[Federal Register Volume 75, Number 101 (Wednesday, May 26, 2010)]
[Notices]
[Pages 29577-29582]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2010-12658]


-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Indian Affairs


Rate Adjustments for Indian Irrigation Projects

AGENCY: Bureau of Indian Affairs, Interior.

ACTION: Notice of Rate Adjustments.

-----------------------------------------------------------------------

SUMMARY: The Bureau of Indian Affairs (BIA) owns, or has an interest 
in, irrigation projects located on or associated with various Indian 
reservations throughout the United States. We are required to establish 
irrigation assessment rates to recover the costs to administer, 
operate, maintain, and rehabilitate these projects. We are notifying 
you that we have adjusted the irrigation assessment rates at several of 
our irrigation projects and facilities to reflect current costs of 
administration, operation, maintenance, and rehabilitation.

DATES: Effective Date: The irrigation assessment rates shown in the 
tables as final are effective as of January 1, 2010.

FOR FURTHER INFORMATION CONTACT: For details about a particular BIA 
irrigation project or facility, please use the tables in the 
SUPPLEMENTARY INFORMATION section to contact the regional or local 
office where the project or facility is located.

SUPPLEMENTARY INFORMATION:

I. Effect of this Notice
II. Responses to Comments on Proposed Rate Adjustments
III. Further Information on This Notice
IV. Administrative Requirements

I. Effect of This Notice

Does this notice affect me?

    This notice affects you if you own or lease land within the 
assessable acreage

[[Page 29578]]

of one of our irrigation projects, or if you have a carriage agreement 
with one of our irrigation projects.

What irrigation assessments or charges are adjusted by this notice for 
the 2010 season?

    The rate table below contains the current, final rates for the 2010 
season for all irrigation projects where we recover costs of 
administering, operating, maintaining, and rehabilitating them. An 
asterisk following the name of the project notes the irrigation 
projects where the 2010 rates are different from the 2009 rates.

