[Federal Register Volume 72, Number 28 (Monday, February 12, 2007)]
[Notices]
[Pages 6606-6609]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: E7-2374]
-----------------------------------------------------------------------
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-397]
Energy Northwest; Notice of Consideration of Issuance of
Amendment to Facility Operating License, Proposed No Significant
Hazards Consideration Determination, and Opportunity for a Hearing
The U.S. Nuclear Regulatory Commission (the Commission) is
considering issuance of an amendment to Facility Operating License No.
NPF-21, issued to Energy Northwest (the licensee), for operation of the
Columbia Generating Station located in Benton County, Washington.
The proposed amendment would revise Technical Specification (TS)
3.6.1.7, ``Suppression Chamber-to-Drywell Vacuum Breakers,'' to allow a
one-time extension to the current closure verification surveillance
requirement (SR) for one of two
[[Page 6607]]
redundant disks in one of nine vacuum breakers until reliable position
indication can be restored in the main control room during the next
refueling outage (R-18). Verification of closure of each vacuum breaker
disk is currently required every 14 days by SR 3.6.1.7.1. The licensee
requested that the proposed change be considered on an exigent basis.
The licensee stated that during the January 6, 2007, functional
test of vacuum breaker CVB-V-1JK, one of the redundant disks in the
vacuum breaker assembly did not meet the procedurally defined
acceptance criteria for open or close due to an issue with position
indication limit switches. This problem has resulted in unreliable
position indication for closure of the rear disk of the vacuum breaker
and requires an alternate method of closure verification be employed
(i.e., a differential pressure test). Consistent with SR 3.6.1.7.1,
this test must be performed every 14 days. However, performance of the
alternate test creates an unnecessary increase in plant risk relative
to other compensatory options.
The proposed one-time change to TS 3.6.1.7 would revise SR
3.6.1.7.1 by adding a note to provide an extension to the SR for the
rear disk of vacuum breaker CVB-V-1JK. This extension would remain in
effect until the end of R-18, currently scheduled to begin on May 12,
2007.
On January 6, 2007, during a functional test of vacuum breaker CVB-
V-1JK, the rear disk of the vacuum breaker did not meet the
procedurally defined acceptance criteria for open or close due to an
issue with the position indication limit switches. When CVB-V-1JK was
cycled from the control room, the close position indication did not
extinguish and prevented the open position indication from
illuminating. The separate full open indication did illuminate,
indicating that the rear disk opened as expected; however, the closure
of the disk could not be confirmed using normal position indication.
With unreliable position indication in the main control room for
the rear disk of vacuum breaker CVB-1JK, the alternate method of
closure verification using the differential pressure test is required.
This test, as described in the TS Bases, involves establishing a
differential pressure between the drywell and suppression chamber equal
to, or in excess of, 0.5 pounds per square inch differential (psid) to
verify that the disk being tested can maintain that differential for 60
minutes. Current test procedures specify that a differential pressure
of 0.7 to 0.75 psid be established between the drywell and suppression
chamber. This value provides margin to accommodate minor internal
drywell temperature changes during the testing. Maintaining a
differential pressure between the drywell and suppression chamber is a
positive indication that the vacuum breaker disk being tested is
closed. This test was performed on the rear disk of vacuum breaker CVB-
V-1JK on January 8, 2007, and again on January 22, 2007, and confirmed
that the disk was seated. The degraded limit switches and associated
circuitry are located in the inerted wetwell and cannot be accessed to
restore normal position indication in the control room for the rear
disk of vacuum breaker CVB-V-1JK while at power. Therefore, continued
compliance with SR 3.6.1.7.1 would require that this pressure test be
performed every 14 days.
The licensee stated that when performing the vacuum breaker closure
differential pressure test, drywell pressure is increased from near
atmospheric conditions to approximately 45 percent of the Drywell
Pressure--High scram setpoint of 1.68 pounds per square inch gauge.
Frequent differential pressure testing places the plant in a condition
with degraded margin for a reactor scram. This increases the risk of an
inadvertent reactor scram from a minor drywell pressure transient which
may have been managed by the operator if it occurred at a normal
drywell pressure and can unduly challenge plant safety systems and
personnel. Furthermore, when performing the differential pressure test
to verify continued closure of the rear disk of vacuum breaker CVB-V-
1JK, the front disk is required to be open for at least 60 minutes
while the test is being performed which degrades the capability of the
vacuum breaker assembly to prevent bypass leakage when required. As
previously discussed, TS 3.6.1.7 recognizes this increase in plant risk
by drawing a distinction between an actual communication path and a
potential communication path in the derivation of entry conditions and
required actions.
