[Federal Register Volume 69, Number 168 (Tuesday, August 31, 2004)]
[Notices]
[Pages 53055-53058]
From the Federal Register Online via the Government Publishing Office [www.gpo.gov]
[FR Doc No: E4-1980]
=======================================================================
-----------------------------------------------------------------------
DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission
[Docket No. EC04-147-000, et al.]
NCP of Virginia, LLC, et al.; Electric Rate and Corporate Filings
August 23, 2004.
The following filings have been made with the Commission. The
filings are listed in ascending order within each docket
classification.
[[Page 53056]]
1. NCP of Virginia, LLC, TM Delmarva Power L.L.C.
[Docket No.: EC04-147-000]
Take notice that on August 18, 2004, NCP of Virginia, LLC (NCP) and
TM Delmarva Power L.L.C. (TMD) submitted an application pursuant to
section 203 of the Federal Power Act for authorization of a disposition
of jurisdictional facilities whereby TMD will purchase NCP's interest
in Commonwealth Chesapeake Company, L.L.C. in exchange for a
combination of cash and TECO Energy, Inc. common stock.
Comment Date: 5 p.m. eastern standard time on September 8, 2004.
2. ANP Bellingham Energy Company, LLC, ANP Blackstone Energy Company,
LLC, ANP Funding I, L.L.C., ANP Marketing Company, Hartwell Energy
Limited Partnership, Milford Power Limited Partnership
[Docket No.: EC04-148-000]
Take notice that on August 18, 2004, ANP Bellingham Energy Company,
LLC (ANP Bellingham), ANP Blackstone Energy Company, LLC (ANP
Blackstone), ANP Funding I, L.L.C. (ANP Funding), ANP Marketing Company
(ANP Marketing), Hartwell Energy Limited Partnership (Hartwell), and
Milford Power Limited Partnership (Milford) (jointly, Applicants) filed
an application pursuant to section 203 of the Federal Power Act
requesting authorization for an internal reorganization. Applicants
requested expedited consideration of the application.
Comment Date: 5 p.m. eastern standard time on September 8, 2004.
3. Vermont Electric Cooperative, Inc.
[Docket No.: EC04-149-000]
Take notice that on August 19, 2004, Vermont Electric Cooperative,
Inc. (VEC) filed with the Commission an application pursuant to section
203 of the Federal Power Act for authorization to purchase certain
shares of voting Class B Common Stock issued by the Vermont Electric
Power Company, Inc. VEC states that approval of the stock issuance by
the Vermont Public Service Board is pending. VEC requests that the
Commission issue an order granting approval no later than September 17,
2004.
VEC states that the Vermont Public Service Board, the Vermont
Department of Public Service, and VELCO were mailed copies of the
filing.
Comment Date: 5 p.m. eastern standard time on September 9, 2004.
4. PSEG Power In-City I, LLC Complainant, v. Consolidated Edison Co. of
New York, Inc. Respondent.
[Docket No.: EL04-126-000]
Take notice that on August 23, 2004, PSEG Power In-City I, LLC (In-
City) filed a complaint under section 206 of the Federal Power Act, 16
U.S.C. 824e (1994), and section 206 of the Commission's Rules of
Practice and Procedure, 18 CFR 206 (2003), against Consolidated Edison
Co. of New York, Inc. (ConEd) requesting that the Commission extend by
18 months the Interconnection Date of In-City's Interconnection
Agreement with ConEd.
Comment Date: 5 p.m. eastern standard time on September 13, 2004.
5. Duke Power, a Division of Duke Energy Corporation
[Docket No.: ER96-110-011]
Take notice that, on August 17, 2004, Duke Power, a division of
Duke Energy Corporation, submitted an errata to its August 11, 2004
compliance filing in Docket No. ER96-110-010.
Duke Power states that copies of the filing were served on parties
on the official service list in the above-captioned proceeding, the
North Carolina Utilities Commission and the South Carolina Public
Service Commission.
Comment Date: 5 p.m. eastern standard time on September 7, 2004.
6. Constellation Power Source, Inc.
[Docket No.: ER97-2261-017]
Take notice that on August 16, 2004, Constellation Power Source,
Inc. (CPS), submitted a notice of change in status under CPS' market-
based rate authority, pursuant to Section 205 of the Federal Power Act
and the Federal Energy Regulatory Commission's order in Constellation
Power Source, Inc., 79 FERC ] 61,167 (1997).
