NUCLEAR REGULATORY COMMISSION
[Docket No. 030-32023; License No. 42-27055-01; EA-08-261; NRC-2009-
0101]
In the Matter of Schlumberger Technology Corporation, Sugar Land,
TX; Confirmatory Order Modifying License; Effective Immediately
I
Schlumberger Technology Corporation (Schlumberger or Licensee) is
the holder of Materials License No. 42-27055-01 issued by the Nuclear
Regulatory Commission (NRC or Commission) pursuant to 10 CFR Part 30 on
November 29, 1989, last amended on May 1, 2006, and due to expire on
December 31, 2015. The license authorizes Schlumberger to possess and
use sealed sources for use in conducting density measurements in
accordance with conditions specified therein. The license authorizes
use at specified field stations located in the States of Alaska,
Virginia, West Virginia, and Wyoming. The license also authorizes use
at temporary job sites of the licensee anywhere in the United States
where the Commission maintains jurisdiction for regulating the use of
licensed material.
II
In accordance with NRC protocols, on October 4, 2007, Schlumberger
timely reported the loss of a fluid density gauge containing licensed
material from its Rock Springs, Wyoming, facility. After identifying
and reporting the missing gauge, Schlumberger took extensive actions in
an attempt to find the gauge and conducted a thorough investigation
into the circumstances surrounding the lost gauge. The gauge was not
located. Schlumberger timely filed its written report pursuant to 10
CFR 20.2201 on November 15, 2007.
On January 29, 2008, the NRC conducted an inspection to review the
circumstances related to Schlumberger's October 4, 2007, report of a
lost fluid density gauge containing licensed material. Following that,
on March 3, 2008, the NRC Office of Investigations (OI) began an
investigation (OI Case No. 4-2008-031) of Schlumberger Technology
Corporation. The investigation was conducted, in part, to determine if
a Radiation Safety Officer (RSO) employed by Schlumberger at the Rock
Springs, Wyoming, field station willfully falsified inventory
documents. Based on the results of the inspection and investigation,
the NRC determined that two apparent violations of NRC requirements
occurred. The apparent violations involved failures to maintain
required records complete and accurate as required by 10 CFR 30.9, and
to maintain control over licensed material as required by 10 CFR
20.1802. The NRC also was concerned that the apparent failure to
maintain required records complete and accurate as required by 10 CFR
30.9 might have resulted from deliberate misconduct on the part of the
RSO at Schlumberger's Rock Springs, Wyoming, field station.
By letter dated December 1, 2008, the NRC transmitted the results
of the inspection and investigation to Schlumberger Technology
Corporation. In the December 1, 2008, letter, the NRC offered
Schlumberger the opportunity to respond to the apparent violations,
request a predecisional enforcement conference, or request Alternative
Dispute Resolution (ADR) with the NRC in an attempt to resolve issues
associated with this matter. In response, on December 5, 2008,
Schlumberger requested ADR to resolve this matter with the NRC.
On January 22, 2009, the NRC and Schlumberger Technology
Corporation met in an ADR session mediated by a professional mediator,
arranged through Cornell University's Institute on Conflict Resolution.
ADR is a process in which a neutral mediator, with no decision-making
authority, assists the parties in reaching an agreement on resolving
any differences regarding the dispute. This confirmatory order is
issued pursuant to the agreement reached during the ADR process.
III
The January 22, 2009, ADR session between the NRC and Schlumberger
was held in Arlington, Texas, in the NRC Region IV offices. During that
ADR session, an Agreement in Principle was reached. The elements of the
agreement consisted of the following:
[[Page 9834]]
1. The NRC acknowledges that Schlumberger identified a missing
gauge and reported it to the NRC, and in addition, the NRC acknowledges
that Schlumberger took extensive actions in an attempt to find the
gauge and conducted a thorough investigation into the circumstances
surrounding the lost gauge. However, the gauge was not found.
2. Within 180 days of the date of this order, Schlumberger will
develop and implement a program that requires well site supervisors to
ensure licensed material is accounted for and secured at temporary job
sites.
3. Within 180 days of the date of this order, Schlumberger will
develop and implement a program that requires line managers to review
security and accountability of licensed material assigned to their
operating locations (base and temporary job sites).