The licensee concluded that a more appropriate method to maintain
public health and safety is to ensure that both disks of vacuum breaker
CVB-V-1JK continue to maintain their current closed position without a
change of state. Operating in this configuration, both the front and
rear disks of vacuum breaker CVB-V-1JK would conservatively not be
credited to perform the open safety function and would be declared
inoperable for opening. Both disks are currently closed and have been
verified as such using the normal position indication in the control
room for the front disk and by the differential pressure test for the
rear disk. This configuration is currently allowed by TS 3.6.1.7, since
only seven of nine vacuum breakers are required to be operable for
opening while in Modes 1, 2, and 3. In addition, with vacuum breaker
CVB-V-1JK declared inoperable for the open function, SR 3.6.1.7.2 would
not be required to be performed and the breaker disks would not need to
be cycled.
Continued operation in this manner until the end of R-18 would
ensure that plant risk is minimized but also requires an extension from
the current 14-day interval of SR 3.6.1.7.1. The proposed change is
necessary because continued performance of SR 3.6.1.7.1 for the rear
disk of CVB-V-1JK results in putting the plant in a condition that
unduly increases the risk of an inadvertent reactor scram challenging
both plant systems and personnel. Failure to perform the differential
pressure test required by SR 3.6.1.7.1 would result in a failed
verification of the current closed state of these vacuum breakers. TS
3.6.1.7 would then require placing the reactor in Mode 3 within the
next 84 hours and Mode 4 in the following 24 hours and would also
challenge plant system and personnel.
The licensee states that it will continue to verify that the front
disk of CVB-V-1JK and both disks of the other 8 vacuum breakers are
closed every 14 days as required by SR 3.6.1.7.1. If reasonable
evidence is discovered to conclude that the rear disk of vacuum breaker
CVB-V-1JK may no longer be in a closed position, the licensee states
that it will take compensatory measures to verify that this disk is
closed within 72 hours or declare the disk not closed and enter the
appropriate action statement. In the proposed note, evidence that the
rear disk may no longer be in a closed position is defined as evidence
that the front disk has opened or that the rear disk has experienced a
differential pressure in the direction that could cause the disk to
open.
Before issuance of the proposed license amendment, the Commission
will have made findings required by the Atomic Energy Act of 1954, as
amended (the Act) and the Commission's regulations.
Pursuant to 10 CFR 50.91(a)(6) for amendments to be granted under
exigent circumstances, the NRC staff must determine that the amendment
request involves no significant hazards consideration. Under the
Commission's regulations in 10 CFR 50.92, this means that operation of
the facility in
[[Page 6608]]
accordance with the proposed amendment would not (1) Involve a
significant increase in the probability or consequences of an accident
previously evaluated; or (2) create the possibility of a new or
different kind of accident from any accident previously evaluated; or
(3) involve a significant reduction in a margin of safety. As required
by 10 CFR 50.91(a), the licensee has provided its analysis of the issue
of no significant hazards consideration, which is presented below:
1. Does the proposed amendment involve a significant increase in
the probability or consequences of an accident previously evaluated?
Response: No.
Proper functioning of the suppression chamber-to-drywell vacuum
breakers is required for accident mitigation. Failure of the vacuum
breakers is not assumed as an accident initiator for any accident
previously evaluated. Therefore, any potential failure of a vacuum
breaker to perform when necessary will not affect the probability of
an accident previously evaluated.
During a LOCA [loss-of-coolant accident], the vacuum breakers
are assumed to initially be closed to limit drywell-to-suppression
chamber bypass leakage and must be capable of re-closing following a
suppression pool swell event. The vacuum breakers open to prevent an
excessive vacuum in the drywell. The proposed change will not affect
the capability of the required vacuum breakers to perform their open
and close safety functions since the change only affects position
verification and high confidence is assured that the disk remains
closed. Therefore, the proposed changes do not involve a significant
increase in the probability or consequences of an accident
previously evaluated.
2. Does the proposed amendment create the possibility of a new
or different kind of accident from any accident previously
evaluated?
Response: No.
The suppression chamber-to-drywell vacuum breakers are used to
mitigate the potential consequences of an accident. The proposed
change does not affect the capability of required vacuum breakers to
perform their open and closed safety functions. Thus, the initial
conditions assumed in the accident analysis are not affected. The
proposed amendment does not involve a change to plant design and
does not involve any new modes of operation or testing methods.