CPS states that copies of the filing were served upon parties on
the official service list in the above-captioned proceeding.
Comment Date: 5 p.m. eastern standard time on September 7, 2004.
7. Consolidated Edison Energy, Inc.
[Docket No.: ER00-865-002]
Take notice that on August 18, 2004, Consolidated Edison Energy,
Inc., (CEE) submitted an amendment to its Tariff for the Wholesale Sale
of Electricity at Market-Based Rates to include the Market Behavior
Rules promulgated by the Commission, Investigation of Terms and
Conditions of Public Utility Market-Based Rate Authorizations, 105 FERC
] 61,218 (2003), and to correct the inadvertent omission from the
tariff of CEE's authority to make sales of ancillary services at
market-based rates to the ISO New England, PJM Interconnection ISO, and
New York ISO.
CEE states that it is serving this filing on all parties to the
subject docket and on the New York Public Service Commission.
Comment Date: 5 p.m. eastern standard time on September 8, 2004.
8. ISO New England Inc .
[Docket No.: ER02-2153-008]
Take notice that on August 16, 2004, ISO New England Inc. (ISO)
submitted a report in compliance with the Commission's order issued
July 31, 2004 in Docket No. ER02-2153-000.
ISO states that copies of the filing have been served upon all
parties to this proceeding and the New England utility regulatory
agencies, and electronically upon the New England Power Pool
participants.
Comment Date: 5 p.m. eastern standard time on September 7, 2004.
9. ONEOK Energy Marketing and Trading Company, L.P.
[Docket No.: ER03-10-002]
Take notice that on August 17, 2004, ONEOK Energy Marketing and
Trading Company, L.P. (OEMT), formerly known as ONEOK Power Marketing
Company, submitted a report regarding its triennial updated market
analysis.
Comment Date: 5 p.m. eastern standard time on September 7, 2004.
10. Southern California Edison Company
[Docket No.: ER04-757-001]
Take notice that on August 18, 2004, Southern California Edison
Company (SCE) submitted a revised Amended and Restated Edison-AEPCO
Firm Transmission Service Agreement and a revised Amended and Restated
Edison-AEPCO Load Control Agreement between SCE and the Arizona
Electric Power Cooperative, Inc. (AEPCO), and the Southwest
Transmission Cooperative, Inc. (SWTC). SEC requests an effective date
of June 1, 2004.
SCE states that copies of the filing were served upon those persons
whose names appear on the official service list compiled by the
Commission for this proceeding, the Public Utilities Commission of the
State of California, AEPCO and SWTC.
Comment Date: 5 p.m. eastern standard time on September 8, 2004.
11. ISO New England Inc.
[Docket No.: ER04-798-002]
Take notice that on August 16, 2004, ISO New England Inc. (ISO)
submitted
[[Page 53057]]
Substitute Sheet No. 51-A to New England Power Pool's FERC Electric
Rate Schedule No. 7 in compliance with the Commission's order issued
July 15, 2004 in Docket No. ER04-798-000. 108 FERC ] 61,069.
Comment Date: 5 p.m. eastern standard time on September 7, 2004.
12. Union Electric Company
[Docket No.: ER04-931-001]
Take notice that on August 16, 2004, Union Electric Company, d/b/a
AmerenUE, (Union) submitted for filing a corrected version of their
June 15, 2004 filing of an unexecuted Contract between United States of
America, represented by the Secretary of Energy, acting by and through
the Administrator, Southwestern Power Administration and Union Electric
Company, d/b/a AmerenUE (the parties). Union states that the purpose of
this filing is to correct typographical errors in the June 15, 2004
document.
Union states that copies of the Application have been served on the
Missouri Public Service Commission and the Southwestern Power
Administration.
Comment Date: 5 p.m. eastern standard time on September 7, 2004.
13. The Detroit Edison Company, DTE East China, LLC, DTE River Rouge
No. 1, LLC
[Docket No.: ER04-948-001]
Take notice that on August 16, 2004, DTE East China, LLC and DTE
River Rouge No. 1, LLC (Applicants) submitted a compliance filing
pursuant to a Commission's order issued July 16, 2004 in Docket No.
ER04-948-000, 108 FERC ] 61,070.
Applicants state that copies of the filing were served on parties
on the official service list in the above-captioned proceeding.
Comment Date: 5 p.m. eastern standard time on September 7, 2004.
