[Federal Register Volume 75, Number 34 (Monday, February 22, 2010)]
[Notices]
[Pages 7628-7631]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: 2010-3370]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-341; NRC-2010-0051]
Davis-Besse Nuclear Power Station; Notice of Consideration of
Issuance of Amendment to Facility Operating License, Proposed No
Significant Hazards Consideration Determination, and Opportunity for a
Hearing
The U.S. Nuclear Regulatory Commission (the Commission) is
considering issuance of an amendment to Facility Operating License No.
NPF-3 issued to FirstEnergy Nuclear Operating Company (the licensee)
for operation of the Davis-Besse Nuclear Power Station, Unit No. 1
(DBNPS) located in Oak Harbor, Ohio.
The proposed amendment would support application of optimized weld
overlays or full structural weld overlays. Applying these weld overlays
on the reactor coolant pump suction and discharge nozzle dissimilar
metal welds requires an update to the DBNPS leak-before-break (LBB)
evaluation.
Before issuance of the proposed license amendment, the Commission
will have made findings required by the Atomic Energy Act of 1954, as
amended (the Act), and the Commission's regulations.
The Commission has made a proposed determination that the amendment
request involves no significant hazards consideration. Under the
Commission's regulations in Title 10 of the Code of Federal Regulations
(10 CFR), Sec. 50.92, this means that operation of the facility in
accordance with the proposed amendment would not (1)
[[Page 7629]]
involve a significant increase in the probability or consequences of an
accident previously evaluated; or (2) create the possibility of a new
or different kind of accident from any accident previously evaluated;
or (3) involve a significant reduction in a margin of safety. As
required by 10 CFR 50.91(a), the licensee has provided its analysis of
the issue of no significant hazards consideration, which is presented
below:
1. Does the proposed amendment involve a significant increase in
the probability or consequences of an accident previously evaluated?
Response: No.
The applicable accident is a Large Break Loss of Coolant
Accident (LBLOCA). Since the application of [optimized weld
overlays] OWOLs or [full structural weld overlays] FSWOLs will
enhance the integrity of welds and the reactor coolant system, the
probability of a previously evaluated accident is not increased. The
consequences of a LBLOCA have been previously evaluated and found to
be acceptable. Application of OWOLs or FSWOLs to the existing welds
will cause no change to the dose analysis associated with a LBLOCA.
Therefore, the leak-before-break (LBB) evaluation update does
not involve a significant increase in the probability or
consequences of an accident previously evaluated.
2. Does the proposed amendment create the possibility of a new
or different kind of accident from any accident previously
evaluated?
Response: No.
The LBB evaluation update will allow application of OWOLs or
FSWOLs to mitigate potential primary water stress corrosion cracking
(PWSCC) of the existing welds. These welds provide a primary
pressure boundary function. This request does not change the
function of the welds, or the way the plant is operated; it supports
the application of OWOLs or FSWOLs that will enhance the ability of
the welds to perform the pressure boundary function.
Therefore, the proposed LBB update does not create the
possibility of a new or different kind of accident from any-accident
previously evaluated.
3. Does the proposed amendment involve a significant reduction
in a margin of safety?
Response: No.
Margin of safety is related to the ability of the fission
product barriers to perform their design functions during and
following accident conditions. These barriers include the fuel
cladding, the reactor coolant system, and the containment. This
request does not involve a change to the fuel cladding or the
containment. This amendment request updates the LBB evaluation to
account for the application of OWOLs or FSWOLs to the existing
reactor coolant pump suction and discharge nozzle dissimilar metal
welds for the Davis-Besse Nuclear Power Station. The effect of
applying a weld overlay repair has been evaluated with respect to
the LBB evaluation at these locations. This evaluation addresses
mitigation of PWSCC in these welds and allows the application of a
PWSCC resistant weld overlay that has the added benefit of producing
compressive stresses on the inner portion of the existing welds.