----------------------------------------------------------------------------------------------------------------
                Project name                           Rate category           Final 2009 rate   Final 2010 rate
----------------------------------------------------------------------------------------------------------------
                                           Northwest Region Rate Table
----------------------------------------------------------------------------------------------------------------
Flathead Irrigation Project *...............  Basic per acre--A.............            $23.45            $23.45
                                              Basic per acre--B.............             10.75             11.75
                                              Minimum Charge per tract......             65.00             65.00
Fort Hall Irrigation Project................  Basic per acre................             40.50             40.50
                                              Minimum Charge per tract......             30.00             30.00
Fort Hall Irrigation Project--Minor Units...  Basic per acre................             21.00             21.00
                                              Minimum Charge per tract......             30.00             30.00
Fort Hall Irrigation Project--Michaud.......  Basic per acre................             41.50             41.50
                                              Pressure per acre.............             58.00             58.00
                                              Minimum Charge per tract......             30.00             30.00
Wapato Irrigation Project--Toppenish/Simcoe   Minimum Charge for per tract..             15.00             15.00
 Units.
                                              Basic per acre................             15.00             15.00
Wapato Irrigation Project--Ahtanum Units....  Minimum Charge per tract......             15.00             15.00
                                              Basic per acre................             15.00             15.00
Wapato Irrigation Project--Satus Unit *.....  Minimum Charge per tract......             58.00             60.00
                                              ``A'' Basic per acre..........             58.00             60.00
                                              ``B'' Basic per acre..........             68.00             70.00
Wapato Irrigation Project--Additional Works   Minimum Charge per tract......             63.00             65.00
 *.
                                              Basic per acre................             63.00             65.00
Wapato Irrigation Project--Water Rental *...  Minimum Charge................             70.00             72.00
                                              Basic per acre................             70.00             72.00
----------------------------------------------------------------------------------------------------------------
                                        Rocky Mountain Region Rate Table
----------------------------------------------------------------------------------------------------------------
Blackfeet Irrigation Project *..............  Basic-per acre................             18.00             19.00
Crow Irrigation Project--Willow Creek O&M     Basic-per acre................             20.80             22.80
 (includes Agency, Lodge Grass 1,
 Lodge Grass 2, Reno, Upper Little
 Horn, and Forty Mile Units) *.
Crow Irrigation Project--All Others           Basic-per acre................             20.50             22.50
 (includes Bighorn, Soap Creek, and Pryor
 Units) *.
Crow Irrigation Two Leggins Drainage          Basic-per acre................              2.00              2.00
 District.
Fort Belknap Irrigation Project.............  Basic-per acre................             14.75             14.75
Fort Peck Irrigation Project *..............  Basic-per acre................             24.00             24.70
Wind River Irrigation Project *.............  Basic-per acre................             18.00             20.00
Wind River Irrigation Project--LeClair        Basic-per acre................             19.00             27.00
 District *.
Wind River Irrigation Project--CrowHeart      Basic-per acre................             18.00             14.00
 Unit *.
----------------------------------------------------------------------------------------------------------------
                                           Southwest Region Rate Table
----------------------------------------------------------------------------------------------------------------
Pine River Irrigation Project...............  Minimum Charge per tract......             50.00             50.00
                                              Basic-per acre................             15.00             15.00
----------------------------------------------------------------------------------------------------------------
                                            Western Region Rate Table
----------------------------------------------------------------------------------------------------------------
Colorado River Irrigation Project *.........  Basic per acre up to 5.75 acre-            51.00             52.50
                                               feet.
                                              Excess Water per acre-foot                 17.00             17.00
                                               over 5.75 acre-feet.
Duck Valley Irrigation Project..............  Basic per acre................              5.30              5.30
Fort Yuma Irrigation Project (See Note        Basic per acre up to 5.0 acre-             77.00             86.00
 1) *.                                feet.
                                              Excess Water per acre-foot                 14.00             14.00
                                               over 5.0 acre-feet.
                                              Basic per acre up to 5.0 acre-             77.00             86.00
                                               feet (Ranch 5).
San Carlos Irrigation Project (Joint Works)   Basic per acre................             21.00             21.00
 (See Note  2).
San Carlos Irrigation Project (Indian Works)  Basic per acre................             57.00             57.00
Uintah Irrigation Project...................  Basic per acre................             15.00             15.00
                                              Minimum Bill..................             25.00             25.00
Walker River Irrigation Project *...........  Basic per acre, Indian........             16.00             19.00
                                              Basic per acre, non-Indian....             16.00             19.00
----------------------------------------------------------------------------------------------------------------
* Notes irrigation projects where rates have been adjusted.
Note 1--The O&M rate for the Fort Yuma Irrigation Project has two components. The first component is
  the O&M rate established by the Bureau of Reclamation (BOR), the owner and operator of the Project. The BOR
  rate for 2010 is $79.00/acre. The second component is for the O&M rate established by BIA to cover
  administrative costs including billing and collections for the Project. The 2010 BIA rate remains unchanged at
  $7.00/acre. The rates shown include the 2010 Reclamation rate and the 2010 BIA rate.
Note 2--The 2010 rate was established by final notice published in the Federal Register on April 22,
  2009 (Vol. 74, No. 76, page 18398).


[[Page 29579]]

When will BIA publish irrigation assessments or charges for the 2011 
season?

    We published some proposed rates for the 2011 season in the Federal 
Register on October 23, 2009 (74 FR 54848), and we will publish other 
proposed 2011 rates in the near future. We will publish the 2011 season 
final rates in the Federal Register after considering any comments that 
we receive on our proposals. (We have already published final rates for 
the 2011 season for the San Carlos Irrigation Project (74 FR 40227).)

