[Federal Register Volume 75, Number 79 (Monday, April 26, 2010)]
[Notices]
[Pages 21678-21679]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2010-9585]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-498 and 50-499; NRC-2010-0162]
STP Nuclear Operating Company South Texas Project, Units 1 and 2
Environmental Assessment and Finding of No Significant Impact
The U.S. Nuclear Regulatory Commission (NRC) is considering
issuance of an exemption, pursuant to Title 10 of the Code of Federal
Regulations (10 CFR), Section 26.9, for Facility Operating Licenses
numbered NPF-76 and NPF-80, issued to STP Nuclear Operating Company
(the licensee), for operation of the South Texas Project (STP), Units 1
and 2, respectively, located in Matagorda County, Texas. In accordance
with 10 CFR 51.21, the NRC prepared an environmental assessment
documenting its finding. The NRC concluded that the proposed action
will have no significant environmental impact.
Environmental Assessment
Identification of the Proposed Action:
The proposed action would consider approval of an exemption for
STP, Units 1 and 2, from some of the requirements of 10 CFR Part 26,
``Fitness for Duty Rule.'' Specifically, the licensee requests approval
of an exemption from the requirements of 10 CFR 26.205(c), ``Work hours
scheduling,'' and (d), ``Work hour controls.''
The licensee states that during declaration of severe weather
conditions such as tropical storm or hurricane force winds, adherence
to all work hour controls requirements could impede the
[[Page 21679]]
licensee's ability to use whatever staff resources may be necessary to
respond to a plant emergency and ensure that the plant reaches and
maintains a safe and secure status.
The exemption would only apply when severe weather conditions
involving tropical storm or hurricane force winds are predicted on site
requiring the sequestering of STP storm crew.
The proposed exemption will allow the licensee not to meet the
requirements of 10 CFR 26.205(c) and (d), from the time that the storm
or hurricane sequestering conditions are met until severe weather exit
conditions are satisfied. The exemption will only apply to individuals
on the storm crew who perform duties identified in 10 CFR 26.4(a)(1)
through (5). When storm crew sequestering exit conditions are met, full
compliance with 10 CFR 26.205(c) and (d) will be required.
The proposed action does not involve any physical changes to the
reactor, fuel, plant structures, support structures, water, or land at
the STP, Units 1 and 2, site.
The proposed action is in accordance with the licensee's
application dated September 21, 2009, as supplemented by letters dated
October 14, 2009, and February 11, 2010.
The Need for the Proposed Action:
Proposed action is needed because the licensee is unable to meet
the requirements of 10 CFR 26.205 (c) and (d) during declarations of
severe weather conditions that could result due to prevailing tropical
storm or hurricane force winds impacting the facility.
Compliance with work hour control requirements would impede the
licensee's ability to use whatever staff resources may be necessary to
respond to a plant emergency and ensure that the plant reaches and
maintains a safe and secure status.
Environmental Impacts of the Proposed Action:
The NRC staff has completed its environmental assessment of the
proposed exemption. The NRC staff has concluded that the proposed
exemption from the implementation of the requirements of 10 CFR
26.205(c) and (d) during declaration of severe weather conditions,
would not significantly affect plant safety and would not have a
significant adverse effect on the probability of occurrence of an
accident.
The proposed action would not result in any increased radiological
hazards beyond those previously evaluated by the NRC staff in NUREG-
0781, ``Safety Evaluation Report Related to Operation of South Texas
Project, Units 1 and 2.'' There will be no change to radioactive
effluents that affect radiation exposures to plant workers and members
of the public. Therefore, no changes in or different types of
radiological impacts are expected as a result of the proposed
exemption.
The proposed action does not result in changes to land use or water
use, or result in changes to the quality or quantity of non-
radiological effluents. No changes to the National Pollution Discharge
Elimination System permit are needed. No effects on the aquatic or
terrestrial habitat in the vicinity of the plant, or to threatened,
endangered, or protected species under the Endangered Species Act, or
impacts to essential fish habitat covered by the Magnuson-Steven's Act
are expected. There are no impacts to the air or ambient air quality.
There are no impacts to historical and cultural resources. There would
be no impact to socioeconomic resources. Therefore, no changes to or
different types of non-radiological environmental impacts are expected
as a result of the proposed exemption.
Accordingly, the NRC staff concludes that there are no significant
environmental impacts associated with the proposed action.
The licensee currently maintains a Hurricane Plan which provides
directions for activation of the storm crew. The storm crew is
activated upon the directions of Emergency Operations Facility
Director. The Plan provides specific entry conditions for the start of
the emergency and specific conditions that will terminate the
emergency. The licensee states that the impact of the exemption on
personnel manning during the implementation of the site Hurricane Plan
will be similar to an Emergency Plan impact. Although the proposed
exemption would allow the licensee not to meet work hour controls
during storm crew activation, sufficient numbers of management and
supervision will be available during storm crew manning and activation
to ensure that public health and safety is adequately protected.
The NRC staff's safety evaluation will be provided as part of the
letter to the licensee approving the exemption to the regulation, if
granted.
Environmental Impacts of the Alternatives to the Proposed Action:
As an alternative to the proposed action, the NRC staff considered
denial of the proposed actions (i.e., the ``no-action'' alternative).
Denial of the exemption request would result in no change in current
environmental impacts. If the proposed action were denied, the licensee
would have to comply with the fatigue rules in 10 CFR 26.205(c) and
(d). This would cause unnecessary burden on the licensee, without a
significant benefit in environmental impacts. The environmental impacts
of the proposed exemption and the ``no-action'' alternative are
similar.
Alternative Use of Resources:
The action does not involve the use of any different resources than
those considered in the Final Environmental Statement for the STP,
Units 1 and 2, NUREG-1172, dated August 1986.
Agencies and Persons Consulted:
In accordance with its stated policy, on April 13, 2010, the NRC
staff consulted with the Texas State official, Ms. Alice Rogers of the
Texas State Department of Health, regarding the environmental impact of
the proposed action. The Texas State official had no comments.
Finding of No Significant Impact
On the basis of the environmental assessment, the NRC concludes
that the proposed action will not have a significant effect on the
quality of the human environment. Accordingly, the NRC has determined
not to prepare an environmental impact statement for the proposed
action.
For further details with respect to the proposed action, see the
licensee's letter dated September 21, 2009, as supplemented by letters
dated October 14, 2009, and February 11, 2010, available in the
Agencywide Documents Access and Management System (ADAMS) Accession
Nos. ML092720178, ML092930172, and ML100490048, respectively. Documents
may be examined, and/or copied for a fee, at the NRC's Public Document
Room (PDR), located at One White Flint North, Public File Area O1 F21,
11555 Rockville Pike (first floor), Rockville, Maryland. Publicly
available records will be accessible electronically from the ADAMS
Public Electronic Reading Room on the Internet at the NRC Web site,
http://www.nrc.gov/reading-rm/adams.html. Persons who do not have
access to ADAMS or who encounter problems in accessing the documents
located in ADAMS should contact the NRC PDR Reference staff by
telephone at 1-800-397-4209 or 301-415-4737, or send an e-mail to
[email protected].
Dated at Rockville, Maryland, this 19th day of April 2010.
For The Nuclear Regulatory Commission.
Mohan C. Thadani,
Senior Project Manager, Plant Licensing Branch IV, Division of
Operating Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2010-9585 Filed 4-23-10; 8:45 am]