Acceptable residual stresses for purposes of satisfying this
requirement are those which, following the application of OWOLs or
FSWOLs with Alloy 52/52M weld metal, provide a PWSCC resistant
barrier and also result in reduced stresses on the inner portion of
the welds. Acceptable residual stresses are those which, after
application of the weld overlay, are substantially reduced on the
inner portion of the nozzle susceptible material at operating
temperatures, pressures, and loads. In addition, the compressive
stresses which exist in the interior of the dissimilar metal weld
are increased to the point where the PWSCC of an existing flaw may
be arrested. The crack growth analyses resulting from these through-
thickness residual stresses ensure that any PWSCC flaws would be
acceptable within the inspection interval of the dissimilar metal
weld. The effect of the adverse morphology on leakage due to PWSCC
cracking was also evaluated. The effect of the application of the
weld overlay is to increase the critical flaw size, resulting in
additional margin between the critical flawsize and the leakage flaw
size. Although the longer flow path and considerations of crack
morphology for the Alloy 82/182 weld location reduces leakage
somewhat for a given through-wall flaw, the larger critical flaw
size following application of the weld overlay allows for increased
leakage margin. The evaluation described above demonstrates that
these welds will perform as originally intended and that the adverse
effects of PWSCC will be mitigated.
Therefore, the proposed LBB update does not involve a
significant reduction in a margin of safety. Based on the above,
FENOC concludes that the proposed amendment does not involve a
significant hazards consideration under the standards set forth in
10 CFR 50.92(c), and, accordingly, a finding of ``no significant
hazards consideration'' is justified.
The NRC staff has reviewed the licensee's analysis and, based on
this review, it appears that the three standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff proposes to determine that the
amendment request involves no significant hazards consideration.
The Commission is seeking public comments on this proposed
determination. Any comments received within 30 days after the date of
publication of this notice will be considered in making any final
determination.
Normally, the Commission will not issue the amendment until the
expiration of 60 days after the date of publication of this notice. The
Commission may issue the license amendment before expiration of the 60-
day period provided that its final determination is that the amendment
involves no significant hazards consideration. In addition, the
Commission may issue the amendment prior to the expiration of the 30-
day comment period should circumstances change during the 30-day
comment period such that failure to act in a timely way would result,
for example, in derating or shutdown of the facility. Should the
Commission take action prior to the expiration of either the comment
period or the notice period, it will publish in the Federal Register a
notice of issuance. Should the Commission make a final No Significant
Hazards Consideration Determination, any hearing will take place after
issuance. The Commission expects that the need to take this action will
occur very infrequently.
Written comments may be submitted by mail to the Chief, Rulemaking
and Directives Branch (RDB), TWB-05-B01M, Division of Administrative
Services, Office of Administration, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, and should cite the publication date and
page number of this Federal Register notice. Written comments may also
be faxed to the RDB at 301-492-3446. Documents may be examined, and/or
copied for a fee, at the NRC's Public Document Room (PDR), located at
One White Flint North, Public File Area O1 F21, 11555 Rockville Pike
(first floor), Rockville, Maryland.
Within 60 days after the date of publication of this notice, any
person(s) whose interest may be affected by this action may file a
request for a hearing and a petition to intervene with respect to
issuance of the amendment to the subject facility operating license.
Requests for a hearing and a petition for leave to intervene shall be
filed in accordance with the Commission's ``Rules of Practice for
Domestic Licensing Proceedings'' in 10 CFR Part 2. Interested person(s)
should consult a current copy of 10 CFR 2.309, which is available at
the Commission's PDR, located at One White Flint North, Public File
Area O1F21, 11555 Rockville Pike (first floor), Rockville, Maryland.
Publicly available records will be accessible from the Agencywide
Documents Access and Management System's (ADAMS) Public Electronic
Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/doc-collections/cfr/. If a request for a hearing or petition
for leave to intervene is filed by the above date, the Commission or a
presiding officer designated by the Commission or by the Chief
Administrative Judge of the Atomic Safety and Licensing Board Panel,
will rule on the request and/or
[[Page 7630]]
petition; and the Secretary or the Chief Administrative Judge of the
Atomic Safety and Licensing Board will issue a notice of a hearing or
an appropriate order.
As required by 10 CFR 2.309, a petition for leave to intervene
shall set forth with particularity the interest of the petitioner in
the proceeding, and how that interest may be affected by the results of
the proceeding. The petition should specifically explain the reasons
why intervention should be permitted with particular reference to the
following general requirements: (1) The name, address and telephone
number of the requestor or petitioner; (2) the nature of the
requestor's/petitioner's right under the Act to be made a party to the
proceeding; (3) the nature and extent of the requestor's/petitioner's
property, financial, or other interest in the proceeding; and (4) the
possible effect of any decision or order which may be entered in the
proceeding on the requestor's/petitioner's interest. The petition must
also identify the specific contentions which the requestor/petitioner
seeks to have litigated at the proceeding.
