National Park Service
Final Environmental Impact Statement and Environmental Impact
Report; Giacomini Wetlands Restoration Project; Point Reyes National
Seashore, Marin County, CA; Notice of Availability
Summary: Pursuant to Sec. 102(2)(C) of the National Environmental
Policy Act of 1969 (Pub. L. 91-190, as amended), and the Council on
Environmental Quality Regulations (40 CFR part 1500-1508), the National
Park Service, Department of the Interior, has prepared a Final
Environmental Impact Statement (FEIS) identifying and evaluating the
no-action alternative and four action alternatives for the restoration
of the Giacomini wetlands. When approved, the plan will guide the
National Park Service in restoration and public access actions for
lands at the headwaters of Tomales Bay, Marin County, California.
Because some of the proposed restoration project area includes state,
county and private lands, the document also fulfills California
Environmental Quality Act (CEQA) requirements as a Final Environmental
Impact Report (EIR). The California State Lands Commission (CALC) is
the CEQA lead agency for this project. Through the FEIS/EIR, the
potential impacts of the five alternatives are assessed and, where
appropriate, measures to avoid or reduce the intensity of potential
effects are identified. Three preliminary restoration options that were
considered, but rejected because they did not achieve restoration
objectives or were infeasible, are also described in the FEIS/EIR.
Project Planning Background: Point Reyes National Seashore is a
unit of the National Park Service (NPS) located in western Marin
County, California. It was established by Congress on September 13,
1962, ``to save and preserve, for the purpose of public recreation,
benefit, and inspiration, a portion of the diminishing seashore of the
United States that remains undeveloped'' (Pub. L. 87-657). A large
portion of Tomales Bay watershed lands were acquired by the NPS in the
1960s and 1970s for establishment of two neighboring parks--Point Reyes
National Seashore (Seashore) and Golden Gate National Recreation Area
(GGNRA). In 1980, the boundary for GGNRA was expanded to include the
Waldo Giacomini Ranch (Giacomini Ranch) and the eastern portion of
Tomales Bay. The Giacomini Ranch falls within the north district of the
GGNRA, which is administered by the Seashore.
The Seashore and CALC are proposing to restore historic wetlands at
Giacomini Ranch in Tomales Bay, an embayment that borders the Seashore
to the east and north. The Giacomini Ranch property was once part of a
large tidal marsh complex at the southern end of Tomales Bay that also
encompassed portions of Olema Marsh (a 60-acre freshwater marsh that is
partially owned by the NPS). The Giacomini property was diked in 1946
and has been used by the Waldo Giacomini family as a dairy since then.
The property was purchased from the Giacomini family in 2000. Partial
funding for the purchase came from the California Department of
Transportation (CalTrans), which was under obligation to the California
Coastal Commission (CCC) to mitigate for impacts resulting from the
Lone Tree road repair along State Route 1 conducted in the early 1990s.
The CCC eventually allowed CalTrans to fulfill mitigation obligations
by making funds available to the NPS to purchase, restore, and manage a
replacement wetland site.
While the NPS is obligated under its agreement with CalTrans and
CCC to mitigate only a total of 3.6 acres, the Seashore believes that
the potential value of the historic salt marsh is significant not only
to the NPS and its resource conservation objectives, but to the Tomales
Bay watershed ecosystem as a whole. Tomales Bay was recently declared
impaired for sediment, nutrients, and fecal coliform by the San
Francisco Regional Water Quality Control Board under Sec. 303(d) of
the Clean Water Act. Coastal wetlands act as both a food source and
filtering system for estuarine and marine systems, and the loss of
these wetlands in many parts of the bay has contributed to this
designation. The diking of the Giacomini property resulted in the loss
of hydrologic connectivity and diminished delta functionality for more
than 50 percent of the coastal tidal wetlands present in Tomales Bay in
the late 1800s. Restoration would reestablish hydrologic connectivity
between Tomales Bay and the project area, resulting in increased
wetland functionality.