14. The Dayton Power and Light Company
[Docket No.: ER04-1079-001]
Take notice that on August 19, 2004, The Dayton Power and Light
Company (Dayton) filed a supplement to its Notice of Cancellation of
its Open Access Transmission Tariff (OATT) filing made on July 30,
2004.
Dayton states that copies of the filing were served on Dayton's
OATT customers, the Ohio state commission, and those on the service
list in the above-captioned docket.
Comment Date: 5 p.m. eastern standard time on September 9, 2004.
15. PPL University Park, LLC
[Docket No.: ER04-1111-001]
Take notice that on August 13, 2004 University Park, LLC (PPL
University Park) amended its filing submitted on August 11, 2004 in
Docket No. ER04-1111-000.
PPL University Park states that copies of the filing were served
upon PJM Interconnection, L.L.C., New York Independent System Operator,
Inc. and ISO New England, Inc.
Comment Date: 5 p.m. eastern standard time on September 3, 2004.
16. Starlight Energy, L.P.
[Docket No.: ER04-1131-000]
Take notice that on August 16, 2004, Starlight Energy, L.P.,
(Starlight) petitioned the Commission for acceptance of Starlight's
Rate Schedule FERC No. 1; the granting of certain blanket approvals,
including the authority to sell electricity at market-based rates; and
the waiver of certain Commission regulations. Starlight states that it
intends to engage in wholesale electric power and energy purchases and
sales as a marketer.
Comment Date: 5 p.m. eastern standard time on September 7, 2004.
17. PJM Transmission Owners Agreement Administrative Committee
[Docket No.: ER04-1132-000]
Take notice that on August 16, 2004 the PJM Transmission Owners
Agreement Administrative Committee (TOA-AC) tendered for filing Second
Revised Sheet No. 14 to PJM Interconnection, L.L.C.'s First Revised
Rate Schedule FERC No. 29, an amendment to the PJM Transmission Owners
Agreement. TOA-AC states that the amendment requires that the senior
representative to the TOA-AC for each transmission owner be an officer
of the transmission owner. TOA-AC requests an effective date of August
17, 2004.
TOA-AC states that copies of the filing were served upon PJM
Interconnection, L.L.C., the representatives of the TOA-AC, and the
relevant State Commissions.
Comment Date: 5 p.m. eastern standard time on September 7, 2004.
18. Southern California Edison Company
[Docket No.: ER04-1133-000]
Take notice that on August 16, 2004 Southern California Edison
Company (SCE) submitted for filing a Notice of Cancellation of Service
Agreement Nos. 79 and 82 under SCE's FERC Electric Tariff, First
Revised Volume No. 5, to be effective December 5, 2003 and May 18,
2004, respectively.
SCE states that a copy of the filing has been served upon the
Public Utilities Commission of the State of California, and Whitewater
Hill Wind Partners, LLC.
Comment Date: 5 p.m. eastern standard time on September 7, 2004.
19. Consolidated Edison Solutions, Inc.
[Docket No.: ER04-1134-000]
Take notice that on August 17, 2004, Consolidated Edison Solutions,
Inc. (ConEdison Solutions) filed a Notice of Cancellation of Inventory
Management and Distribution Company, Inc.'s (IMD), FERC Rate Schedule
No. 1, to terminate IMD's market-based rate authority effective
February 27, 2001.
Comment Date: 5 p.m. eastern standard time on September 7, 2004.
20. Wisconsin Power and Light Company
[Docket No.: ER04-1135-000]
Take notice that on August 17, 2004, Wisconsin Power and Light
Company (WPL) tendered for filing proposed changes in its FERC Electric
Service Tariff--W-2A, W-3A, W-4A, and PR-1 (Volume Nos. 1 and 2). WPL
states that the proposed changes would increase revenues from
jurisdictional sales and service by $12.2 million based on the 12-month
period ending December 31, 2005. In addition, WPL proposes to extend
the applicability of its fuel adjustment clause to its FERC Electric
Service Tariff--W-2A. WPL requests that proposed rates in this
proceeding go into effect under bond on January 1, 2005.
WPL states that copies of the filing were served upon WPL's
jurisdictional customers, their representatives and the Public Service
Commission of Wisconsin.
Comment Date: 5 p.m. eastern standard time on September 7, 2004.
21. Huntington Beach Development, LLC
[Docket No.: ER04-1136-000]
Take notice that, on August 17, 2004, Huntington Beach Development,
LLC (HBD) filed a Notice of Cancellation of its FERC Electric Rate
Schedule No. 1. HBD requests an effective date of July 18, 2004.