----------------------------------------------------------------------------------------------------------------
                                                                                                           Final
              Project name                      Rate category         Final 2009 rate    Final 2010 rate    2011
                                                                                                            rate
----------------------------------------------------------------------------------------------------------------
                                            Western Region Rate Table
----------------------------------------------------------------------------------------------------------------
San Carlos Irrigation Project (Joint     Basic per acre............            $21.00             $21.00   $25.0
 Works) (See Note 3).                                                                               0
----------------------------------------------------------------------------------------------------------------
Note 3-The 2011 rate was established by final notice published in the Federal Register on August 11,
  2009 (Vol. 74, No. 153, page 40227).

Has a Notice of Proposed Rate Adjustment been published?

    Yes. A Notice of Proposed Rate Adjustment was published in the 
Federal Register on October 23, 2009 (74 FR 54846) to propose 
adjustments to the irrigation assessment rates at several BIA 
irrigation projects. The public and interested parties were provided an 
opportunity to submit written comments during the 60-day period that 
ended December 22, 2009.

Did the BIA defer or change any proposed rate increases?

    No.

II. Responses to Comments on Proposed Rate Adjustments

Did the BIA receive any comments on the proposed irrigation assessment 
rate adjustments?

    BIA received written comments related to the proposed rate 
adjustments for the Crow Irrigation Project and the Wapato Irrigation 
Project.

What issues were of concern to the commenters?

    Commenters raised concerns specific to the Crow Irrigation Project 
about the following issues: (1) Opposition to the $2.00 rate increase 
for 2010; (2) opposition to the amount of the operation and maintenance 
(O&M) budget spent on administration and salaries versus maintenance 
projects; (3) lack of supervision and direction during the irrigation 
season; (4) opposition to the hiring of additional project employees; 
(5) efficiencies of contracting with private entities to perform O&M; 
and (6) impact of rate increases on the local agricultural economy and 
individual land owners.
    Commenters raised concerns specific to the Wapato Irrigation 
Project on the proposed rates about one or more of the following 
issues: (1) Objection that the underlying O&M charges are inconsistent 
with the Yakama Nation's litigation position in the pending appeals ; 
and (2) assertion concerning BIA's responsibility to manage land that 
is designated for irrigation water delivery.

The following comments are specific to the Crow Irrigation Project: How 
does the BIA respond to the opposition to the $2.00 rate increase for 
2010?

    The proposed 2010 O&M budget for the Crow Irrigation Project budget 
was prepared in accordance with BIA financial guidelines. The BIA 
considers the following when determining an irrigation project's 
budget: project personnel costs; materials and supplies; vehicle and 
equipment repairs; equipment; capitalization expenses; acquisition 
expenses; rehabilitation costs; maintenance of a reserve fund for 
contingencies or emergencies; and other expenses that are determined to 
be necessary to operate and maintain an irrigation project. The 
proposed 2010 O&M budget for the Crow Irrigation Project contains 
increased amounts in staffing, contracts, and materials in an effort to 
address increasing project rehabilitation needs. These increased budget 
amounts support the rate increase of $2.00.

How does the BIA respond to the opposition to the amount of O&M budget 
spent on administration and salaries versus maintenance projects?

    The proposed 2010 O&M budget for the Crow Irrigation Project is an 
increase of approximately three percent (3%) over the 2009 O&M budget. 
Administrative salaries have been held steady from 2009 to 2010 at 
approximately 28% to 29% of the entire budget. In 2009 the amount 
budgeted for maintenance contracts and materials was 16% of the budget 
total and in 2010 that amount was increased to 32% of the budget total. 
The BIA is committed to working with local stakeholders in the 
development of other cost-saving options. Examples of cost-saving 
options include stakeholder contracts or agreements for selected O&M 
functions within the project boundaries.

How does the BIA respond to the lack of supervision and direction 
during the irrigation season?

