[Federal Register Volume 70, Number 123 (Tuesday, June 28, 2005)]
[Notices]
[Page 37124]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: E5-3341]



[[Page 37124]]

=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No 72-13]


Entergy Operations, Incorporated; Notice of Withdrawal of Request 
for Exemption for Arkansas Nuclear One, Unit 1 and Unit 2

AGENCY: Nuclear Regulatory Commission.

ACTION: Notice of withdrawal of the request for exemption from the 
requirements of 10 CFR 72.212(a)(2) and 10 CFR 72.214.

-----------------------------------------------------------------------

FOR FURTHER INFORMATION CONTACT: Christopher M. Regan, Senior Project 
Manager, Spent Fuel Project Office, Office of Nuclear Material Safety 
and Safeguards, U.S. Nuclear Regulatory Commission, Washington, DC 
20555. Telephone: (301) 415-1179; fax number: (301) 415-1179; e-mail: 
[email protected].

SUPPLEMENTARY INFORMATION:

I. Discussion

    In a letter dated June 9, 2005, to the U.S. Nuclear Regulatory 
Commission (NRC or Commission) Entergy Operations, Inc. (applicant or 
Entergy Operations) withdrew a request dated May 23, 2005, for 
exemption from the requirements of 10 CFR 72.212(a)(2) and 10 CFR 
72.214 pursuant to 10 CFR 72.7, for the Arkansas Nuclear One, Unit 1 
(ANO-1) and Unit 2 (ANO-2), facility located 6 miles west-northwest of 
Russellville, Arkansas. The staff has terminated its review of the 
request. The request was docketed under 10 CFR part 72; the Independent 
Spent Fuel Storage Installation Docket No. is 72-13.

II. Further Information

    In accordance with 10 CFR 2.390 of NRC's ``Rules of Practice,'' 
final NRC records and documents regarding this proposed action, 
including the exemption request dated May 23, 2005, and withdrawal 
dated June 9, 2005, are publically available in the records component 
of NRC's Agencywide Documents Access and Management System (ADAMS). 
These documents may be inspected at NRC's Public Electronic Reading 
Room at http://www.nrc.gov/reading-rm/adams.html. These documents may 
also be viewed electronically on the public computers located at the 
NRC's Public Document Room (PDR), O1F21, One White Flint North, 11555 
Rockville Pike, Rockville, MD 20852. The PDR reproduction contractor 
will copy documents for a fee. Persons who do not have access to ADAMS 
or who encounter problems in accessing the documents located in ADAMS, 
should contact the NRC PDR Reference staff by telephone at 1-800-397-
4209 or (301) 415-4737, or by e-mail to [email protected].

    Dated in Rockville, Maryland, this 20th day of June 2005.

    For the Nuclear Regulatory Commission.
Christopher M. Regan,
Senior Project Manager, Spent Fuel Project Office, Office of Nuclear 
Material Safety and Safeguards.
[FR Doc. E5-3341 Filed 6-27-05; 8:45 am]
BILLING CODE 7590-01-P