4. Schlumberger's corporate radiation safety staff will conduct
annual radiation safety audits at the Rock Springs, Wyoming, field
station through calendar year 2010. This shall include audits of
temporary job sites that will include, but not be limited to,
compliance with security and transportation regulations associated with
licensed radioactive material.
5. Within 180 days of the date of this order, Schlumberger will
develop and implement a required annual training program that describes
the requirements in 10 CFR 30.9 and 10 CFR 30.10 to employees using
licensed material. This training is to include the potential
consequences individuals may experience for violations of 10 CFR 30.10.
This training will be included in Schlumberger's initial training
program.
6. Within 90 days of the date of this order, Schlumberger will
submit a license amendment request, for Materials License No. 42-27055-
01, to incorporate the changes to its inventory procedure, to include
the photographic inventory process.
7. The NRC agrees not to pursue any further enforcement action
against Schlumberger in connection with the NRC's December 1, 2008,
Inspection Report 030-32023/08-001 issued to Schlumberger and will not
count this matter as previous enforcement for the purposes of assessing
potential future enforcement action civil penalty assessments in
accordance with Section VI.C of the Enforcement Policy. The NRC,
however, will evaluate Schlumberger's compliance with this confirmatory
order; and consider enforcement action for any violations identified,
as appropriate.
8. In consideration of the extensive actions taken and the
additional actions to be taken by Schlumberger, the NRC will issue a
civil monetary penalty only in the base amount of $3250. Schlumberger
will pay the civil penalty within 30 days of the effective date of this
order.
9. The NRC acknowledges the extensive actions taken by
Schlumberger, which include:
In 2005, Schlumberger started a program entitled, ``U.S.
Compliance Audits,'' to conduct audits every 3 years of each field
station by a corporate team of experts. These audits include temporary
job sites.
Schlumberger's local site personnel conduct annual self-
assessments of various programs, including the radiation safety
program.
There is a pre-existing Schlumberger code of ethics which
includes a tiered approach on discipline. Management involvement is
included in the process. Employees are given mechanisms to identify and
report perceived non-conformances.
Photographic inventories of licensed material are
conducted at least annually. Schlumberger's business system generates a
random, 6-digit number on a monthly basis that must be in the
photograph to ensure the inventory occurs in a given month.
Confirmation inventories of licensed radioactive material
are conducted every 3 months.
Third-party leak test analysis results are provided to the
corporate radiation safety office for review.
Training has been provided to Schlumberger's U.S.
employees, who work with licensed materials, on the legal ramifications
of willful failures to follow NRC regulations.
Training has been provided to Schlumberger's Rock Springs,
Wyoming, personnel on security for transport and shipping requirements.
This training was conducted in December 2007 and January 2008.
Training has been provided to Schlumberger's U.S.
employees on radiation safety and control of licensed material. This
training was conducted during the first quarter of 2008.
World-wide training on security and control of gauges and
inventory controls (photographic inventory) was conducted.
A Quality Health Safety and Environment alert was issued
within the company describing the circumstances surrounding the event
related to Schlumberger's October 4, 2007, report of a lost fluid
density gauge, and discussing the importance of the security of
licensed material. This alert went out to site management located in
the United States and Canada.
Procedural changes were made on how and where licensed
materials are stored at Schlumberger's Rock Springs, Wyoming, field
station. An enhanced security system is now in place at Rock Springs,
Wyoming.
It was noted in the agreement that the NRC concluded that two
violations of NRC requirements occurred. The violations involved: (1) A
failure to maintain control over licensed material occurred, which
constitutes a violation of 10 CFR 20.1802, and (2) a site RSO at
Schlumberger's field station located at Rock Springs, Wyoming,
deliberately failed to provide complete and accurate information on the
records documenting physical inventories, which constitutes a violation
of 10 CFR 30.9. The NRC acknowledges that Schlumberger does not concede
that any violations occurred.
On February 23, 2009, the Licensee consented to issuing this Order
with the commitments, as described in Section V below. The Licensee
further agreed that this Order is to be effective upon issuance and
that it has waived its right to a hearing.
IV
Since the licensee has agreed to take additional actions to address
NRC concerns, as set forth in Item III above, the NRC has concluded
that its concerns can be resolved through issuance of this Order.
