[Federal Register Volume 73, Number 55 (Thursday, March 20, 2008)]
[Notices]
[Pages 15009-15011]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: E8-5644]
=======================================================================
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket Nos.: 52-018 and 52-019]
Duke Energy Carolina, LLC (Duke); William States Lee III Combined
License Application; Notice of Intent To Prepare an Environmental
Impact Statement and Conduct Scoping Process
Duke Energy Carolinas, LLC (Duke) has submitted an application for
a combined license (COL) for its William States Lee III Nuclear Station
(Lee) Site to build Units 1 & 2, located in the eastern portion of
Cherokee County in north central South Carolina, approximately 7.5
miles southeast of Gaffney, South Carolina. The application for the COL
was submitted by letter dated December 12, 2007, pursuant to the
requirements of Title 10 of the Code of Federal Regulations part 52 (10
CFR part 52). A notice of receipt and availability of the application,
including the environmental report (ER), was published in the Federal
Register on February 1, 2008 (73 FR 6218). A notice of acceptance for
docketing of the application for the COL was published in the Federal
Register on February 29, 2008 (73 FR 11156). A notice of hearing and
opportunity to petition for leave to intervene will be published in the
Federal Register at a later date. The purpose of this notice is to
inform the public that the U.S. Nuclear Regulatory Commission (NRC)
will be preparing an environmental impact statement (EIS) in support of
the review of the COL application and to provide the public an
opportunity to participate in the environmental scoping process, as
defined in 10 CFR 51.29.
In addition, as outlined in 36 CFR 800.8(c), ``Coordination with
the National Environmental Policy Act,'' the NRC staff intends to use
the process and documentation required for the preparation of an EIS to
comply with Section 106 of the National Historic Preservation Act, in
lieu of the procedures set for in 36 CFR 800.3 through 800.6. In
accordance with 10 CFR 51.45 and 51.50, Duke submitted the ER as part
of the application. The ER was prepared pursuant to 10 CFR parts 51 and
52 and is available for public inspection at the NRC Public Document
Room (PDR), located at One White Flint North, 11555 Rockville Pike
(first floor), Rockville, Maryland or from the Publicly Available
Records component of the NRC's Agencywide Documents Access and
Management System (ADAMS). ADAMS is accessible at http://www.nrc.gov/reading-rm/adams.html, which provides access through the NRC's
Electronic Reading Room (ERR) link. The ADAMS Accession Number for the
application dated December 12, 2007 is ML073510876. The ADAMS Accession
Number for supplemental information related to the ER, submitted by
letter dated January 28, 2008, is ML080350324. Persons who do not have
access to ADAMS or who encounter problems in accessing the documents
located in ADAMS should contact the NRC's PDR Reference staff at 1-800-
397-4209 or 301-415-4737 or by sending an e-mail to [email protected]. The
application may also be viewed on the Internet at http://www.nrc.gov/reactors/new-licensing/col/lee.html.
In addition, the Cherokee County Public Library, 300 E. Rutledge
Avenue, Gaffney, SC 29340 has agreed to make the ER available for
public inspection.
The following key reference documents related to the COL
application and the NRC staff's review process are available through
the NRC's Web site at http://www.nrc.gov:
a. 10 CFR part 51, Environmental Protection Regulations for
Domestic Licensing and Related Regulatory Functions,
b. 10 CFR part 52, Licenses, Certifications, and Approvals for
Nuclear Power Plants,
c. 10 CFR part 100, Reactor Site Criteria,
d. NUREG-1555, Standard Review Plans for Environmental Reviews for
Nuclear Power Plants,
e. NUREG/BR-0298, Brochure on Nuclear Power Plant Licensing
Process,
f. Fact Sheet on Nuclear Power Plant Licensing Process,
g. Regulatory Guide 4.2, Preparation of Environmental Reports for
Nuclear Power Stations,
h. Regulatory Guide 1.206, Combined License Applications for
Nuclear Power Plants, and
i. NRR Office Instruction LIC-203, Procedural Guidance for
Preparing
[[Page 15010]]
Environmental Assessments and Considering Environmental Issues.
The regulations, NUREG-series documents, regulatory guides, and
fact sheets can be found under Document Collections in the Electronic
Reading Room on the NRC web page. Finally, Office Instruction LIC-203
can be found in ADAMS in two parts under Accession Numbers ML011710073
(main text) and ML011780314 (charts and figures).
This notice advises the public that the NRC intends to gather the
information necessary to prepare an EIS in support of the review of the
application for the COL at the Duke COL Site. Possible alternatives to
the proposed action (issuance of the COL at the Duke COL Site) include
no action and consideration of alternative sites.
The NRC is required by 10 CFR 51.20(b)(2) to prepare an EIS in
connection with the issuance of a COL. This notice is being published
in accordance with NEPA and NRC regulations found in 10 CFR Part 51.
The NRC will first conduct a scoping process for the EIS and, as soon
as practicable thereafter, will prepare a draft EIS for public comment.
Participation in the scoping process by members of the public and
local, State, Tribal, and Federal government agencies is encouraged.