The project purpose and goals reflect a broad ecosystem-level
approach to restoration. The purpose of the proposed project is to
restore natural hydrologic processes within a significant portion of
the project area, thereby promoting restoration of ecological processes
and functions. Three goals, which further support the overall purpose,
were also developed, as follows:
Restore natural, self-sustaining tidal, fluvial
(streamflow), and groundwater hydrologic processes, thereby enabling
reestablishment of some of the ecological processes and functions
associated with wetland and riparian areas, such as water quality
improvement, floodwater storage, food chain support, and wildlife
habitat.
Pursue a watershed-based approach to restoration so as to
emphasize opportunities to improve ecological conditions within the
entire Tomales Bay watershed, not just in the project area itself.
To the extent possible, incorporate opportunities for the
public to experience and enjoy the restoration process as long as
opportunities do not conflict with the project's purpose or with NPS,
CALC, or other agency legislation or policies.
For these reasons, the NPS and CALC propose to restore natural
hydrologic and ecological processes on most or all of the 563-acre
property. The NPS and CALC developed a range of alternatives for
accomplishing this restoration project that encompass a spectrum of
hydrologic and topographic changes. However, there are a series of
activities that would be conducted under all five alternatives,
including: Discontinuation of agricultural land management on the
property, removal of general agricultural infrastructure and buildings
from upland areas, and periodic maintenance of creeks to ensure that
sediment deposition does not elevate flood risk to adjacent properties.
In addition, the Giacomini family would remove all personal property
from the project area, including worker housing trailers near Mesa
Road. Water rights to Lagunitas Creek, acquired as part of the transfer
of ownership, would be dedicated to in-stream flow. The NPS would also
enter into a lease agreement with the CALC for leasing of subtidal
lands in Lagunitas Creek within the project area. Finally, the NPS will
be working with the USGS on an effort to expand the tidewater Goby
population within the southern portions of Tomales Bay.
Proposed Giacomini Wetlands Restoration: Extensive Restoration of
the Giacomini Ranch East Pasture, Full Restoration of the West Pasture,
and
[[Page 36028]]
Restoration of Olema Marsh with Limited Public Access (Alternative D).
This alternative has been determined to be ``environmentally
preferred'', and involves complete removal of levees in both the West
and East Pasture. In general, this alternative builds upon the actions
proposed in Alternative B and Alternative C (see below) by fully
realigning one of the leveed creeks within the Giacomini Ranch;
excavating a portion of the ranch pasture into active intertidal
marshplain and floodplain; increasing the amount of culvert replacement
to improve hydraulic connectivity, streamflow, and passage of salmonid
species; and increasing active revegetation and invasive non-native
plant removal efforts. In addition, this alternative incorporates
adaptive restoration of Olema Marsh (which is located south of
Giacomini Ranch and White House Pool and is owned by Audubon Canyon
Ranch (ACR) and the NPS); this would include a phased approach to
shallow channel excavation, vegetated berm removal, and potential
replacement of Levee Road and/or Bear Valley Road culverts in the
future should initial restoration efforts not achieve the desired
degree of success.
Public access components of Alternative D include an improved spur
trail leading to the edge of the Dairy Mesa; an improved spur trail
extension of the existing Tomales Bay Trail; an improved spur trail on
the southern perimeter following the existing alignment of an informal
social path; and an ADA-compliant path in White House Pool County Park.
The NPS would also pursue working with Marin County (through separate
environmental compliance) to consider additional public access
facilities on the southern perimeter of the project area, including
reevaluation of a trail along Levee Road, extension of a trail to
Inverness Park, and, should other options not prove viable, a non-
vehicular bridge across Lagunitas Creek.
Alternatives to Proposed Project: Under the No Action Alternative,
levees, tidegates, and culverts in the Giacomini Ranch will remain. An
11-acre area will be restored on the northeast corner of the east
pasture to satisfy mitigation requirements for aquatic habitat impacts
caused by CalTrans due to road repairs on State Route 1 in Marin County
in exchange for the NPS receiving monies to purchase and restore the
Giacomini Ranch. The remainder of the levees in the East Pasture and
West Pasture would no longer be maintained. Under the No Action
Alternative only, there is potential for limited grazing, with
consultation conducted under a separate compliance process. Olema Marsh
would not be restored, and there would be no new public access
facilities.