Accordingly, the required vacuum breakers will continue to perform
their accident mitigation safety functions as previously evaluated.
Therefore, the proposed changes do not create the possibility of a
new or different kind of accident from any accident previously
evaluated.
3. Does the proposed amendment involve a significant reduction
in a margin of safety?
Response: No.
The extension of the closure verification surveillance interval
for one of the two disks in a vacuum breaker for approximately 4
months is not risk significant as all required safety functions will
continue to be performed. The vacuum breakers are not modified by
the proposed amendment. The accident analysis assumptions for the
closed safety functions of the vacuum breakers are satisfied when at
least one of the disks in each of the nine vacuum breaker lines are
fully closed and capable of re-closing following a suppression pool
swell. The additional disk in each line satisfies the single failure
criterion. The open safety function of the vacuum breakers is
satisfied when 6 of the 9 vacuum breaker assemblies open during a
DBA [design basis accident]. The other vacuum breakers satisfy the
single failure criterion and provide additional defense-in-depth.
Since all of the vacuum breakers are considered to perform their
close safety function and 8 of 9 would be available to perform their
open safety function, the proposed change will not involve a
significant reduction in a margin of safety.
The NRC staff has reviewed the licensee's analysis and, based on
this review, it appears that the three standards of 10 CFR 50.92(c) are
satisfied. Therefore, the NRC staff proposes to determine that the
amendment request involves no significant hazards consideration.
The Commission is seeking public comments on this proposed
determination. Any comments received within 14 days after the date of
publication of this notice will be considered in making any final
determination.
Normally, the Commission will not issue the amendment until the
expiration of the 14-day notice period. However, should circumstances
change during the notice period, such that failure to act in a timely
way would result, for example, in derating or shutdown of the facility,
the Commission may issue the license amendment before the expiration of
the 14-day notice period, provided that its final determination is that
the amendment involves no significant hazards consideration. The final
determination will consider all public and State comments received.
Should the Commission take this action, it will publish in the Federal
Register a notice of issuance. The Commission expects that the need to
take this action will occur very infrequently.
Written comments may be submitted by mail to the Chief, Rulemaking,
Directives and Editing Branch, Division of Administrative Services,
Office of Administration, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, and should cite the publication date and
page number of this Federal Register notice. Written comments may also
be delivered to Room 6D59, Two White Flint North, 11545 Rockville Pike,
Rockville, Maryland, from 7:30 a.m. to 4:15 p.m. Federal workdays.
Documents may be examined, and/or copied for a fee, at the NRC's Public
Document Room, located at One White Flint North, Public File Area O1
F21, 11555 Rockville Pike (first floor), Rockville, Maryland.
The filing of requests for hearing and petitions for leave to
intervene is discussed below.
Within 60 days after the date of publication of this notice, the
licensee may file a request for a hearing with respect to issuance of
the amendment to the subject facility operating license and any person
whose interest may be affected by this proceeding and who wishes to
participate as a party in the proceeding must file a written request
for a hearing and a petition for leave to intervene. Requests for a
hearing and a petition for leave to intervene shall be filed in
accordance with the Commission's ``Rules of Practice for Domestic
Licensing Proceedings and Issuance of Orders'' in 10 CFR Part 2.
Interested persons should consult a current copy of 10 CFR 2.309, which
is available at the Commission's PDR, located at One White Flint North,
Public File Area O1 F21, 11555 Rockville Pike (first floor), Rockville,
Maryland. Publicly available records will be accessible from the
Agencywide Documents Access and Management System's (ADAMS) Public
Electronic Reading Room on the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/doc-collections/cfr/. If a request for a hearing
or petition for leave to intervene is filed by the above date, the
Commission or a presiding officer designated by the Commission or by
the Chief Administrative Judge of the Atomic Safety and Licensing Board
Panel, will rule on the request and/or petition; and the Secretary or
the Chief Administrative Judge of the Atomic Safety and Licensing Board
will issue a notice of a hearing or an appropriate order.
As required by 10 CFR 2.309, a petition for leave to intervene
shall set forth with particularity the interest of the petitioner in
the proceeding, and how that interest may be affected by the results of
the proceeding. The petition should specifically explain the reasons
why intervention should be permitted with particular reference to the
following general requirements: (1) The name, address and telephone
number of the requestor or petitioner; (2) the nature of the
requestor's/petitioner's right under the Act to be made a party to the
proceeding; (3) the nature and extent of the requestor's/petitioner's
property, financial, or other interest in the proceeding; and (4) the
possible
[[Page 6609]]
effect of any decision or order which may be entered in the proceeding
on the requestor's/petitioner's interest. The petition must also
identify the specific contentions which the petitioner/requestor seeks
to have litigated at the proceeding.