I find that the Licensee's commitments as set forth in Section V
are acceptable and necessary and conclude that with these commitments
the public health and safety are reasonably assured. In view of the
foregoing, I have determined that public health and safety require that
the Licensee's commitments be confirmed by this Order. Based on the
above and the Licensee's consent, this Order is immediately effective
upon issuance.
Accordingly, pursuant to Sections 81, 161b, 161i, 161o, 182 and 186
of the Atomic Energy Act of 1954, as amended, and the Commission's
regulations in 10 CFR 2.202 and 10 CFR Parts 20 and 30 it is hereby
ordered, effective immediately, that License No. 42-27055-01 is
modified as follows:
1. Within 180 days of the effective date of this order,
Schlumberger will develop and implement a program that requires well
site supervisors to ensure licensed material is accounted for and
secured at temporary job sites.
2. Within 180 days of the effective date of this order,
Schlumberger will develop and implement a program that requires line
managers to review security and accountability of licensed
[[Page 9835]]
material assigned to their operating locations (base and temporary job
sites).
3. Schlumberger's corporate radiation safety staff will conduct
annual radiation safety audits at the Rock Springs, Wyoming, field
station through calendar year 2010. This shall include audits of
temporary job sites that will include, but not be limited to,
compliance with security and transportation regulations associated with
licensed radioactive material.
4. Within 180 days of the effective date of this order,
Schlumberger will develop and implement a required annual training
program that describes the requirements in 10 CFR 30.9 and 10 CFR 30.10
to employees using licensed material. This training is to include the
potential consequences individuals may experience for violations of 10
CFR 30.10. This training will be included in Schlumberger's initial
training program.
5. Within 90 days of the effective date of this order, Schlumberger
will submit a license amendment request, for Materials License No. 42-
27055-01, to incorporate the changes to its inventory procedure, to
include the photographic inventory process.
6. Within 30 days of the effective date of this order, Schlumberger
Technology Corporation must pay the civil penalty of $3,250 in
accordance with NUREG/BR-0254 and submit to the Director, Office of
Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555,
a statement indicating when and by what method payment was made.
7. Schlumberger shall continue the following actions:
``U.S. Compliance Audits'' shall be conducted every 3
years at each field station by a corporate team of experts. These
audits will include temporary job sites.
Annual self-assessments shall be conducted by site
personnel. These self-assessments include the radiation safety program.
Schlumberger will maintain its pre-existing code of
ethics, which includes a tiered approach on discipline.
Confirmation inventories of licensed radioactive material
shall be conducted every 3 months.
Third-party leak test analysis results shall be provided
to the corporate radiation safety office for review.
The enhanced security system shall remain in place at
Schlumberger's Rock Springs, Wyoming, field station, provided that
licensed material is used or stored therein.
The license, which is the subject of this order, is modified in
accordance with the requirements of the order. As such, in the event of
the transfer of Materials License No. 42-27055-01 held by Schlumberger
Technology Corporation, by the virtue of the sale (of the facility or
the license holder), merger, bankruptcy, agreement or otherwise, the
requirements of this confirmatory order shall survive any such transfer
and shall be binding on the new license holder.
The Regional Administrator, NRC Region IV, may, in writing, relax
or rescind any of the above conditions upon demonstration by the
Licensee of good cause.
VI
Any person adversely affected by this Confirmatory Order, other
than the Licensee, may request a hearing within 20 days of its
issuance. Where good cause is shown, consideration will be given to
extending the time to request a hearing. A request for extension of
time must be directed to the Director, Office of Enforcement, U.S.
Nuclear Regulatory Commission, Washington, DC 20555-0001, and include a
statement of good cause for the extension.
A request for a hearing must be filed in accordance with the NRC E-
Filing rule, which the NRC promulgated in August 2007, 72 FR 49,139
(Aug. 28, 2007). The E-Filing process requires participants to submit
and serve documents over the Internet or, in some cases, to mail copies
on electronic optical storage media. Participants may not submit paper
copies of their filings unless they seek a waiver in accordance with
the procedures described below.