Each contention must consist of a specific statement of the issue
of law or fact to be raised or controverted. In addition, the
requestor/petitioner shall provide a brief explanation of the bases for
the contention and a concise statement of the alleged facts or expert
opinion which support the contention and on which the petitioner
intends to rely in proving the contention at the hearing. The
requestor/petitioner must also provide references to those specific
sources and documents of which the petitioner is aware and on which the
petitioner intends to rely to establish those facts or expert opinion.
The petition must include sufficient information to show that a genuine
dispute exists with the applicant on a material issue of law or fact.
Contentions shall be limited to matters within the scope of the
amendment under consideration. The contention must be one which, if
proven, would entitle the petitioner to relief. A requestor/petitioner
who fails to satisfy these requirements with respect to at least one
contention will not be permitted to participate as a party.
Those permitted to intervene become parties to the proceeding,
subject to any limitations in the order granting leave to intervene,
and have the opportunity to participate fully in the conduct of the
hearing.
If a hearing is requested, the Commission will make a final
determination on the issue of no significant hazards consideration. The
final determination will serve to decide when the hearing is held. If
the final determination is that the amendment request involves no
significant hazards consideration, the Commission may issue the
amendment and make it immediately effective, notwithstanding the
request for a hearing. Any hearing held would take place after issuance
of the amendment. If the final determination is that the amendment
request involves a significant hazards consideration, any hearing held
would take place before the issuance of any amendment.
All documents filed in NRC adjudicatory proceedings, including a
request for hearing, a petition for leave to intervene, any motion or
other document filed in the proceeding prior to the submission of a
request for hearing or petition to intervene, and documents filed by
interested governmental entities participating under 10 CFR 2.315(c),
must be filed in accordance with the NRC E-Filing rule (72 FR 49139,
August 28, 2007). The E-Filing process requires participants to submit
and serve all adjudicatory documents over the internet, or in some
cases to mail copies on electronic storage media. Participants may not
submit paper copies of their filings unless they seek an exemption in
accordance with the procedures described below.
To comply with the procedural requirements of E-Filing, at least
ten (10) days prior to the filing deadline, the participant should
contact the Office of the Secretary by e-mail at
[email protected], or by telephone at (301) 415-1677, to request
(1) a digital ID certificate, which allows the participant (or its
counsel or representative) to digitally sign documents and access the
E-Submittal server for any proceeding in which it is participating; and
(2) advise the Secretary that the participant will be submitting a
request or petition for hearing (even in instances in which the
participant, or its counsel or representative, already holds an NRC-
issued digital ID certificate). Based upon this information, the
Secretary will establish an electronic docket for the hearing in this
proceeding if the Secretary has not already established an electronic
docket.
Information about applying for a digital ID certificate is
available on NRC's public Web site at http://www.nrc.gov/site-help/e-submittals/apply-certificates.html. System requirements for accessing
the E-Submittal server are detailed in NRC's ``Guidance for Electronic
Submission,'' which is available on the agency's public Web site at
http://www.nrc.gov/site-help/e-submittals.html. Participants may
attempt to use other software not listed on the Web site, but should
note that the NRC's E-Filing system does not support unlisted software,
and the NRC Meta System Help Desk will not be able to offer assistance
in using unlisted software.
If a participant is electronically submitting a document to the NRC
in accordance with the E-Filing rule, the participant must file the
document using the NRC's online, Web-based submission form. In order to
serve documents through EIE, users will be required to install a Web
browser plug-in from the NRC Web site. Further information on the Web-
based submission form, including the installation of the Web browser
plug-in, is available on the NRC's public Web site at http://www.nrc.gov/site-help/e-submittals.html.