Each contention must consist of a specific statement of the issue
of law or fact to be raised or controverted. In addition, the
petitioner/requestor shall provide a brief explanation of the bases for
the contention and a concise statement of the alleged facts or expert
opinion which support the contention and on which the petitioner
intends to rely in proving the contention at the hearing. The
petitioner/requestor must also provide references to those specific
sources and documents of which the petitioner/requestor is aware and on
which the petitioner/requestor intends to rely to establish those facts
or expert opinion. The petitioner/requestor must provide sufficient
information to show that a genuine dispute exists with the applicant on
a material issue of law or fact. Contentions shall be limited to
matters within the scope of the amendment under consideration. The
contention must be one which, if proven, would entitle the petitioner/
requestor to relief. A petitioner/requestor who fails to satisfy these
requirements with respect to at least one contention will not be
permitted to participate as a party.
Those permitted to intervene become parties to the proceeding,
subject to any limitations in the order granting leave to intervene,
and have the opportunity to participate fully in the conduct of the
hearing.
If a hearing is requested, the Commission will make a final
determination on the issue of no significant hazards consideration. The
final determination will serve to decide when the hearing is held. If
the final determination is that the amendment request involves no
significant hazards consideration, the Commission may issue the
amendment and make it immediately effective, notwithstanding the
request for a hearing. Any hearing held would take place after issuance
of the amendment. If the final determination is that the amendment
request involves a significant hazards consideration, any hearing held
would take place before the issuance of any amendment.
Nontimely requests and/or petitions and contentions will not be
entertained absent a determination by the Commission or the presiding
officer of the Atomic Safety and Licensing Board that the petition,
request and/or the contentions should be granted based on a balancing
of the factors specified in 10 CFR 2.309(c)(1)(i)-(viii).
A request for a hearing or a petition for leave to intervene must
be filed by: (1) First class mail addressed to the Office of the
Secretary of the Commission, U.S. Nuclear Regulatory Commission,
Washington, DC 20555-0001, Attention: Rulemaking and Adjudications
Staff; (2) courier, express mail, and expedited delivery services:
Office of the Secretary, Sixteenth Floor, One White Flint North, 11555
Rockville Pike, Rockville, Maryland, 20852, Attention: Rulemaking and
Adjudications Staff; (3) E-mail addressed to the Office of the
Secretary, U.S. Nuclear Regulatory Commission, [email protected];
or (4) facsimile transmission addressed to the Office of the Secretary,
U.S. Nuclear Regulatory Commission, Washington, DC, Attention:
Rulemakings and Adjudications Staff at (301) 415-1101, verification
number is (301) 415-1966. A copy of the request for hearing and
petition for leave to intervene should also be sent to the Office of
the General Counsel, U.S. Nuclear Regulatory Commission, Washington, DC
20555-0001, and it is requested that copies be transmitted either by
means of facsimile transmission to 301-415-3725 or by e-mail to
[email protected]. A copy of the request for hearing and petition
for leave to intervene should also be sent to William A. Horin, Esq.,
Winston & Strawn, 1700 K Street, NW., Washington, DC 20006-3817,
attorney for the licensee.
For further details with respect to this action, see the
application for amendment dated February 2, 2007, which is available
for public inspection at the Commission's Public Document Room (PDR),
located at One White Flint North, Public File Area O1 F21, 11555
Rockville Pike (first floor), Rockville, Maryland. Publicly available
records will be accessible electronically from the Agencywide Documents
Access and Management System's (ADAMS) Public Electronic Reading Room
on the Internet at the NRC Web site http://www.nrc.gov/reading-rm.html.
Persons who do not have access to ADAMS or who encounter problems in
accessing the documents located in ADAMS should contact the NRC PDR
Reference staff by telephone at 1-800-397-4209, or 301-415-4737, or by
e-mail to [email protected].
Dated at Rockville, Maryland, this 6th day of February 2007.
For the Nuclear Regulatory Commission.
Carl F. Lyon,
Project Manager, Plant Licensing Branch IV, Division of Operating
Reactor Licensing Office of Nuclear Reactor Regulation.
[FR Doc. E7-2374 Filed 2-9-07; 8:45 am]
BILLING CODE 7590-01-P