Comment Date: 5 p.m. eastern standard time on September 7, 2004.
22. MeadWestvaco Energy Services, LLC
[Docket No.: ER04-1137-000]
Take notice that on August 18, 2004, MeadWestvaco Energy Services,
LLC, (MWES) filed a petition for acceptance of MWES's Rate Schedule
FERC No. 1;
[[Page 53058]]
the granting of certain blanket approvals, including the authority to
sell electricity at market-based rates; and the waiver of certain
Commission regulations. MWES states that it intends to engage in
wholesale electric power and energy purchases and sales as a marketer.
Comment Date: 5 p.m. eastern standard time on September 8, 2004.
23. New York Independent System Operator, Inc.
[Docket No.: ER04-1138-000]
Take notice that on August 18, 2004, the New York Independent
System Operator, Inc. (NYISO) filed proposed revisions to its Market
Administration and Control Area Services Tariff (Services Tariff) and
Open Access Transmission Tariff to revise the exception from special
balancing rules for certain generators. In addition, NYISO proposed to
revise its Services Tariff to eliminate penalty exemptions for certain
generators and to revise an accepted but not yet effective provision to
extend bid-cost protections for certain generators.
NYISO states that it has electronically served a copy of this
filing on the official representative of each of its customers, on each
participant in its stakeholder committees, and on the New York Public
Service Commission. In addition, the NYISO has served a copy of this
filing on the electric utility regulatory agencies of New Jersey and
Pennsylvania.
Comment Date: 5 p.m. eastern standard time on September 8, 2004.
24. Pacific Gas and Electric Company
[Docket No.: ER04-1139-000]
Take notice that on August 19, 2004, Pacific Gas and Electric
Company (PG&E) tendered for filing an amendment to the Interconnection
Agreement (IA) between PG&E and the Port of Oakland (Port) to include
the Davis Substation at Transmission Voltage as a Point of
Interconnection. PG&E states that the IA is submitted pursuant to the
PG&E Wholesale Distribution Tariff (WDT). PG&E requests an effective
date of January 5, 2005.
PG&E states that copies of this filing have been served upon Port,
the California Independent System Operator Corporation, Western Area
Power Administration and the California Public Utilities Commission.
Comment Date: 5 p.m. eastern standard time on September 9, 2004.
25. New England Power Pool
[Docket No.: ER04-1140-000]
Take notice that on August 20, 2004, New England Power Pool,
(NEPOOL) Participants Committee filed changes to NEPOOL's Market Rule 1
and its Appendices. NEPOOL Participants Committee requests an effective
date of November 1, 2004.
NEPOOL Participants Committee states that copies of these materials
were sent to the New England state governors and regulatory commissions
and the Participants in NEPOOL.
Comment Date: 5 p.m. eastern standard time on September 10, 2004.
Standard Paragraph
Any person desiring to intervene or to protest this filing must
file in accordance with Rules 211 and 214 of the Commission's Rules of
Practice and Procedure (18 CFR 385.211 and 385.214). Protests will be
considered by the Commission in determining the appropriate action to
be taken, but will not serve to make protestants parties to the
proceeding. Any person wishing to become a party must file a notice of
intervention or motion to intervene, as appropriate. Such notices,
motions, or protests must be filed on or before the comment date.
Anyone filing a motion to intervene or protest must serve a copy of
that document on the Applicant. On or before the comment date, it is
not necessary to serve motions to intervene or protests on persons
other than the Applicant.
The Commission encourages electronic submission of protests and
interventions in lieu of paper using the ``eFiling'' link at http://www.ferc.gov. Persons unable to file electronically should submit an
original and 14 copies of the protest or intervention to the Federal
Energy Regulatory Commission, 888 First Street, NE., Washington, DC
20426.
This filing is accessible on-line at http://www.ferc.gov, using the
``eLibrary'' link and is available for review in the Commission's
Public Reference Room in Washington, DC. There is an ``eSubscription''
link on the Web site that enables subscribers to receive e-mail
notification when a document is added to a subscribed docket(s). For
assistance with any FERC Online service, please e-mail
[email protected], or call (866) 208-3676 (toll free). For
TTY, call (202) 502-8659.
Magalie R. Salas,
Secretary.
[FR Doc. E4-1980 Filed 8-30-04; 8:45 am]
BILLING CODE 6717-01-P