[Federal Register Volume 71, Number 97 (Friday, May 19, 2006)]
[Notices]
[Pages 29148-29149]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: E6-7663]


-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

[ER-FRL-6675-3]


Environmental Impacts Statements; Notice of Availability

    Responsible Agency: Office of Federal Activities, General 
Information (202) 564-7167 or http://www.epa.gov/compliance/nepa/.

Weekly receipt of Environmental Impact Statements
Filed May 8, 2006 Through May 12, 2006.
Pursuant to 40 CFR 1506.9.

EIS No. 20060178, Draft EIS, WPA, 00, Big Stone II Power Plant and 
Transmission Project, Propose Power Plant, Transmission Alternatives, 
and Substation Modification, (DOE/EIS-0377), U.S. Army COE Section 10 
and 404 Permits, Big Stone City, Grant County, SD and MN, Comment 
Period Ends: July 3, 2006, Contact: Nancy Werdel 720-962-7251.

EIS No. 20060179, Final EIS, AFS, WY, Moose-Gypsum Project, Proposes to 
Authorize Vegetation Treatments, Watershed Improvements, and Travel 
Plan and Recreation Updates, Pinedale Ranger District, Bridger-Teton 
National Forest, Sublette County, WY, Wait Period Ends: June 19, 2006, 
Contact: Craig Trulock 307-367-4326.

EIS No. 20060180, Final EIS, AFS, IN, Tell City Windthrow 2004 Project, 
Salvage Harvest and Prescribed Burning of Windthrow Timber, 
Implementation, Hoosier National Forest, Perry, Crawford and Dubois 
Counties, IN, Wait Period Ends: June 19, 2006, Contact: Ron Ellis 812-
275-5987.

EIS No. 20060181, Draft EIS, BLM, 00, Devers-Palo Verde No. 2 
Transmission Line Project, Construction and Operation a New 230-mile 
500 kV Electric Transmission Line between Devers Substation in 
California and Harquahala Generating Substation in Arizona, Comment 
Period Ends: July 5, 2006, Contact: Greg Hill 760-251-4840.

EIS No. 20060182, Draft EIS, COE, CA, San Clemente Dam Seismic Safety 
Project, Increase Dam Safety to Meet Current Design Standards, Monterey 
County, CA, Comment Period Ends: July 3, 2006, Contact: Robert Smith 
415-977-8450.

EIS No. 20060183, Final EIS, FAA, UT, St. George Municipal Airport 
Replacement, Funding, City of St. George, Washington County, UT, Wait 
Period Ends: June 19, 2006, Contact: T.J. Stetz 425-227-2611.

EIS No. 20060184, Draft EIS, COE, MD, Masonville Dredge Material 
Containment Facility (DMCF), Construction from Baltimore Harbor Channel 
north of Point-Rock Point Line, U.S. Army COE Section 10 and 404 
Permits, Baltimore, MD, Comment Period Ends: July 7, 2006, Contact: Jon 
Romeo 410-962-6079.

EIS No. 20060185, Final EIS, AFS, MI, Hiawatha National Forest, 
Proposed Land and Resource Management Plan, Forest Plan Revision, 
Implementation, Alger, Cheboygan, Chippewa, Delta, Luce, Mackinac, 
Marquette and Schoolcraft Counties, MI, Wait Period Ends: June 19, 
2006, Contact: Dave Maercklein 906-789-3301.

EIS No. 20060186, Final Supplement, TPT, CA, Presidio Trust Public 
Health Service Hospital (PUSH or Building 1801) at the Presidio of San 
Francisco (Area B) of Presidio Trust Management Plan, Rehabilitation 
and Reuse of Buildings, Gold Gate National Recreation Area, San 
Francisco Bay, Marin County, CA, Wait Period Ends: June 19, 2006, 
Contact: John G. Pelka 415-561-5300.

EIS No. 20060187, Draft EIS, AFS, WI, Long Rail Vegetation and 
Transportation Management Project, Implementation, Eagle River-Florence 
Ranger District, Chequamegon-Nicolet National Forest, Florence and 
Forest Counties, WI, Comment Period Ends: July 3, 2006, Contact: 
Christine Brunner 715-479-2827.

EIS No. 20060188, Draft EIS, NOA, CA, Channel Islands National Marine 
Sanctuary Management Plan Review, Implementation, Santa Barbara and 
Ventura Counties, CA, Comment Period Ends: July 21, 2006, Contact: 
Chris Mobley 805-966-7107 x465.

