NCP of Virginia, LLC, et al.; Electric Rate and Corporate Filings

August 23, 2004.
    The following filings have been made with the Commission. The 
filings are listed in ascending order within each docket 
classification.

[[Page 53056]]

1. NCP of Virginia, LLC, TM Delmarva Power L.L.C.

[Docket No.: EC04-147-000]

    Take notice that on August 18, 2004, NCP of Virginia, LLC (NCP) and 
TM Delmarva Power L.L.C. (TMD) submitted an application pursuant to 
section 203 of the Federal Power Act for authorization of a disposition 
of jurisdictional facilities whereby TMD will purchase NCP's interest 
in Commonwealth Chesapeake Company, L.L.C. in exchange for a 
combination of cash and TECO Energy, Inc. common stock.
    Comment Date: 5 p.m. eastern standard time on September 8, 2004.

2. ANP Bellingham Energy Company, LLC, ANP Blackstone Energy Company, 
LLC, ANP Funding I, L.L.C., ANP Marketing Company, Hartwell Energy 
Limited Partnership, Milford Power Limited Partnership

[Docket No.: EC04-148-000]

    Take notice that on August 18, 2004, ANP Bellingham Energy Company, 
LLC (ANP Bellingham), ANP Blackstone Energy Company, LLC (ANP 
Blackstone), ANP Funding I, L.L.C. (ANP Funding), ANP Marketing Company 
(ANP Marketing), Hartwell Energy Limited Partnership (Hartwell), and 
Milford Power Limited Partnership (Milford) (jointly, Applicants) filed 
an application pursuant to section 203 of the Federal Power Act 
requesting authorization for an internal reorganization. Applicants 
requested expedited consideration of the application.
    Comment Date: 5 p.m. eastern standard time on September 8, 2004.

3. Vermont Electric Cooperative, Inc.

[Docket No.: EC04-149-000]

    Take notice that on August 19, 2004, Vermont Electric Cooperative, 
Inc. (VEC) filed with the Commission an application pursuant to section 
203 of the Federal Power Act for authorization to purchase certain 
shares of voting Class B Common Stock issued by the Vermont Electric 
Power Company, Inc. VEC states that approval of the stock issuance by 
the Vermont Public Service Board is pending. VEC requests that the 
Commission issue an order granting approval no later than September 17, 
2004.
    VEC states that the Vermont Public Service Board, the Vermont 
Department of Public Service, and VELCO were mailed copies of the 
filing.
    Comment Date: 5 p.m. eastern standard time on September 9, 2004.

4. PSEG Power In-City I, LLC Complainant, v. Consolidated Edison Co. of 
New York, Inc. Respondent.

[Docket No.: EL04-126-000]

    Take notice that on August 23, 2004, PSEG Power In-City I, LLC (In-
City) filed a complaint under section 206 of the Federal Power Act, 16 
U.S.C. 824e (1994), and section 206 of the Commission's Rules of 
Practice and Procedure, 18 CFR 206 (2003), against Consolidated Edison 
Co. of New York, Inc. (ConEd) requesting that the Commission extend by 
18 months the Interconnection Date of In-City's Interconnection 
Agreement with ConEd.
    Comment Date: 5 p.m. eastern standard time on September 13, 2004.

5. Duke Power, a Division of Duke Energy Corporation

[Docket No.: ER96-110-011]

    Take notice that, on August 17, 2004, Duke Power, a division of 
Duke Energy Corporation, submitted an errata to its August 11, 2004 
compliance filing in Docket No. ER96-110-010.
    Duke Power states that copies of the filing were served on parties 
on the official service list in the above-captioned proceeding, the 
North Carolina Utilities Commission and the South Carolina Public 
Service Commission.
    Comment Date: 5 p.m. eastern standard time on September 7, 2004.

6. Constellation Power Source, Inc.

[Docket No.: ER97-2261-017]

    Take notice that on August 16, 2004, Constellation Power Source, 
Inc. (CPS), submitted a notice of change in status under CPS' market-
based rate authority, pursuant to Section 205 of the Federal Power Act 
and the Federal Energy Regulatory Commission's order in Constellation 
Power Source, Inc., 79 FERC ] 61,167 (1997).
    CPS states that copies of the filing were served upon parties on 
the official service list in the above-captioned proceeding.
    Comment Date: 5 p.m. eastern standard time on September 7, 2004.