Once a participant has obtained a digital ID certificate and a
docket has been created, the participant can then submit a request for
hearing or petition for leave to intervene. Submissions should be in
Portable Document Format (PDF) in accordance with NRC guidance
available on the NRC public Web site at http://www.nrc.gov/site-help/e-submittals.html. A filing is considered complete at the time the
documents are submitted through the NRC's E-Filing system. To be
timely, an electronic filing must be submitted to the E-Filing system
no later than 11:59 p.m. Eastern Time on the due date. Upon receipt of
a transmission, the E-Filing system time-stamps the document and sends
the submitter an e-mail notice confirming receipt of the document. The
E-Filing system also distributes an e-mail notice that provides access
to the document to the NRC Office of the General Counsel and any others
who have advised the Office of the Secretary that they wish to
participate in the proceeding, so that the filer need not serve the
documents on those participants separately. Therefore, applicants and
other participants (or their counsel or representative) must apply for
and receive a digital ID certificate before a hearing request/petition
to intervene is filed so that they can obtain access to the document
via the E-Filing system.
A person filing electronically using the agency's adjudicatory E-
Filing system may seek assistance by contacting the NRC Meta System
Help Desk through the ``Contact Us'' link located on the NRC Web site
at http://www.nrc.gov/site-help/e-submittals.html, by e-mail at
[email protected], or by a toll-
[[Page 7631]]
free call at (866) 672-7640. The NRC Meta System Help Desk is available
between 8 a.m. and 8 p.m., Eastern Time, Monday through Friday,
excluding government holidays.
Participants who believe that they have a good cause for not
submitting documents electronically must file an exemption request, in
accordance with 10 CFR 2.302(g), with their initial paper filing
requesting authorization to continue to submit documents in paper
format. Such filings must be submitted by: (1) First class mail
addressed to the Office of the Secretary of the Commission, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, Attention:
Rulemaking and Adjudications Staff; or (2) courier, express mail, or
expedited delivery service to the Office of the Secretary, Sixteenth
Floor, One White Flint North, 11555 Rockville Pike, Rockville, Maryland
20852, Attention: Rulemaking and Adjudications Staff. Participants
filing a document in this manner are responsible for serving the
document on all other participants. Filing is considered complete by
first-class mail as of the time of deposit in the mail, or by courier,
express mail, or expedited delivery service upon depositing the
document with the provider of the service. A presiding officer, having
granted an exemption request from using E-Filing, may require a
participant or party to use E-Filing if the presiding officer
subsequently determines that the reason for granting the exemption from
use of E-Filing no longer exists.
Documents submitted in adjudicatory proceedings will appear in
NRC's electronic hearing docket which is available to the public at
http://ehd.nrc.gov/EHD_Proceeding/home.asp, unless excluded pursuant
to an order of the Commission, or the presiding officer. Participants
are requested not to include personal privacy information, such as
social security numbers, home addresses, or home phone numbers in their
filings, unless an NRC regulation or other law requires submission of
such information. With respect to copyrighted works, except for limited
excerpts that serve the purpose of the adjudicatory filings and would
constitute a Fair Use application, participants are requested not to
include copyrighted materials in their submission.
Petitions for leave to intervene must be filed no later than 60
days from the date of publication of this notice. Non-timely filings
will not be entertained absent a determination by the presiding officer
that the petition or request should be granted or the contentions
should be admitted, based on a balancing of the factors specified in 10
CFR 2.309(c)(1)(i)-(viii).
For further details with respect to this license amendment
application, see the application for amendment dated [date], which is
available for public inspection at the Commission's PDR, located at One
White Flint North, File Public Area O1 F21, 11555 Rockville Pike (first
floor), Rockville, Maryland. Publicly available records will be
accessible electronically from the Agencywide Documents Access and
Management System's (ADAMS) Public Electronic Reading Room on the
Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html.
Persons who do not have access to ADAMS or who encounter problems in
accessing the documents located in ADAMS, should contact the NRC PDR
Reference staff by telephone at 1-800-397-4209, 301-415-4737, or by e-
mail to [email protected].
Attorney for licensee: David W. Jenkins, Attorney, FirstEnergy
Corporation, Mail Stop A-GO-15, 76 South Main Street, Akron, OH 44308.
Dated at Rockville, Maryland, this 16th day of February 2010.
For the Nuclear Regulatory Commission.
Michael Mahoney,
Project Manager, Plant Licensing Branch III-2, Division of Operating
Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2010-3370 Filed 2-19-10; 8:45 am]