    At the end of the 2008 irrigation season, the Crow Irrigation 
Supervisory Project Engineer vacated to take a new position. In early 
March 2009, the BIA advertised for new Crow Irrigation Supervisory 
Project Engineer. Later that month, the BIA entered into negotiations 
with the Crow Tribe in response to its request to contract all of the 
O&M functions of the Crow Irrigation Project for the 2009 season. These 
contract negotiations resulted in cancellation of the Project Engineer 
vacancy announcement. The Crow Tribe subsequently canceled its request 
for contracting options, and the supervisory position went unfilled in 
the 2009 irrigation season. Currently, BIA is pursuing a stakeholder 
cooperative agreement for O&M activities for the 2010 season. The 
extent of O&M cooperative agreements will help BIA determine the type 
of supervision required at the Crow Irrigation Project for 2010.

How does the BIA respond to opposition to the hiring of additional 
project employees?

    In July 2008, the BIA conducted a program review of the Crow 
Irrigation Project and found, ``the number of equipment operators and 
irrigation system operators is insufficient. This reduces the amount of 
control the project has over water deliveries. Most if not all repair 
work is reactionary versus planned.'' (2008 Program Review, Crow 
Irrigation Project, page 8). In the follow-up Corrective Action Plan, 
the Project and Regional staff agreed to increase staff to fill vacant 
positions and/or pursue stakeholder agreements to increase the level of 
maintenance activities. The final decision on hiring additional field 
staff for 2010 is dependent on the development of

[[Page 29580]]

stakeholder agreements. Likewise, the timing of a new Project Engineer 
is also dependent on the development of stakeholder agreements.

How does the BIA respond to the efficiencies of contracting with 
private entities to perform O&M?

    The BIA agrees with the potential for efficiency increases through 
contracting options. The BIA continues to encourage stakeholder 
cooperative agreements for selected O&M activities for the 2010 season.

How does the BIA respond to how rate increases impact the local 
agricultural economy and individual land owners?

    The BIA's projects are important economic contributors to the local 
communities they serve. These projects contribute millions of dollars 
in crop value annually. Historically, the BIA tempered irrigation rate 
increases to demonstrate sensitivity to the economic impact on water 
users. This past practice resulted in a rate deficiency at some 
irrigation projects. The BIA does not have discretionary funds to 
subsidize irrigation projects. Funding to operate and maintain these 
projects needs to come from revenues from the water users served by 
those projects.
    The BIA's irrigation program has been the subject of several Office 
of Inspector General (OIG) and U.S. Government Accountability Office 
(GAO) audits. In the most recent OIG audit, No. 96-I-641, March 1996, 
the OIG concluded:

    Operation and maintenance revenues were insufficient to maintain 
the projects, and some projects had deteriorated to the extent that 
their continued capability to deliver water was in doubt. This 
occurred because operation and maintenance rates were not based on 
the full cost of delivering irrigation water, including the costs of 
systematically rehabilitating and replacing project facilities and 
equipment, and because project personnel did not seek regular rate 
increases to cover the full cost of project operation.

.A previous OIG audit performed on one of the BIA's largest irrigation 
projects, the Wapato Indian Irrigation Project, No. 95-I-1402, 
September 1995, reached the same conclusion.
    To address the issues noted in these audits, the BIA must 
systematically review and evaluate irrigation assessment rates and 
adjust them, when necessary, to reflect the full costs to operate and 
perform all appropriate maintenance on the irrigation project or 
facility infrastructure to ensure safe and reliable operation. If this 
review and adjustment is not accomplished, a rate deficiency can 
accumulate over time. Rate deficiencies force the BIA to raise 
irrigation assessment rates in larger increments over shorter periods 
of time than would have been otherwise necessary.

The following comments are specific to the Wapato Irrigation Project: 
How does BIA respond to concerns that the operation and maintenance 
charges reflected in the 2010 rates conflict with the Yakama Nation's 
position in pending appeals of these charges?

    The Yakama Nation, which is served by the Wapato Irrigation 
Project, has an administrative appeal regarding the BIA charging the 
irrigation operation and maintenance on trust lands. Because this is a 
legal issue currently being appealed and does not specifically target 
the rate change, it will not be discussed in this notice.