7. Consolidated Edison Energy, Inc.

[Docket No.: ER00-865-002]

    Take notice that on August 18, 2004, Consolidated Edison Energy, 
Inc., (CEE) submitted an amendment to its Tariff for the Wholesale Sale 
of Electricity at Market-Based Rates to include the Market Behavior 
Rules promulgated by the Commission, Investigation of Terms and 
Conditions of Public Utility Market-Based Rate Authorizations, 105 FERC 
] 61,218 (2003), and to correct the inadvertent omission from the 
tariff of CEE's authority to make sales of ancillary services at 
market-based rates to the ISO New England, PJM Interconnection ISO, and 
New York ISO.
    CEE states that it is serving this filing on all parties to the 
subject docket and on the New York Public Service Commission.
    Comment Date: 5 p.m. eastern standard time on September 8, 2004.

8. ISO New England Inc .

[Docket No.: ER02-2153-008]

    Take notice that on August 16, 2004, ISO New England Inc. (ISO) 
submitted a report in compliance with the Commission's order issued 
July 31, 2004 in Docket No. ER02-2153-000.
    ISO states that copies of the filing have been served upon all 
parties to this proceeding and the New England utility regulatory 
agencies, and electronically upon the New England Power Pool 
participants.
    Comment Date: 5 p.m. eastern standard time on September 7, 2004.

9. ONEOK Energy Marketing and Trading Company, L.P.

[Docket No.: ER03-10-002]

    Take notice that on August 17, 2004, ONEOK Energy Marketing and 
Trading Company, L.P. (OEMT), formerly known as ONEOK Power Marketing 
Company, submitted a report regarding its triennial updated market 
analysis.
    Comment Date: 5 p.m. eastern standard time on September 7, 2004.

10. Southern California Edison Company

[Docket No.: ER04-757-001]

    Take notice that on August 18, 2004, Southern California Edison 
Company (SCE) submitted a revised Amended and Restated Edison-AEPCO 
Firm Transmission Service Agreement and a revised Amended and Restated 
Edison-AEPCO Load Control Agreement between SCE and the Arizona 
Electric Power Cooperative, Inc. (AEPCO), and the Southwest 
Transmission Cooperative, Inc. (SWTC). SEC requests an effective date 
of June 1, 2004.
    SCE states that copies of the filing were served upon those persons 
whose names appear on the official service list compiled by the 
Commission for this proceeding, the Public Utilities Commission of the 
State of California, AEPCO and SWTC.
    Comment Date: 5 p.m. eastern standard time on September 8, 2004.

11. ISO New England Inc.

[Docket No.: ER04-798-002]

    Take notice that on August 16, 2004, ISO New England Inc. (ISO) 
submitted

[[Page 53057]]

 Substitute Sheet No. 51-A to New England Power Pool's FERC Electric 
Rate Schedule No. 7 in compliance with the Commission's order issued 
July 15, 2004 in Docket No. ER04-798-000. 108 FERC ] 61,069.
    Comment Date: 5 p.m. eastern standard time on September 7, 2004.

12. Union Electric Company

[Docket No.: ER04-931-001]

    Take notice that on August 16, 2004, Union Electric Company, d/b/a 
AmerenUE, (Union) submitted for filing a corrected version of their 
June 15, 2004 filing of an unexecuted Contract between United States of 
America, represented by the Secretary of Energy, acting by and through 
the Administrator, Southwestern Power Administration and Union Electric 
Company, d/b/a AmerenUE (the parties). Union states that the purpose of 
this filing is to correct typographical errors in the June 15, 2004 
document.
    Union states that copies of the Application have been served on the 
Missouri Public Service Commission and the Southwestern Power 
Administration.
    Comment Date: 5 p.m. eastern standard time on September 7, 2004.

13. The Detroit Edison Company, DTE East China, LLC, DTE River Rouge 
No. 1, LLC

[Docket No.: ER04-948-001]

    Take notice that on August 16, 2004, DTE East China, LLC and DTE 
River Rouge No. 1, LLC (Applicants) submitted a compliance filing 
pursuant to a Commission's order issued July 16, 2004 in Docket No. 
ER04-948-000, 108 FERC ] 61,070.
    Applicants state that copies of the filing were served on parties 
on the official service list in the above-captioned proceeding.
    Comment Date: 5 p.m. eastern standard time on September 7, 2004.