Alternative A--Limited Restoration of the Giacomini Ranch East
Pasture Only with Expanded Public Access, Including Culverted Earthen
Fill Trail on Eastern Perimeter. This alternative involves selective
breaching of the East Pasture levee, while levees and tidegates in the
West Pasture would not be removed. A limited amount of tidal channel
creation, creek bank grading, and revegetation would also be performed
in the East Pasture. Most of the actions under this alternative focus
on removing agricultural infrastructure such as filling of ditches,
ripping of compacted roads, fence removal, and removal of pumps,
pipelines, and concrete spillways, as well as removal of ranch
buildings. For future public access, the southern perimeter trail would
include a prefabricated bridge across Lagunitas Creek, near the old
summer dam location across from White House Pool County Park. The
bridge design would place footings outside of the active channel, so as
to not impinge on hydrologic processes. Future extension of the
southern perimeter trail, in collaboration with the County of Marin,
would connect White House Pool County Park with a path along Sir
Francis Drake Boulevard (that would either run alongside the road or
move off the road at the southern end of the unrestored West Pasture
onto a low-elevation boardwalk that would join back with Sir Francis
Drake Boulevard in Inverness Park). Other infrastructure constructed is
a culverted berm through-trail on the eastern perimeter of the East
Pasture.
Alternative B--Moderate Restoration of the Giacomini Ranch East
Pasture and Limited Restoration of the West Pasture with Expanded
Public Access, Including Boardwalk Trail on the Eastern Perimeter. This
alternative would completely remove the East Pasture levees and create
several breaches in the West Pasture levee, as well as remove the
tidegate on Fish Hatchery Creek. More tidal channel creation, grading,
and revegetation would occur than under Alternative A. There would be
no activities taken at Olema Marsh. Most of the new public access
facilities would continue to be limited to the eastern and southern
perimeters of the East Pasture, including construction of the
pedestrian access bridge across Lagunitas Creek near the old summer
dam, and extension of the southern perimeter trail to Inverness Park.
The culverted berm through-trail on the eastern perimeter in
Alternative A would instead be a boardwalk. On the West Pasture north
levee, a viewing area would replace the existing informal trail.
Alternative C--Full Restoration of the Giacomini Ranch East and
West Pastures and Restoration of Olema Marsh, with Moderate Public
Access. This alternative involves complete removal of levees in both
the West and East Pasture. In general, this alternative would result in
more tidal channel creation, grading, and revegetation than Alternative
B. In addition, the project boundary is expanded to include Olema
Marsh, which is located south of the Giacomini Ranch and White House
Pool and is owned by ACR and the NPS. Olema Marsh and the Giacomini
Ranch once formed an integrated tidal wetland complex. In Alternative
C, there would be an adaptive approach for Olema Marsh restoration that
would include phased shallow channel excavation and vegetated berm
removal. Levee Road and Bear Valley Road culverts could be replaced in
the future should initial restoration efforts not achieve the desired
degree of success. Public access components include the southern
perimeter path and proposed future trails as described under
Alternative A and Alternative B, but there would be two spur trails
rather than a through-trail on the eastern perimeter of the Giacomini
Ranch.
Principal Differences Between the Draft and Final EIS/EIR:
Change in Preferred Alternative: The alternative preferred by the
NPS and CALC has been changed to Alternative D from Alternative C. The
lead agencies initially chose Alternative C as the Preferred
Alternative as it appeared to best meet both wetland restoration goals
and community public access needs. During public review of the DEIS/
EIR, a large number of responses from the public, organizations, and
agencies advocated selecting Alternative D because it was more
compatible with restoration and would have less traffic, noise,
pollution, and land use impacts.