How does the BIA respond to comments regarding the BIA's trust 
responsibility to enhance idle tracts to make them productive?

    As stated in the answer to the preceding question, the BIA has no 
trust obligation to operate and maintain irrigation projects. See, 
e.g., Grey v. United States, 21 Cl. Ct. 285 (1990), aff'd, 935 F.2d 281 
(Fed. Cir. 1991), cert. denied, 502 U.S. 1057 (1992). This means the 
BIA has no obligation to enhance idle tracks of land. However, 
recognizing the potential benefits to projects from such enhancements, 
the updated Irrigation O&M regulations (25 CFR part 171.610) provide 
for an incentive to potential lessees who want to lease project land 
that is not being farmed (idle land). The lessee is eligible to enter 
into an incentive agreement with BIA. Under such an incentive 
agreement, BIA is able to waive operation and maintenance (O&M) fees 
for up to three years while improvements are made to bring lands that 
are currently idle back into production. This feature provides benefits 
to landowners, who can more readily lease their lands; to lessees, who 
experience reduced costs associated with bringing lands back into 
production through reduced or waived O&M assessments; and to the 
projects, which realize a more stable and productive land base.

III. Further Information on this Notice

Where can I get information on the regulatory and legal citations in 
this notice?

    You can contact the appropriate office(s) stated in the tables for 
the irrigation project that serves you, or you can use the Internet 
site for the Government Printing Office at http://www.gpo.gov.

What authorizes you to issue this notice?

    Our authority to issue this notice is vested in the Secretary of 
the Interior by 5 U.S.C. 301 and the Act of August 14, 1914 (38 Stat. 
583; 25 U.S.C. 385). The Secretary has in turn delegated this authority 
to the Assistant Secretary--Indian Affairs under Part 209, Chapter 
8.1A, of the Department of the Interior's Departmental Manual.

Who can I contact for further information?

    The following tables are the regional and project/agency contacts 
for our irrigation facilities.

------------------------------------------------------------------------
           Project Name                    Project/Agency Contacts
------------------------------------------------------------------------
                        Northwest Region Contacts
------------------------------------------------------------------------
Stanley Speaks, Regional Director, Bureau of Indian Affairs, Northwest
 Regional Office, 911 NE. 11th Avenue, Portland, Oregon 97232-4169,
 Telephone: (503) 231-6702.
------------------------------------------------------------------------
Flathead Irrigation Project.......  Chuck Courville, Superintendent,
                                     Flathead Agency Irrigation
                                     Division, P.O. Box 40, Pablo, MT
                                     59855-0040, Telephone: (406) 675-
                                     2700.
Fort Hall Irrigation Project......  Eric J. LaPointe, Superintendent,
                                     Dean Fox, Deputy Superintendent,
                                     Daniel Harelson, Irrigation Project
                                     Engineer, Fort Hall Agency, P.O.
                                     Box 220, Fort Hall, ID 83203-0220,
                                     Telephone: (208) 238-1992.
Wapato Irrigation Project.........  Pierce Harrison, Project
                                     Administrator, Wapato Irrigation
                                     Project, P.O. Box 220, Wapato, WA
                                     98951-0220, Telephone: (509) 877-
                                     3155.
------------------------------------------------------------------------

[[Page 29581]]