The scoping process for the EIS will be used to accomplish the
following:
a. Define the proposed action which is to be the subject of the
EIS;
b. Determine the scope of the EIS and identify the significant
issues to be analyzed in depth;
c. Identify and eliminate from detailed study those issues that are
peripheral or that are not significant;
d. Identify any environmental assessments and other EISs that are
being or will be prepared that are related to, but are not part of the
scope of the EIS being considered;
e. Identify other environmental review and consultation
requirements related to the proposed action;
f. Identify parties consulting with the NRC under the National
Historic Preservation Act, as set forth in 36 CFR 800.8(c)(1)(i);
g. Indicate the relationship between the timing of the preparation
of the environmental analysis and the Commission's tentative planning
and decision-making schedule;
h. Identify any cooperating agencies and as appropriate, allocate
assignments for preparation and schedules for completing the EIS to the
NRC and any cooperating agencies; and
i. Describe how the EIS will be prepared and include any contractor
assistance to be used.
The NRC invites the following entities to participate in the
scoping process:
a. The applicant, Duke Energy Carolinas, LLC;
b. Any Federal agency that has jurisdiction by law or special
expertise with respect to any environmental impact involved or that is
authorized to develop and enforce relevant environmental standards;
c. Affected State and local government agencies, including those
authorized to develop and enforce relevant environmental standards;
d. Any affected Indian tribe;
e. Any person who requests or has requested an opportunity to
participate in the scoping process; and
f. Any person who intends to petition for leave to intervene.
In accordance with 10 CFR 51.26, the scoping process for an EIS may
include a public scoping meeting to help identify significant issues
related to a proposed activity and to determine the scope of issues to
be addressed in an EIS. The NRC will hold one public scoping meeting
for the EIS regarding the Duke COL application. The scoping meeting is
scheduled for Thursday, May 1, 2008, at the Gaffney High School
Auditorium, 149 Twin Lake Road, Gaffney, South Carolina. The meeting
will convene at 7 p.m. and will continue until 10 p.m. The meeting will
be transcribed and will include: (1) An overview by the NRC staff of
the NEPA environmental review process, the proposed scope of the EIS,
the proposed review schedule, and (2) the opportunity for interested
government agencies, organizations, and individuals to submit comments
or suggestions on the environmental issues or the proposed scope of the
EIS. Additionally, the NRC staff will host informal discussions from 5
p.m. to 7 p.m. before the start of the meeting at the Gaffney High
School. No formal comments on the proposed scope of the EIS will be
accepted during the informal discussions. To be considered, comments
must be provided either at the transcribed public meeting or in
writing, as discussed below. Persons may register to attend or present
oral comments at the meeting on the scope of the NEPA review by
contacting Ms. Linda M. Tello at 1-800-368-5642, extension 2907 or by
email to the NRC at [email protected], no later than April 18, 2008.
Members of the public may also register to speak at the meeting within
15 minutes of the start of the meeting. Individual oral comments may be
limited by the time available, depending on the number of persons who
register. Members of the public who have not registered may also have
an opportunity to speak, if time permits. Public comments will be
considered in the scoping process for the EIS. Ms. Linda M. Tello will
need to be contacted no later than April 18, 2008, if special equipment
or accommodations are needed to attend or present information at the
public meeting, so that the NRC staff can determine whether the request
can be accommodated.
Members of the public may send written comments on the
environmental scope of the Duke COL review to the Chief, Rulemaking,
Directives, and Editing Branch, Division of Administrative Services,
Office of Administration, Mailstop T-6D59, U.S. Nuclear Regulatory
Commission, Washington, DC 20555-0001 and should cite the publication
date and page number of this Federal Register notice. Comments may also
be delivered to Room T-6D59, Two White Flint North, 11545 Rockville
Pike, Rockville, Maryland from 7:30 a.m. to 4:15 p.m., during Federal
workdays.
To be considered in the scoping process, comments should be
received by the end of the scoping comment period, which is May 20,
2008. Written comments should be postmarked by May 20, 2008. Electronic
comments may be sent via the Internet to the NRC at
[email protected]. Submissions should be sent no later than May 20,
2008, to be considered in the scoping process. Comments will be
available in the scoping summary report electronically and accessible
through the NRC's ERR link at http://www.nrc.gov/reading-rm/adams.html.
Participation in the scoping process for the EIS does not entitle
participants to become parties to the proceeding to which the EIS
relates.
At the conclusion of the scoping process, the NRC staff will
prepare a concise summary of the determination and conclusions reached
including the significant issues identified and will make it publicly
available. The summary will also be available for inspection through
the NRC's ERR link. The staff will then prepare and issue for comment
the draft EIS which will be the subject of separate notices and a
separate public meeting. A copy of the draft EIS will be available for
public inspection at the above-mentioned address and one copy per
request will be provided free of charge. After receipt and
consideration of the comments, the NRC staff will prepare a final EIS
(which will also be available for public inspection).
[[Page 15011]]
Information about the proposed EIS and the scoping process may be
obtained from Ms. Linda M. Tello, Environmental Project Manager at
(301) 415-2907 or by email at [email protected].
Dated at Rockville, Maryland, this 14th day of March 2008.
For the Nuclear Regulatory Commission.
John R. Tappert,
Acting Deputy Director, Division of Site and Environmental Reviews,
Office of New Reactors.
[FR Doc. E8-5644 Filed 3-19-08; 8:45 am]