that regulatory experience shows NRC staff turnover,
changes in oversight, licensee staff changes, and ownership (licensee)
changes, greater in a 20-year period than a 10-year period, will at
once complicate and place increased emphasis on proper handoff of
unfulfilled licensee commitments.
The petitioners state that 20 years from application to onset of
extended operation will, based on regulatory history, certainly see an
inordinate amount of applicable regulatory change, with lack of
compliance likely to be grandfathered in. The petitioners state that
current issues under consideration for treatment in the license renewal
process include aging management for underground, buried, or
inaccessible pipes that carry radionuclides, and aging management for
safety-related low voltage cables that are below-grade and not
qualified for a wet environment.
The petitioners state that, in its current form, the regulation
conflicts with, circumvents, and otherwise frustrates the letter and
spirit of the National Environmental Policy Act (NEPA). The petitioners
state it further conflicts with, circumvents, and otherwise frustrates
the object and goals of NEPA. The petitioners state that the NEPA
provides at Section 1500.2, that the Federal agencies, ``shall to the
fullest extent possible: (e) Use the NEPA process to identify and
assess the reasonable alternatives to proposed actions that will avoid
or minimize adverse effects of these actions upon the quality of the
human environment.'' The petitioners state that the Act provides at
Section 1500.1(b) that ``NEPA procedures must insure that environmental
information is available to public officials and citizens before
decisions are made and before actions are taken. The information must
be of high quality. Accurate scientific analysis, expert agency
comments, and public scrutiny are essential to implementing NEPA. Most
important, NEPA documents must concentrate on the issues that are truly
significant to the action in question, rather than amassing needless
detail.''
The Petition
The petitioners request that the NRC amend its regulations to
change the time before expiration of the operating license or combined
license currently in effect in which a licensee may apply for a renewed
license from 20 to 10 years. The petitioners request that the NRC amend
10 CFR 54.17(c) to read as follows:
An application for a renewed license may not be submitted to the
Commission earlier than 20 years before the expiration of the operating
license or combined license currently in effect.
An application for a renewed license may not be submitted to the
Commission earlier than 10 years before the expiration of the operating
license or combined license currently in effect.
Petitioner's Request To Suspend All License Renewal Review Pending
Disposition of the Petition for Rulemaking
The petitioners request that the Commission suspend all license
renewal review pending disposition of this petition for rulemaking. The
petitioners state that given the lead-in time on the application(s) and
the fact that no additional work would be required of the licensee, no
significant additional burden would accrue to the applicant. The
petitioners state that, inasmuch as several petitioners intend to file
requests for a hearing and petitions for leave to intervene in the
matter of Seabrook license renewal, this suspension would preserve the
order of the application review process and contribute to judicial
efficiency and economy. The petitioners state that further suspension
of review activities now would avoid duplication of effort should the
Commission issue the requested rule change.
The petitioners state that although they are not parties to a
proceeding in this matter and no proceeding has yet been convened, the
petitioners urge the Commission to find that the present situation is
analogous to that described in 10 CFR 2.802(d) and to exercise its
discretion for the benefit of the NRC and all parties by suspending
review of all license renewal applications submitted more than10 years
in advance of current license expiration until resolution of this
petition.
The NRC has determined that this request is not part of the
rulemaking process. The NRC will address in a separate action the
petitioners' request to freeze all new relicensing activity pending
disposition of the PRM.
Conclusion
For the reasons stated previously the petitioners request that NRC
revise its regulations at 10 CFR 54.17 to permit license renewal
application no sooner than 10 years before the expiration of current
license and to apply the rule to all license renewal applications that
have not yet been issued an NRC staff FSER.
Dated at Rockville, Maryland, this 21st day of September 2010.
For the Nuclear Regulatory Commission.
Annette L. Vietti-Cook,
Secretary of the Commission.
[FR Doc. 2010-24132 Filed 9-24-10; 8:45 am]