 
                     Rocky Mountain Region Contacts
------------------------------------------------------------------------
Ed Parisian, Regional Director, Bureau of Indian Affairs, Rocky Mountain
 Regional Office, 316 North 26th Street, Billings, Montana 59101,
 Telephone: (406) 247-7943.
------------------------------------------------------------------------
Blackfeet Irrigation Project......  Stephen Pollock, Superintendent, Ted
                                     Hall, Irrigation Project Manager,
                                     Box 880, Browning, MT 59417,
                                     Telephones: (406) 338-7544,
                                     Superintendent, (406) 338-7519,
                                     Irrigation Project Manager.
Crow Irrigation Project...........  Judy Gray, Superintendent, Vacant,
                                     Irrigation Project Manager, P.O.
                                     Box 69, Crow Agency, MT 59022,
                                     Telephones: (406) 638-2672,
                                     Superintendent, (406) 638-2863,
                                     Irrigation Project Manager.
Fort Belknap Irrigation Project...  Jim Montes, Acting Superintendent,
                                     Vacant, Irrigation Project Manager,
                                     (Project operations & management
                                     contracted by the Tribes), R.R.1,
                                     Box 980, Harlem, MT 59526,
                                     Telephones: (406) 353-2901,
                                     Superintendent, (406) 353-2905,
                                     Irrigation Project Manager.
Fort Peck Irrigation Project......  Florence White Eagle,
                                     Superintendent, P.O. Box 637,
                                     Poplar, MT 59255, Vacant,
                                     Irrigation Manager, 602 6th Avenue
                                     North, Wolf Point, MT 59201,
                                     Telephones: (406) 768-5312,
                                     Superintendent, (406) 653-1752,
                                     Irrigation Manager.
Wind River Irrigation Project.....  Ed Lone Fight, Superintendent,
                                     Sheridan Nicholas, Irrigation
                                     Project Engineer, P.O. Box 158,
                                     Fort Washakie, WY 82514,
                                     Telephones: (307) 332-7810,
                                     Superintendent, (307) 332-2596,
                                     Irrigation Project Manager.
------------------------------------------------------------------------
                        Southwest Region Contacts
------------------------------------------------------------------------
William T. Walker, Regional Director, Bureau of Indian Affairs,
 Southwest Regional Office, 1001 Indian School Road, Albuquerque, New
 Mexico 87104, Telephone: (505) 563-3100.
------------------------------------------------------------------------
Pine River Irrigation Project.....  John Waconda, Superintendent,
                                     Vacant, Irrigation Engineer, P.O.
                                     Box 315, Ignacio, CO 81137-0315,
                                     Telephones: (970) 563-4511,
                                     Superintendent, (970) 563-9484,
                                     Irrigation Engineer.
------------------------------------------------------------------------
                         Western Region Contacts
------------------------------------------------------------------------
Vacant, Regional Director, Bureau of Indian Affairs, Western Regional
 Office, 2600 N, Central Avenue, 4th Floor Mailroom, Phoenix, Arizona
 85004, Telephone: (602) 379-6600.
------------------------------------------------------------------------
Colorado River Irrigation Project.  Janice Staudte, Superintendent, Ted
                                     Henry, Irrigation Project Manager,
                                     12124 1st Avenue, Parker, AZ 85344,
                                     Telephone: (928) 669-7111.
Duck Valley Irrigation Project....  Joseph McDade, Superintendent, 1555
                                     Shoshone Circle, Elko, NV 89801,
                                     Telephone: (775) 738-5165.
Fort Yuma Irrigation Project......  Marlene Walker, Acting
                                     Superintendent, P.O. Box 11000,
                                     Yuma, AZ 85366, Telephone: (520)
                                     782-1202.
San Carlos Irrigation Project       Bryan Bowker, Project Manager,
 Joint Works.                        Clarence Begay, Irrigation Manager,
                                     P.O. Box 250, Coolidge, AZ 85228,
                                     Telephone: (520) 723-6215.
San Carlos Irrigation Project       Cecilia Martinez, Superintendent,
 Indian Works.                       Joe Revak, Supervisory General
                                     Engineer, Pima Agency, Land
                                     Operations, P.O. Box 8, Sacaton, AZ
                                     85247, Telephone: (520) 562-3326,
                                     Telephone: (520) 562-3372.
Uintah Irrigation Project.........  Daniel Picard, Superintendent, Dale
                                     Thomas, Irrigation Manager, P.O.
                                     Box 130, Fort Duchesne, UT 84026,
                                     Telephone: (435) 722-4300,
                                     Telephone: (435) 722-4341.
Walker River Irrigation Project...  Athena Brown, Superintendent, 311 E.
                                     Washington Street, Carson City, NV
                                     89701, Telephone: (775) 887-3500.
------------------------------------------------------------------------