To comply with the procedural requirements associated with E-
Filing, at least five (5) days prior to the filing deadline the
requestor must contact the Office of the Secretary by e-mail at
[email protected], or by calling (301) 415-1677, to request (1) a
digital ID certificate, which allows the participant (or its counsel or
representative) to digitally sign documents and access the E-Submittal
server for any NRC proceeding in which it is participating; and/or (2)
creation of an electronic docket for the proceeding (even in instances
when the requestor (or its counsel or representative) already holds an
NRC-issued digital ID certificate). Each requestor will need to
download the Workplace Forms Viewer \TM\ to access the Electronic
Information Exchange (EIE), a component of the E-Filing system. The
Workplace Forms Viewer is free and is available at http://www.nrc.gov/site-help/e-submittals/install-viewer.html. Information about applying
for a digital ID certificate also is available on NRC's public Web site
at http://www. nrc.gov/ site-help/e-submittals/ apply-
certificates.html.
Once a requestor has obtained a digital ID certificate, had a
docket created, and downloaded the EIE viewer, it can then submit a
request for a hearing through EIE. Submissions should be in Portable
Document Format (PDF) in accordance with NRC guidance available on the
NRC public Web site at http://www.nrc.gov/site-help/e-submittals.html.
A filing is considered complete at the time the filer submits its
document through EIE. To be timely, electronic filings must be
submitted to the EIE system no later than 11:59 p.m. Eastern Time on
the due date. Upon receipt of a transmission, the E-Filing system time-
stamps the document and sends the submitter an e-mail notice confirming
receipt of the document. The EIE system also distributes an e-mail
notice that provides access to the document to the NRC Office of the
General Counsel and any others who have advised the Office of the
Secretary that they wish to participate in the proceeding, so that the
filer need not serve the document on those participants separately.
Therefore, any others who wish to participate in the proceeding (or
their counsel or representative) must apply for and receive a digital
ID certificate before a hearing request is filed so that they may
obtain access to the document via the E-Filing system.
A person filing electronically may seek assistance through the
Contact Us link located on the NRC Web site at http://www.nrc.gov/site-help/e-submittals.html or by calling the NRC technical help line, which
is available between 8:30 a.m. and 4:15 p.m., Eastern Time, Monday
through Friday. The help line number is (800) 397-4209 or locally,
(301) 415-4737.
Participants who believe that they have good cause for not
submitting documents electronically must file a motion, in accordance
with 10 CFR 2.302(g), with their initial paper filing requesting
authorization to continue to submit documents in paper format. Such
filings must be submitted by (1) first class mail addressed to the
Office of the Secretary of the Commission, U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001, Attention: Rulemaking and
Adjudications Staff; or (2) courier, express mail, or expedited
delivery service to the Office of the Secretary, Sixteenth Floor, One
White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852,
Attention: Rulemaking and Adjudications Staff. Participants filing a
document in this manner are responsible for serving the
[[Page 9836]]
document on all other participants. Filing is considered complete by
first-class mail as of the time of deposit in the mail, or by courier,
express mail, or expedited delivery service upon depositing the
document with the provider of the service.
Documents submitted in adjudicatory proceedings will appear in
NRC's electronic hearing docket, which is available to the public at
http://ehd.nrc.gov/EHD_Proceeding/home.asp, unless excluded pursuant
to an order of the Commission, an Atomic Safety and Licensing Board, or
a Presiding Officer. Participants are requested not to include personal
privacy information, such as social security numbers, home addresses,
or home phone numbers in their filings. With respect to copyrighted
works, except for limited excerpts that serve the purpose of the
adjudicatory filings and would constitute a Fair Use application,
Participants are requested not to include copyrighted materials in
their works.
If a person other than Schlumberger Technology Corporation requests
a hearing, that person shall set forth with particularity the manner in
which his interest is adversely affected by this Order and shall
address the criteria set forth in 10 CFR 2.309(d) and (f).
If the hearing is requested by a person whose interest is adversely
affected, the Commission will issue an Order designating the time and
place of any hearing. If a hearing is held, the issue to be considered
at such hearing shall be whether this Confirmatory Order should be
sustained. In the absence of any request for hearing, or written
approval of an extension of time in which to request a hearing, the
provisions specified in Section V above shall be final 20 days from the
date of this Order without further order or proceedings. If an
extension of time for requesting a hearing has been approved, the
provisions specified in Section V shall be final when the extension
expires if a hearing request has not been received. A request for
hearing shall not stay the immediate effectiveness of this order.
Dated this 24th day of February 2009.
For the Nuclear Regulatory Commission.
Elmo E. Collins,
Regional Administrator.
[FR Doc. E9-4761 Filed 3-5-09; 8:45 am]