14. The Dayton Power and Light Company

[Docket No.: ER04-1079-001]

    Take notice that on August 19, 2004, The Dayton Power and Light 
Company (Dayton) filed a supplement to its Notice of Cancellation of 
its Open Access Transmission Tariff (OATT) filing made on July 30, 
2004.
    Dayton states that copies of the filing were served on Dayton's 
OATT customers, the Ohio state commission, and those on the service 
list in the above-captioned docket.
    Comment Date: 5 p.m. eastern standard time on September 9, 2004.

15. PPL University Park, LLC

[Docket No.: ER04-1111-001]

    Take notice that on August 13, 2004 University Park, LLC (PPL 
University Park) amended its filing submitted on August 11, 2004 in 
Docket No. ER04-1111-000.
    PPL University Park states that copies of the filing were served 
upon PJM Interconnection, L.L.C., New York Independent System Operator, 
Inc. and ISO New England, Inc.
    Comment Date: 5 p.m. eastern standard time on September 3, 2004.

16. Starlight Energy, L.P.

[Docket No.: ER04-1131-000]

    Take notice that on August 16, 2004, Starlight Energy, L.P., 
(Starlight) petitioned the Commission for acceptance of Starlight's 
Rate Schedule FERC No. 1; the granting of certain blanket approvals, 
including the authority to sell electricity at market-based rates; and 
the waiver of certain Commission regulations. Starlight states that it 
intends to engage in wholesale electric power and energy purchases and 
sales as a marketer.
    Comment Date: 5 p.m. eastern standard time on September 7, 2004.

17. PJM Transmission Owners Agreement Administrative Committee

[Docket No.: ER04-1132-000]

    Take notice that on August 16, 2004 the PJM Transmission Owners 
Agreement Administrative Committee (TOA-AC) tendered for filing Second 
Revised Sheet No. 14 to PJM Interconnection, L.L.C.'s First Revised 
Rate Schedule FERC No. 29, an amendment to the PJM Transmission Owners 
Agreement. TOA-AC states that the amendment requires that the senior 
representative to the TOA-AC for each transmission owner be an officer 
of the transmission owner. TOA-AC requests an effective date of August 
17, 2004.
    TOA-AC states that copies of the filing were served upon PJM 
Interconnection, L.L.C., the representatives of the TOA-AC, and the 
relevant State Commissions.
    Comment Date: 5 p.m. eastern standard time on September 7, 2004.

18. Southern California Edison Company

[Docket No.: ER04-1133-000]

    Take notice that on August 16, 2004 Southern California Edison 
Company (SCE) submitted for filing a Notice of Cancellation of Service 
Agreement Nos. 79 and 82 under SCE's FERC Electric Tariff, First 
Revised Volume No. 5, to be effective December 5, 2003 and May 18, 
2004, respectively.
    SCE states that a copy of the filing has been served upon the 
Public Utilities Commission of the State of California, and Whitewater 
Hill Wind Partners, LLC.
    Comment Date: 5 p.m. eastern standard time on September 7, 2004.

19. Consolidated Edison Solutions, Inc.

[Docket No.: ER04-1134-000]

    Take notice that on August 17, 2004, Consolidated Edison Solutions, 
Inc. (ConEdison Solutions) filed a Notice of Cancellation of Inventory 
Management and Distribution Company, Inc.'s (IMD), FERC Rate Schedule 
No. 1, to terminate IMD's market-based rate authority effective 
February 27, 2001.
    Comment Date: 5 p.m. eastern standard time on September 7, 2004.

20. Wisconsin Power and Light Company

[Docket No.: ER04-1135-000]

    Take notice that on August 17, 2004, Wisconsin Power and Light 
Company (WPL) tendered for filing proposed changes in its FERC Electric 
Service Tariff--W-2A, W-3A, W-4A, and PR-1 (Volume Nos. 1 and 2). WPL 
states that the proposed changes would increase revenues from 
jurisdictional sales and service by $12.2 million based on the 12-month 
period ending December 31, 2005. In addition, WPL proposes to extend 
the applicability of its fuel adjustment clause to its FERC Electric 
Service Tariff--W-2A. WPL requests that proposed rates in this 
proceeding go into effect under bond on January 1, 2005.
    WPL states that copies of the filing were served upon WPL's 
jurisdictional customers, their representatives and the Public Service 
Commission of Wisconsin.
    Comment Date: 5 p.m. eastern standard time on September 7, 2004.