IV. Administrative Requirements

Consultation and Coordination With Tribal Governments (Executive Order 
13175)

    To fulfill its consultation responsibility to tribes and tribal 
organizations, BIA communicates, coordinates, and consults on a 
continuing basis with these entities on issues related to water 
delivery, water availability, and costs of administration, operation, 
maintenance, and rehabilitation of projects that concern them. This is 
accomplished at the individual irrigation project by project, agency, 
and regional representatives, as appropriate, in accordance with local 
protocol and procedures. This notice is one component of our overall 
coordination and consultation process to provide notice to these 
entities when we adjust irrigation assessment rates.

Actions Concerning Regulations That Significantly Affect Energy Supply, 
Distribution, or Use (Executive Order 13211)

    The rate adjustments will have no adverse effects on energy supply, 
distribution, or use (including a shortfall in supply, price increases, 
and increase use of foreign supplies) as this rate adjustment is 
implemented. This is a notice for rate adjustments at BIA-owned and 
operated irrigation projects, except for the Fort Yuma Irrigation 
Project. The Fort Yuma Irrigation Project is owned and operated by the 
Bureau of Reclamation with a portion serving the Fort Yuma Reservation.

Regulatory Planning and Review (Executive Order 12866)

    These rate adjustments are not a significant regulatory action and 
do not need to be reviewed by the Office of Management and Budget under 
Executive Order 12866.

Regulatory Flexibility Act

    These rate adjustments are not a rule for the purposes of the 
Regulatory Flexibility Act because they establish ``a rule of 
particular applicability relating to rates.'' 5 U.S.C. 601(2).

Unfunded Mandates Reform Act of 1995

    These rate adjustments do not impose an unfunded mandate on State, 
local, or tribal governments in the aggregate, or on the private 
sector, of more than $130 million per year. The rule does not have a 
significant or unique effect on State, local, or tribal governments or 
the private sector. Therefore, the Department of the Interior 
(Department) is not required to prepare a statement containing the 
information required by the Unfunded Mandates Reform Act (2 U.S.C. 1531 
et seq.).

[[Page 29582]]

Takings (Executive Order 12630)

    The Department has determined that these rate adjustments do not 
have significant ``takings'' implications. The rate adjustments do not 
deprive the public, state, or local governments of rights or property.

Federalism (Executive Order 13132)

    The Department has determined that these rate adjustments do not 
have significant Federalism effects because they will not affect the 
States, the relationship between the national government and the 
States, or the distribution of power and responsibilities among various 
levels of government.

Civil Justice Reform (Executive Order 12988)

    In issuing this rule, the Department has taken the necessary steps 
to eliminate drafting errors and ambiguity, minimize potential 
litigation, and provide a clear legal standard for affected conduct, as 
required by section 3 of Executive Order 12988.

Paperwork Reduction Act of 1995

    These rate adjustments do not affect the collections of information 
which have been approved by the Office of Information and Regulatory 
Affairs, Office of Management and Budget, under the Paperwork Reduction 
Act of 1995. The OMB Control Number is 1076-0141 and expires December 
31, 2012.

National Environmental Policy Act

    The Department has determined that these rate adjustments do not 
constitute a major Federal action significantly affecting the quality 
of the human environment and that no detailed statement is required 
under the National Environmental Policy Act of 1969 (42 U.S.C. 4321-
4370(d)).

Information Quality Act

    In developing this notice, we did not conduct or use a study, 
experiment, or survey requiring peer review under the Information 
Quality Act (Pub. L. 106-554).

    Dated: May 17, 2010.
Larry Echo Hawk,
Assistant Secretary--Indian Affairs.
[FR Doc. 2010-12658 Filed 5-25-10; 8:45 am]
BILLING CODE 4310-W7-P