NUCLEAR REGULATORY COMMISSION
[Docket Nos. 50-317, 50-318, and 72-8; Renewed License Nos. DPR-53 and
DPR-69, and Materials License No. SNM-2505]
In the Matter of Calvert Cliffs Nuclear Power Plant, Inc.
(Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2, and Calvert
Cliffs Independent Spent Fuel Storage Installation); Order Approving
Application Regarding Proposed Corporate Merger
I.
Calvert Cliffs Nuclear Power Plant, Inc. (CCNPP Inc. or the
licensee) is the holder of Renewed Facility Operating Licenses Nos.
DPR-53 and DPR-69, which authorize the possession, use, and operation
of the Calvert Cliffs Nuclear Power Plant (the facility or CCNPP), and
Materials License No. SNM-2505, which authorizes the possession, use,
and operation of the Calvert Cliffs Independent Spent Fuel Storage
Installation (CCISFSI). CCNPP Inc. is licensed by the U.S. Nuclear
Regulatory Commission (NRC or Commission) to operate CCNPP and CCISFSI.
The facility is located at the licensee's site in Calvert County,
Maryland.
II.
By application dated January 23, 2006, as supplemented by letters
dated April 25 and May 25, 2006 (collectively referred to herein as the
application), Constellation Generation Group, LLC (CGG LLC), acting on
behalf of CCNPP Inc., requested that the NRC, pursuant to 10 CFR 50.80
and 10 CFR 72.50, consent to the proposed indirect transfer of control
of the licenses.
According to the application filed by CGG LLC, on behalf of CCNPP
Inc., CCNPP and CCISFSI are wholly owned by CCNPP Inc. CCNPP Inc. is
wholly owned by Constellation Nuclear Power Plants, Inc.
As stated in the application, in connection with the merger of CGG
LLC's parent company, Constellation Energy Group, Inc. (CEG, Inc.), and
FPL Group, Inc. (FPL Group), FPL Group will become a wholly owned
subsidiary of CEG, Inc. At the closing of the merger, the former
shareholders of FPL Group will own approximately 60% of the outstanding
stock of CEG, Inc., and the pre-merger shareholders of CEG, Inc., will
own the remaining approximately 40%. In addition, the CEG, Inc., board
of directors will be composed of fifteen members, nine of whom will be
named by FPL Group, and six of whom will be named by the current CEG,
Inc. CCNPP Inc. will continue to own and operate the facility and the
ISFSI and hold the licenses.
Approval of the indirect transfer of the facility operating
licenses and material license was requested by CGG LLC pursuant to 10
CFR 50.80 and 10 CFR 72.50. Notice of the request for approval and an
opportunity for a hearing was published in the Federal Register on
February 22, 2006 (71 FR 9168). Comments and a petition to intervene
were received from the Maryland Office of the People's Counsel.
However, the petition to intervene was dismissed by the Secretary of
the Commission by order dated March 17, 2006.
Under 10 CFR 50.80 and 10 CFR 72.50, no license, or any right
thereunder, shall be transferred, directly or indirectly, through
transfer of control of the license, unless the Commission shall give
its consent in writing. Upon review of the information in the
application by CGG LLC and other information before the Commission, the
NRC staff concludes that the proposed merger and resulting indirect
transfer of control of the licenses will not affect the qualifications
of CCNPP Inc. as a holder of the CCNPP and CCISFSI licenses, and that
the indirect transfer of control of the licenses as held by CCNPP Inc.,
is otherwise consistent with the applicable provisions of law,
regulations, and orders issued by the Commission pursuant thereto.
The findings set forth above are supported by a safety evaluation
dated August 3, 2006.
III.
Accordingly, pursuant to Sections 161b, 161i, and 184 of the Atomic
Energy Act of 1954, as amended (the Act), 42 U.S.C. 2201(b), 2201(i),
and 2234; and 10 CFR 50.80 and 10 CFR 72.50, it is hereby ordered that
the application regarding the proposed merger and indirect license
transfer is approved, subject to the following condition:
Should the proposed merger not be completed within one year from
the date of issuance, this Order shall become null and void,
provided, however, upon written application and good cause shown,
such date may in writing be extended.
This Order is effective upon issuance.
For further details with respect to this Order, see the initial
application dated January 23, 2006, as supplemented by letters dated
April 25 and May 25, 2006, and the safety evaluation dated August 3,
2006, which are available for public inspection at the Commission's
Public Document Room (PDR), located at One White Flint North, Public
File Area 01 F21, 11555 Rockville Pike (first floor), Rockville,
Maryland and accessible electronically from the Agencywide Documents
Access and Management System (ADAMS) Public Electronic Reading Room on
the Internet at the NRC Web site, http://www.nrc.gov/reading-rm/adams.html. Persons who do not have access to ADAMS or who encounter
problems in accessing the documents located in ADAMS, should contact
the NRC PDR Reference staff by telephone at 1-800-397-4209, 301-415-
4737, or by e-mail to [email protected].
Dated at Rockville, Maryland this 3rd day of August 2006.
For the Nuclear Regulatory Commission.
Catherine Haney,
Director, Division of Operating Reactor Licensing, Office of Nuclear
Reactor Regulation.
[FR Doc. E6-12924 Filed 8-8-06; 8:45 am]