EIS No. 20060189, Final EIS, NRC, OH, American Centrifuge Plant, Gas 
Centrifuge Uranium Enrichment Facility, Construction, Operation, and 
Decommission, License Issuance, Piketon, OH, Wait Period Ends: June 19, 
2006, Contact: Matthew Blevins 301-415-7684.

EIS No. 20060190, Final EIS, AFS, MI, Ottawa National Forest, Proposed 
Land and Resource Management Plan, Forest Plan Revision, 
Implementation, Baraga, Gogebic, Houghton, Iron, Marquette and 
Ontonagan Counties, MI, Wait Period Ends: June 19, 2006, Contact: 
Robert Brenner 906-931-1330 x317.

EIS No. 20060191, Final EIS, FAA, FL, Panama City-Bay County 
International Airport (PFN), Proposed Relocation to a New Site, NPDES 
Permit and U.S. Army COE Section 404 Permit, Bay County, FL, Wait 
Period Ends: June 19, 2006, Contact: Virginia Lane 407-872-6331 Ext. 
129.

EIS No. 20060192, Draft EIS, AFS, ID, Myrtle Creek Healthy Forest 
Restoration Act Project, Proposes Aquatic and Vegetation Improvement 
Treatments, Panhandle National Forests, Bonners Ferry Ranger District, 
City of Bonners Ferry, Boundary County, ID, Comment Period Ends: July 
3, 2006, Contact: Doug Nishek 208-267-5561.

EIS No. 20060193, Final EIS, AFS, UT, Ogden Ranger District Travel 
Plan, To Update the Travel Management Plan, Wasatch-Cache National 
Plan, Ogden Ranger District, Box Elder, Cache, Morgan, Weber and Rich 
Counties, UT, Wait Period Ends: June 19, 2006, Contact: Rick Vallejos 
801-625-5112.


[[Page 29149]]


EIS No. 20060194, Draft EIS, AFS, 00, Kootenai National Forest Invasive 
Plant Management, Proposes to Manage Noxious Weed and Invasive Plant 
Species, Lincoln Sanders, Flathead Counties, MT and Bonner and Boundary 
Counties, ID, Comment Period Ends: July 3, 2006, Contact: Ellen 
Sullivan 406-296-7114.

EIS No. 20060195, Draft EIS, CGD, MA, Northeast Gateway Deepwater Port 
License Application, Construct, Own and Operate a Deepwater Port to 
Import Liquefied Natural Gas (LNG) in Massachusetts Bay, City of 
Gloucester, MA, Comment Period Ends: July 3, 2006, Contact: Mark 
Prescott 202-267-0225.

EIS No. 20060196, Final EIS, COE, FL, South Florida Water Management 
District, (SFWMD), Proposes Construction and Operation Everglades 
Agricultural Area Reservoir A-1 Project, Lake Okeechobee, Palm Beach 
County, FL, Wait Period Ends: June 19, 2006, Contact: Tori White 561-
742-8888.

Amended Notices

EIS No. 20060136, Draft EIS, AFS, AK, Kenai Winter Access Project, 
Develop a Winter Access Management Plan for 2006/2007 Winter Season, 
Implementation, Seward Ranger District, Chugach National Forest, 
Located on the Kenai Peninsula in Southcentral, AK, Comment Period 
Ends: June 12, 2006, Contact: Sharon Randall 907-743-9497.

    Revision to FR Notice Published April 21, 2006: Comment Period 
Extended from June 5, 2006 to June 12, 2006.

EIS No. 20060162, Draft EIS, FHW, 00, TIER 1--DEIS Trans-Texas 
Corridor--35 (TTC-35) System, Improvement to International, Interstate 
and Intrastate Movement of Goods and People, Oklahoma-Mexico/Gulf Coast 
Element, Comment Period Ends: August 21, 2006, Contact: Salvador 
Decampo 512-536-5950.

    Revision to FR Notice Published May 5, 2006: Comment Period 
Extended from June 19, 2006 to August 21, 2006.

    Dated: May 16, 2006.
Robert W. Hargrove,
Director, NEPA Compliance Division, Office of Federal Activities.
[FR Doc. E6-7663 Filed 5-18-06; 8:45 am]
BILLING CODE 6560-50-P