Changes to Alternative D: Alternative D has been modified slightly
in the FEIS/EIR in response to public feedback so as to slightly
decrease the degree of excavation, to remove eucalyptus from Tomasini
Creek, and to construct an ADA-compliant trail and viewing platform at
the nearby White House Pool County Park. In addition, this alternative
now also incorporates the option for NPS to collaborate with Marin
County in a separate environmental process on possible additional
public access facilities on the southern perimeter of the project area
(as noted above).
[[Page 36029]]
Change in Impact Determinations: Because of refinement of
construction scheduling and project design (identified in Chapter 2),
the NPS and CALC have re-assessed some levels of impact identified,
although none of these changes results in any ``Significant,
Unavoidable Impacts'', such that all major impacts are mitigated to
moderate or lesser intensities.
Construction-related air quality impacts under Alternative
C have been reduced to moderate, although Alternative D still would
have major or substantial impacts that are mitigated to moderate levels
through implementation of recommended Best Management Practices.
Alternative A and Alternative B would have major impacts
on riparian habitat due to construction of the eastern perimeter trail
that could conflict with state and local policies on riparian habitat
protection, but these impacts would be mitigated to minor or moderate
through active and passive revegetation efforts.
Major restoration actions in Olema Marsh identified as
part of the adaptive restoration under Alternative C and Alternative D
such as culvert replacement would not be implemented until the NPS can
confirm these actions would not cause major impacts to municipal water
supply through increasing water salinities in the portion of the
Lagunitas Creek that is adjacent to municipal groundwater wells.
Summary of Public Engagement: On September 23, 2002, a Notice of
Intent (NOI) to conduct public scoping to inform preparation of an EIS
was published in the Federal Register. On September 25, 2002, a copy of
the NOI and scoping information was sent to 45 landowners adjacent to
the project area, and 163 persons and organizations on a public review
request list maintained by the Seashore. On October 4, 2002, the NOI
was sent to the Governor's Office of Planning and Research State
Clearinghouse for distribution to relevant state agencies (SCH
2002114002). Following agreement by CALC to act as the lead CEQA
agency, a Notice of Preparation (NOP) for preparation of a joint EIS/
EIR was prepared by CALC, and distributed to the State Clearinghouse,
which circulated the NOP between May 29 and June 30, 2003. The
extensive public scoping period also closed on June 30, 2003.
Oral comments were heard at a public information meeting at the
October 19, 2002 Advisory Commission held at the Point Reyes Dance
Palace where approximately 30 to 40 members of the public attended. In
addition to the oral comments obtained, approximately 86 individuals or
private organizations provided written comments regarding the proposed
restoration. Regulatory scoping meetings were conducted on November 6,
2002 and November 8, 2002 during the public scoping period. The NPS and
CALC received comments from seven local, state, or federal agencies.
After the public scoping phase concluded on June 30, 2003, a staff
report was prepared that summarized all information derived from the
public scoping process.
After a series of internal post-scoping discussions in spring 2004,
the NPS and CALC hosted a series of information meetings with
regulatory and local and state agencies, adjacent landowners, and local
technical experts in the field of wetland restoration, to present and
receive feedback on preliminary restoration and public access concepts.
This phase culminated in a public workshop on June 22, 2004, at the
Seashore Red Barn attended by more than 110 people. Following the June
public workshop, all interested individuals and organizations were
encouraged to submit comments to the NPS and CALC on the restoration
concepts and scope of the proposed DEIS/EIR.
Through July 23, 2004 written letters or e-mails from 58
individuals and 14 private organizations were received, as well as two
petitions with a total of approximately 450 signatures. NPS staff also
met with representatives of stakeholder groups from Marin County and
interested agencies that requested briefings. In response to the
comments received, the NPS and CALC contracted for two additional
studies on public access options within the project area that evaluated
potential impacts on resources and adjacent land uses, as well as
technical feasibility and costs. As part of this effort, additional
meetings were held with adjacent landowners and the general public in
February-March, 2005.
