DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP03-327-000]


Southern Natural Gas Company; Notice of Request Under Blanket 
Authorization

June 27, 2003.
    Take notice that on June 20, 2003, Southern Natural Gas Company 
(Southern), P.O. Box 2563, Birmingham, Alabama, filed a request 
pursuant to Sections 157.205, 157.208(b)(2) and 157.211(a)(2) of the 
Federal Energy Regulatory Commission*s (Commission) Regulations under 
the Natural Gas Act (NGA), as amended, and blanket certificate 
authority granted September 1, 1982, in Docket No. CP82-406-000, 20 
FERC ] 62,414 for authorization to construct and operate a new delivery 
point to Tamko Roofing Products, Inc. (Tamko) in Tuscaloosa County, 
Alabama, all as more fully set forth in the request, which is on file 
with the Commission, and open for public inspection. This filing is 
available for review at the Commission or may be viewed on the 
Commission's Web site at http://www.ferc.gov, using the ``FERRIS'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, please 
contact FERC Online Support at [email protected] or toll-free 
at (866) 208-3676 or for TTY, contact (202) 502-8659.
    Southern proposes to construct and operate certain measurement and 
other appurtenant facilities to provide up to 1,800 Mcf/day of 
transportation service for Tamko, under Southern's Rate Schedule IT. 
Service to the Tamko Plant will be provided at a new delivery point to 
be located at approximately Mile Post 20.625 on Southern's 12-inch 
Montgomery-Columbus Line in Tuscaloosa County, Alabama. Southern and 
Tamko have complied with all of the requirements under Section 36 of 
the General Terms and Conditions of Southern's FERC Gas Tariff, 7th 
Revised Volume No. 1 for the installation of the direct delivery 
connection by Southern. Tamko will reimburse Southern for the estimated 
$235,100 cost of constructing and installing the proposed facilities 
pursuant to an executed Construction and Reimbursement Agreement dated 
May 30, 2003.
    Southern states that the installation of the proposed facilities 
will have no adverse effect on its ability to provide its firm 
deliveries. Any questions regarding this filing should be directed to 
John Griffin, Senior Counsel, Southern Natural Gas Company, P.O. Box 
2563, Birmingham, Alabama 35202-2563 or call 205-325-7133.
    Any person or the Commission's staff may, within 45 day after 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and pursuant to section 157.205 of 
the Regulations under the NGA (18 CFR 157.205), a protest to the 
request. If no protest is filed within the time allowed therefor, the 
proposed activity shall be deemed to be authorized effective the day 
after the time allowed for filing a protest. If a protest is filed and 
not withdrawn within 30 days after the time allowed for filing a 
protest, the instant request shall be treated as an application for 
authorization pursuant to Section 7 of the NGA. Comments, protests and 
interventions may be filed electronically via the Internet in lieu of 
paper; see 18 CFR 385.2001(a)(1)(iii) and the instructions on the 
Commission's Web site under the ``e-Filing'' link. The Commission 
strongly encourages electronic filings.

Magalie R. Salas,
Secretary.
[FR Doc. 03-16852 Filed 7-2-03; 8:45 am]
BILLING CODE 6717-01-P