21. Huntington Beach Development, LLC

[Docket No.: ER04-1136-000]

    Take notice that, on August 17, 2004, Huntington Beach Development, 
LLC (HBD) filed a Notice of Cancellation of its FERC Electric Rate 
Schedule No. 1. HBD requests an effective date of July 18, 2004.
    Comment Date: 5 p.m. eastern standard time on September 7, 2004.

22. MeadWestvaco Energy Services, LLC

[Docket No.: ER04-1137-000]

    Take notice that on August 18, 2004, MeadWestvaco Energy Services, 
LLC, (MWES) filed a petition for acceptance of MWES's Rate Schedule 
FERC No. 1;

[[Page 53058]]

the granting of certain blanket approvals, including the authority to 
sell electricity at market-based rates; and the waiver of certain 
Commission regulations. MWES states that it intends to engage in 
wholesale electric power and energy purchases and sales as a marketer.
    Comment Date: 5 p.m. eastern standard time on September 8, 2004.

23. New York Independent System Operator, Inc.

[Docket No.: ER04-1138-000]

    Take notice that on August 18, 2004, the New York Independent 
System Operator, Inc. (NYISO) filed proposed revisions to its Market 
Administration and Control Area Services Tariff (Services Tariff) and 
Open Access Transmission Tariff to revise the exception from special 
balancing rules for certain generators. In addition, NYISO proposed to 
revise its Services Tariff to eliminate penalty exemptions for certain 
generators and to revise an accepted but not yet effective provision to 
extend bid-cost protections for certain generators.
    NYISO states that it has electronically served a copy of this 
filing on the official representative of each of its customers, on each 
participant in its stakeholder committees, and on the New York Public 
Service Commission. In addition, the NYISO has served a copy of this 
filing on the electric utility regulatory agencies of New Jersey and 
Pennsylvania.
    Comment Date: 5 p.m. eastern standard time on September 8, 2004.

24. Pacific Gas and Electric Company

[Docket No.: ER04-1139-000]

    Take notice that on August 19, 2004, Pacific Gas and Electric 
Company (PG&E) tendered for filing an amendment to the Interconnection 
Agreement (IA) between PG&E and the Port of Oakland (Port) to include 
the Davis Substation at Transmission Voltage as a Point of 
Interconnection. PG&E states that the IA is submitted pursuant to the 
PG&E Wholesale Distribution Tariff (WDT). PG&E requests an effective 
date of January 5, 2005.
    PG&E states that copies of this filing have been served upon Port, 
the California Independent System Operator Corporation, Western Area 
Power Administration and the California Public Utilities Commission.
    Comment Date: 5 p.m. eastern standard time on September 9, 2004.

25. New England Power Pool

[Docket No.: ER04-1140-000]

    Take notice that on August 20, 2004, New England Power Pool, 
(NEPOOL) Participants Committee filed changes to NEPOOL's Market Rule 1 
and its Appendices. NEPOOL Participants Committee requests an effective 
date of November 1, 2004.
    NEPOOL Participants Committee states that copies of these materials 
were sent to the New England state governors and regulatory commissions 
and the Participants in NEPOOL.
    Comment Date: 5 p.m. eastern standard time on September 10, 2004.

Standard Paragraph

    Any person desiring to intervene or to protest this filing must 
file in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be 
considered by the Commission in determining the appropriate action to 
be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a notice of 
intervention or motion to intervene, as appropriate. Such notices, 
motions, or protests must be filed on or before the comment date. 
Anyone filing a motion to intervene or protest must serve a copy of 
that document on the Applicant. On or before the comment date, it is 
not necessary to serve motions to intervene or protests on persons 
other than the Applicant.
    The Commission encourages electronic submission of protests and 
interventions in lieu of paper using the ``eFiling'' link at http://www.ferc.gov. Persons unable to file electronically should submit an 
original and 14 copies of the protest or intervention to the Federal 
Energy Regulatory Commission, 888 First Street, NE., Washington, DC 
20426.
    This filing is accessible on-line at http://www.ferc.gov, using the 
``eLibrary'' link and is available for review in the Commission's 
Public Reference Room in Washington, DC. There is an ``eSubscription'' 
link on the Web site that enables subscribers to receive e-mail 
notification when a document is added to a subscribed docket(s). For 
assistance with any FERC Online service, please e-mail 
[email protected], or call (866) 208-3676 (toll free). For 
TTY, call (202) 502-8659.

Magalie R. Salas,
Secretary.
 [FR Doc. E4-1980 Filed 8-30-04; 8:45 am]
BILLING CODE 6717-01-P