The Seashore's Notice of Availability for the DEIS/EIR was
published in the Federal Register on November 3, 2006. The EPA's
notification of filing of the DEIS/EIR was published in the Federal
Register on December 15, 2006, formally initiating the 60-day public
comment period. A notice that the DEIS/EIR had been also filed with the
State Clearinghouse was published on December 18, 2006. The Seashore
mailed over 450 letters regarding availability of the DEIS/EIR for
public review on December 13, 2006 (this letter also announced a public
meeting scheduled for January 25, 2007, at the Seashore Red Barn, and
confirmed that the public comment period would end February 14, 2007).
On December 14, 2006, a press release announcing the public meeting
was distributed to the Point Reyes Light, Marin Independent Journal,
and Press Democrat, as well as 28 other media outlets, including
newspapers, radio stations, and television stations. Details about the
public meeting were also posted on the Seashore's Web site. The Marin
Independent Journal and Point Reyes Light published articles about
release of the DEIS/EIR and the pending public meeting. Approximately
100 members of the public attended the January 25, 2007 meeting. The
Point Reyes Light published an account of the meeting on February 1,
2007.
Altogether approximately 180 interested individuals and
organizations responded to release of the DEIS/EIR; approximately 170
were from private individuals. There were no form letters. More than 99
percent of the letters submitted were from residents of Marin County.
Organizations providing comments included the Environmental Action
Committee of Marin; Point Reyes Lodging Association; Marin County
Bicycle Coalition/Community Pathways Committee/Access 4 Bikes;
California Native Plant Society; Point Reyes Village Association;
Sierra Club, Marin Chapter; and Tomales Bay Association. Ten responses
were received from local, state, or federal agencies--the California
Coastal Commission; the California Regional Water Quality Control
Board; the Gulf of the Farallones National Marine Sanctuary; the North
Marin Water District; the Marin/Sonoma Mosquito and Vector Control
District; the County of Marin Department of Public Works; the County of
Marin Department of Parks and Open Space District; the State Department
of Conservation; the State of California Department of Fish and Game;
and the EPA.
More than 90 percent of the oral and written comments received
during the public meeting and throughout the comment period concerned
the choice of Alternative C as the Preferred Alternative. A large
number of comments also advocated modifications to either the existing
Preferred Alternative or to Alternative D, with most of these proposed
modifications focusing on changes to the public access components on
the eastern and southern perimeters of the project area. On March 2,
2007, the EPA published its Lack of Objection (LO) findings regarding
the DEIS/EIR, noting that the ``EPA supports the proposed project and
believes it will significantly improve the hydrologic
[[Page 36030]]
and ecological processes and functions in the Tomales Bay Watershed.''
All written comments received and a summary of commentary from the
January 25, 2007, public meeting are available for inspection at the
Seashore Administration Building, 1 Bear Valley Road, Point Reyes
Station, CA. Substantive comments and responses are documented in the
FEIS/EIR. Copies of the FEIS/EIR may be obtained from the
Superintendent, Point Reyes National Seashore, Point Reyes, CA 94956,
Attn: Giacomini Wetlands Restoration Project, or by e-mail request to:
[email protected] (in the subject line, type: Giacomini Wetlands
Restoration Project). The document will be sent directly to those who
have requested it, and also will be posted on the Internet at the
Seashore's Web site http://www.nps.gov/pore; and both the printed
document and digital version on compact disk will be available at the
park headquarters and local libraries.
Decision: As a delegated EIS/EIR, the official responsible for the
final decision is the Regional Director, Pacific West Region. A Record
of Decision, fully documenting the entire conservation planning and
environmental decision-making process, will be prepared not sooner than
30 days following publication in the Federal Register of the EPA's
notice of filing and availability of the Final EIS/EIR. Subsequently
and prior to implementation, notice of approval of the Record of
Decision will likewise be published in the Federal Register, as well as
announced via local and regional news media. Following approval of the
Giacomini Wetlands Restoration Project, the official responsible for
project implementation will be the Superintendent, Point Reyes National
Seashore.
Dated: April 25, 2007.
George J. Turnbull,
Acting Regional Director, Pacific West Region.
[FR Doc. E7-12714 Filed 6-29-07; 8:45 am]