NUCLEAR REGULATORY COMMISSION
Notice of Clarification to Steam Generator Tube Integrity Event
Reporting Guideline in NUREG-1022, ``Event Reporting Guidelines 10 CFR
50.72 and 50.73''
AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of clarification in reporting guideline for steam
generator tube integrity event.
-----------------------------------------------------------------------
SUMMARY: The U.S. Nuclear Regulatory Commission plans to make a
clarification in the reporting guideline for serious steam generator
tube degradation contained within Revision 2 to NUREG-1022, ``Event
Reporting Guidelines 10 CFR 50.72 and 50.73.'' The NRC intends to issue
an errata to NUREG-1022, Revision 2. The purpose of this clarification
is to ensure that the NRC receives timely notification of serious steam
generator tube degradation.
SUPPLEMENTARY INFORMATION: In NUREG-1022, Revision 2, ``Event Reporting
Guidelines 10 CFR 50.72 and 50.73,'' steam generator tube degradation
is characterized in Section 3.2.4(A)(3) as being seriously degraded if
the tubing fails to meet the following two performance criteria: (A)
Steam generator tubing shall retain structural integrity over the full
range of normal operating conditions (including startup, operation in
the power range, hot standby, and cooldown and all anticipated
transients included in the design specification) and design basis
accidents. This includes retaining a margin of 3.0 against burst under
normal steady state full power operation and a margin of 1.4 against
burst under the limiting design basis accident concurrent with a safe
shutdown earthquake. (B) The primary to secondary accident induced
leakage rate for the limiting design basis accident, other than a steam
generator tube rupture, shall not exceed the leakage rate assumed in
the accident analysis in terms of total leakage rate for all steam
generators and leakage rate for an individual steam generator. The
licensing basis accident analyses typically assume a 1 gallon per
minute primary to secondary leak rate per steam generator, except for
specific types of degradation at specific locations where the tubes are
confined, as approved by the NRC and enumerated in conjunction with the
list of approved repair criteria in the licensee's design basis
documents. The first performance criteria is commonly referred to as
the structural integrity performance criteria and the second criteria
is commonly referred to as the accident induced leakage performance
criteria. As written, NUREG-1022, Revision 2 implies that the principal
safety barrier (i.e., the steam generator tubes in this case) would not
be considered seriously degraded if it had either structural or leakage
integrity. This is contradictory to existing NRC regulations which
require, in part, that the reactor coolant pressure boundary (which
includes the steam generator tubes) be designed to permit periodic
inspection and testing of important areas and features to assess both
their structural and leak-tight integrity (refer to General Design
Criterion 32 of Appendix A to 10 CFR part 50) and be designed and
tested so as to have an extremely low probability of abnormal leakage,
of rapidly propagating failure, and of gross rupture (refer to General
Design Criterion 14 of Appendix A to 10 CFR part 50). The regulations,
therefore, indicate that both structural and leakage integrity criteria
must be satisfied and not meeting either one of the two performance
criteria should constitute serious degradation of the principal safety
barrier. Accordingly, steam generator tube degradation should be
considered serious if either of the two criteria specified in Section
3.2.4(A)(3) of NUREG-1022, Revision 2, are not satisfied.
The intended clarification involves changing the wording in Section
3.2.4(A)(3) of NUREG-1022, Revision 2 (page 39) from ``Steam generator
tube degradation is considered serious if the tubing fails to meet the
following two performance criteria'' to ``Steam generator tube
degradation is considered serious if the tubing fails to meet either of
the following two performance criteria.''
The NRC will consider any comments it receives pertaining to this
intended change in NUREG-1022, Revision 2.
DATES: Comment period expires March 19, 2004. Comments submitted after
this date will be considered if it is practical to do so, but assurance
of consideration cannot be given except for comments received on or
before this date.
ADDRESSES: Submit written comments to the Chief, Rules and Directives
Branch, Division of Administrative Services, Office of Administration,
U.S. Nuclear Regulatory Commission, Mail Stop T6-D59, Washington, DC
20555-0001, and cite the publication date and page number of this
Federal Register notice. Written comments may also be delivered to NRC
Headquarters, 11545 Rockville Pike (Room T6-D59), Rockville, Maryland,
between 7:30 a.m. and 4:15 p.m. on Federal workdays.
FOR FURTHER INFORMATION, CONTACT: Samuel Lee at (301) 415-1061 or by E-
mail to [email protected], or Ken Karwoski at (301) 415-2752 or by e-mail to
[email protected].
Dated at Rockville, Maryland, this 10th day of February, 2004.
For the Nuclear Regulatory Commission.
William D. Beckner,
Chief, Reactor Operations Branch, Division of Inspection Program
Management, Office of Nuclear Reactor Regulation.
[FR Doc. 04-3441 Filed 2-17-04; 8:45 am]